1512 N MURCHISON ST 90033
Certificate Information: 1512 N MURCHISON ST 90033
- Application / Permit
- 22010-10000-05198
- Plan Check / Job No.
- B22LA18526
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- EPLAN. NEW 3-STORY SFD WITH ATTACHED 2-CAR GARAGE
- Permit Issued
- Issued on 11/13/2023
- Issuing Office
- Current Status
- CofO Issued on 6/21/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/12/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 10/13/2022 | MAHNAZ NOURHASHEMI |
| Corrections Issued | 10/24/2022 | MAHNAZ NOURHASHEMI |
| Quality Review Completed | 11/2/2022 | TEODORO DIAZ RODRIGUEZ |
| Applicant returned to address corrections | 10/25/2023 | MAHNAZ NOURHASHEMI |
| Plan Check Approved | 11/8/2023 | MAHNAZ NOURHASHEMI |
| Issued | 11/13/2023 | APPLICANT |
| CofO in Progress | 6/17/2025 | ALIZAH MAYAGOITIA |
| Permit Finaled | 6/21/2025 | DEROLD HAUFF |
| Permit Finaled | 6/21/2025 | DEROLD HAUFF |
| CofO Issued | 6/21/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Hydrant and Access approval | Cleared | 12/4/2022 | JOHN CONNEALLY |
| Address approval | Cleared | 12/13/2022 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 12/20/2022 | WALLIE JONG |
| Trees in Parkway | Cleared | 1/5/2023 | ADALBERTO VERA |
| Permit | Cleared | 1/9/2023 | WALLIE JONG |
| Sewer availability | Cleared | 2/23/2023 | WALLIE JONG |
| Low Impact Development | Cleared | 6/14/2023 | LUIS LUVANO |
| Roof/Waste drainage to street | Cleared | 6/14/2023 | WALLIE JONG |
| GPI Written Notices | Cleared | 10/25/2023 | MAHNAZ NOURHASHEMI |
| Grading Pre-Inspection | Cleared | 10/25/2023 | MAHNAZ NOURHASHEMI |
| SB8 RUD | Cleared | 10/26/2023 | LOUIE MILLER |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Salto,, Alvaro; Lic. No.: C83859 | 2543 E NORMAN AVE WEST COVINA, CA 91791 |
Inspector Information
| OSVALDO PARAMO, (213) 202-9854 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 4/4/2024 | Not Ready for Inspection | OSVALDO PARAMO |
| Underground Mechanical | 4/4/2024 | Partial Approval | OSVALDO PARAMO |
| Footing/Foundation/Slab | 4/10/2024 | Partial Inspection | OSVALDO PARAMO |
| Excavation/Setback/Form/Re-Bar | 4/11/2024 | Approved | OSVALDO PARAMO |
| Floor/Roof Diaphrgm/Shear Wall | 4/26/2024 | Partial Approval | OSVALDO PARAMO |
| Wood Frame | 5/7/2024 | Partial Approval | OSVALDO PARAMO |
| ELECTRICAL-Rough | 6/13/2024 | Not Ready for Inspection | OSVALDO PARAMO |
| HVAC-Rough | 6/13/2024 | Approved | OSVALDO PARAMO |
| PLUMBING-Rough | 6/13/2024 | Not Ready for Inspection | OSVALDO PARAMO |
| Floor/Roof Diaphrgm/Shear Wall | 6/14/2024 | Approved | OSVALDO PARAMO |
| ELECTRICAL-Rough | 6/18/2024 | Corrections Issued | OSVALDO PARAMO |
| ELECTRICAL-Rough | 6/20/2024 | Approved | OSVALDO PARAMO |
| PLUMBING-Rough | 6/20/2024 | Corrections Issued | OSVALDO PARAMO |
| PLUMBING-Rough | 6/26/2024 | Conditional Approval | OSVALDO PARAMO |
| BUILDING-Rough-Frame | 7/2/2024 | Conditional Approval | OSVALDO PARAMO |
| Green Building Rough | 7/2/2024 | Approved | OSVALDO PARAMO |
| PLUMBING-Rough | 7/2/2024 | Approved | OSVALDO PARAMO |
| Verify Sprinkler Sign Off | 7/2/2024 | Approved | OSVALDO PARAMO |
| Interior/Exterior Lathing | 7/5/2024 | Partial Approval | OSVALDO PARAMO |
| Insulation | 7/24/2024 | Approved | OSVALDO PARAMO |
| Interior/Exterior Lathing | 7/24/2024 | Partial Approval | OSVALDO PARAMO |
| Drywall Nailing | 8/8/2024 | Approved | OSVALDO PARAMO |
| Shower Pan | 8/29/2024 | Approved | OSVALDO PARAMO |
| Interior/Exterior Lathing | 9/6/2024 | Approved | ALEX COLIN |
| Gas Test | 1/15/2025 | Partial Approval | ALIZAH MAYAGOITIA |
| PLUMBING-Rough | 1/15/2025 | Approved | ALIZAH MAYAGOITIA |
| Sewer | 1/15/2025 | Approved | ALIZAH MAYAGOITIA |
| Underground Mechanical | 1/15/2025 | Approved | ALIZAH MAYAGOITIA |
| BUILDING-Rough-Frame | 3/11/2025 | Approved | ALIZAH MAYAGOITIA |
| ELECTRICAL-Final | 3/11/2025 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Final | 3/11/2025 | Corrections Issued | ALIZAH MAYAGOITIA |
| Footing/Foundation/Slab | 3/11/2025 | Approved | ALIZAH MAYAGOITIA |
| Green Building Final | 3/11/2025 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| HVAC-Final | 3/11/2025 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| PLUMBING-Final | 3/11/2025 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| SGSOV-Seismic Gas S/O Valve | 3/11/2025 | SGSOV Not Ready | ALIZAH MAYAGOITIA |
| Service/Power Release | 3/11/2025 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Smoke Detectors | 3/11/2025 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| ELECTRICAL-Final | 3/13/2025 | Corrections Issued | ALIZAH MAYAGOITIA |
| PLUMBING-Final | 3/13/2025 | Approved | ALIZAH MAYAGOITIA |
| Gas Test | 3/17/2025 | Approved | BRENDAN MORELLI |
| HVAC-Final | 3/17/2025 | Corrections Issued | BRENDAN MORELLI |
| ELECTRICAL-Final | 4/3/2025 | Approved | ALIZAH MAYAGOITIA |
| HVAC-Final | 4/3/2025 | Partial Approval | ALIZAH MAYAGOITIA |
| Final | 5/21/2025 | Corrections Issued | ALIZAH MAYAGOITIA |
| Green Building Final | 5/21/2025 | Approved | ALIZAH MAYAGOITIA |
| SGSOV-Seismic Gas S/O Valve | 5/21/2025 | SGSOV Approved | ALIZAH MAYAGOITIA |
| Service/Power Release | 5/21/2025 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Smoke Detectors | 5/21/2025 | Approved | ALIZAH MAYAGOITIA |
| Final | 6/16/2025 | OK to Issue CofO | ALIZAH MAYAGOITIA |
| Service/Power Release | 6/16/2025 | Approved | ALIZAH MAYAGOITIA |