17214 W KILLION ST 91316
Certificate Information: 17214 W KILLION ST 91316
- Application / Permit
- 22010-10000-05219
- Plan Check / Job No.
- B22LA21472
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN (N) 2-story Detached ADU per ordinance 1200 sqft
- Permit Issued
- Issued on 5/10/2024
- Issuing Office
- Current Status
- Issued on 5/10/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 10/25/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 11/9/2022 | JAD BASMA |
| Corrections Issued | 11/16/2022 | JAD BASMA |
| Quality Review Completed | 11/29/2022 | TEODORO DIAZ RODRIGUEZ |
| Plan Check Approved | 5/9/2024 | JAD BASMA |
| Issued | 5/10/2024 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 11/30/2022 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 12/5/2022 | CARLOS AGUILERA |
| Sewer availability | Cleared | 12/5/2022 | CARLOS AGUILERA |
| Low Impact Development | Cleared | 6/9/2023 | MELINEH AGHAKHABIAN |
| Construction near power lines | Cleared | 1/22/2024 | RIDWAN HARDY |
| Roof/Waste drainage to street | Cleared | 4/25/2024 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JON MCHUGH, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
| IVAN SARABIA, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 10/30/2024 | Partial Inspection | JON MCHUGH |
| Underground Mechanical | 11/15/2024 | Partial Approval | JON MCHUGH |
| Footing/Foundation/Slab | 11/20/2024 | Approved | JON MCHUGH |
| Floor/Roof Diaphrgm/Shear Wall | 11/27/2024 | Partial Approval | JON MCHUGH |
| Floor/Roof Diaphrgm/Shear Wall | 12/10/2024 | Partial Approval | JON MCHUGH |
| Special/Order Compliance | 12/10/2024 | Corrections Issued | JON MCHUGH |
| BUILDING-Rough-Frame | 1/22/2025 | Corrections Issued | JON MCHUGH |
| ELECTRICAL-Rough | 1/22/2025 | Approved | JON MCHUGH |
| Floor/Roof Diaphrgm/Shear Wall | 1/22/2025 | Approved | JON MCHUGH |
| HVAC-Rough | 1/22/2025 | Approved | JON MCHUGH |
| MERV13>=Rough | 1/22/2025 | Approved | JON MCHUGH |
| PLUMBING-Rough | 1/22/2025 | Approved | JON MCHUGH |
| Special/Order Compliance | 1/22/2025 | Partial Approval | SCOTT SOBEL |
| Verify Sprinkler Sign Off | 1/22/2025 | Approved | JON MCHUGH |
| Deputy Wood Construction | 1/24/2025 | Conditional Approval | MORRIS JACKSON |
| BUILDING-Rough-Frame | 2/26/2025 | Approved | JON MCHUGH |
| Insulation | 2/26/2025 | Conditional Approval | JON MCHUGH |
| Interior/Exterior Lathing | 2/26/2025 | Corrections Issued | JON MCHUGH |
| Drywall Nailing | 3/10/2025 | Approved | JON MCHUGH |
| Interior/Exterior Lathing | 3/10/2025 | Partial Approval | JON MCHUGH |
| Interior/Exterior Lathing | 3/24/2025 | Not Ready for Inspection | MORRIS JACKSON |
| Shower Pan | 3/24/2025 | Approved | MORRIS JACKSON |
| Interior/Exterior Lathing | 3/27/2025 | Approved | JON MCHUGH |
| Underground Mechanical | 6/16/2025 | Partial Approval | JOHN COLEMAN |
| Underground Mechanical | 7/7/2025 | Approved | MORRIS JACKSON |
| Final | 5/7/2026 | Corrections Issued | JON MCHUGH |
| MERV13>=Final | 5/7/2026 | Approved | JON MCHUGH |
| SGSOV-Seismic Gas S/O Valve | 5/7/2026 | SGSOV Approved | JON MCHUGH |
| Service/Power Release | 5/7/2026 | Not Ready for Inspection | JON MCHUGH |
| Smoke Detectors | 5/7/2026 | Approved | JON MCHUGH |
| Final | 6/4/2026 | Not Ready for Inspection | JON MCHUGH |
| Service/Power Release | 6/4/2026 | Not Ready for Inspection | JON MCHUGH |