1175 W BROWNING BLVD 1-2 90037
Certificate Information: 1175 W BROWNING BLVD 1-2 90037
- Application / Permit
- 22010-10000-05195
- Plan Check / Job No.
- B22LA20828
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- NEW DUPLEX (3-STORY) LOCATED AT REAR OF LOT
- Permit Issued
- Issued on 8/5/2024
- Issuing Office
- Current Status
- Issued on 8/5/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 10/16/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 10/20/2022 | CARLOS MONTES |
| Corrections Issued | 10/23/2022 | CARLOS MONTES |
| Quality Review Completed | 10/25/2022 | GARO TELMI |
| Applicant returned to address corrections | 8/7/2023 | CARLOS MONTES |
| Applicant returned to address corrections | 11/2/2023 | CARLOS MONTES |
| Applicant returned to address corrections | 3/21/2024 | CARLOS MONTES |
| Applicant returned to address corrections | 5/3/2024 | CARLOS MONTES |
| Plan Check Approved | 5/15/2024 | CARLOS MONTES |
| Issued | 8/5/2024 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 11/3/2022 | WALLIE JONG |
| Highway dedication | Cleared | 11/3/2022 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 11/4/2022 | WALLIE JONG |
| Hydrant and Access approval | Cleared | 11/26/2022 | JOHN CONNEALLY |
| ZI | Cleared | 10/17/2023 | JAZMIN ROQUE |
| Low Impact Development | Cleared | 2/27/2024 | LUIS CRUZ |
| Roof/Waste drainage to street | Cleared | 2/29/2024 | DAVID LOPEZ |
| Sewer availability | Cleared | 3/11/2024 | DAVID LOPEZ |
Contact Information
| Contractor | Kgk Construction Inc; Lic. No.: 1092143-B | , |
| Engineer | Smith,, Melvin Bruce; Lic. No.: GE2673 | 2165 N MARVEL AVE SIMI VALLEY, CA 93065 |
| Engineer | Standley,, Craig Erick; Lic. No.: C87675 | 60 VIA CARATAMA SAN CLEMENTE, CA 92673 |
Inspector Information
| SABAS ALONSO, (213) 202-3468 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 8/7/2024 | Partial Approval | SABAS ALONSO |
| Underground Mechanical | 8/7/2024 | Partial Approval | SABAS ALONSO |
| Excavation/Setback/Form/Re-Bar | 8/13/2024 | Not Ready for Inspection | CRAIG DAVIS |
| Footing/Foundation/Slab | 8/13/2024 | Not Ready for Inspection | CRAIG DAVIS |
| Excavation/Setback/Form/Re-Bar | 8/15/2024 | Approved | CRAIG DAVIS |
| Floor/Roof Diaphrgm/Shear Wall | 9/3/2024 | Partial Approval | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 9/12/2024 | Not Ready for Inspection | CRAIG DAVIS |
| Floor/Roof Diaphrgm/Shear Wall | 9/18/2024 | Partial Approval | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 10/8/2024 | Corrections Issued | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 10/22/2024 | Partial Approval | SABAS ALONSO |
| ELECTRICAL-Rough | 11/18/2024 | Approved | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 11/18/2024 | Conditional Approval | SABAS ALONSO |
| HVAC-Rough | 11/18/2024 | Corrections Issued | SABAS ALONSO |
| PLUMBING-Rough | 11/27/2024 | Corrections Issued | SABAS ALONSO |
| Verify Sprinkler Sign Off | 11/27/2024 | Approved | SABAS ALONSO |
| HVAC-Rough | 12/18/2024 | No Access for Inspection | SABAS ALONSO |
| PLUMBING-Rough | 12/18/2024 | No Access for Inspection | SABAS ALONSO |
| Wood Frame | 12/18/2024 | No Access for Inspection | SABAS ALONSO |
| ELECTRICAL-Rough | 1/3/2025 | Approved | SABAS ALONSO |
| Green Building Rough | 1/3/2025 | Corrections Issued | SABAS ALONSO |
| HVAC-Rough | 1/3/2025 | Approved | SABAS ALONSO |
| Interior/Exterior Lathing | 1/3/2025 | Not Ready for Inspection | SABAS ALONSO |
| PLUMBING-Rough | 1/3/2025 | Approved | SABAS ALONSO |
| Green Building Rough | 1/14/2025 | Not Ready for Inspection | SABAS ALONSO |
| Interior/Exterior Lathing | 1/14/2025 | Not Ready for Inspection | SABAS ALONSO |
| BUILDING-Rough-Frame | 1/16/2025 | Corrections Issued | SABAS ALONSO |
| Green Building Rough | 1/16/2025 | Approved | SABAS ALONSO |
| Interior/Exterior Lathing | 1/16/2025 | Partial Approval | SABAS ALONSO |
| BUILDING-Rough-Frame | 1/21/2025 | Not Ready for Inspection | SABAS ALONSO |
| Insulation | 1/24/2025 | Not Ready for Inspection | ALEX COLIN |
| Insulation | 1/28/2025 | Corrections Issued | SABAS ALONSO |
| BUILDING-Rough-Frame | 1/30/2025 | Approved | SABAS ALONSO |
| Insulation | 1/30/2025 | Not Ready for Inspection | SABAS ALONSO |
| Insulation | 1/31/2025 | Approved | ALEX COLIN |
| Shower Pan | 1/31/2025 | Approved | ALEX COLIN |
| Insulation | 2/3/2025 | Approved | ANTHONY RAMOS |
| Drywall Nailing | 2/14/2025 | Approved | ANTHONY RAMOS |
| Interior/Exterior Lathing | 2/25/2025 | Not Ready for Inspection | SABAS ALONSO |
| Interior/Exterior Lathing | 3/3/2025 | Not Ready for Inspection | SABAS ALONSO |
| Interior/Exterior Lathing | 3/10/2025 | Approved | SABAS ALONSO |
| Sewer | 7/2/2025 | Approved | RONNIE MEDINA |
| Underground Mechanical | 7/2/2025 | Approved | RONNIE MEDINA |
| ELECTRICAL-Final | 6/11/2026 | Approved | SABAS ALONSO |
| Final | 6/11/2026 | Corrections Issued | SABAS ALONSO |
| HVAC-Final | 6/11/2026 | Approved | SABAS ALONSO |
| PLUMBING-Final | 6/11/2026 | Approved | SABAS ALONSO |
| Smoke Detectors | 6/11/2026 | Approved | SABAS ALONSO |