844 W 78TH ST 90044
Certificate Information: 844 W 78TH ST 90044
- Application / Permit
- 22010-10000-05192
- Plan Check / Job No.
- B22LA21004
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- eplan NEW 2-STORY S.F.D. (26' X 45.5') WITH ATTACHED 4 CAR GARAGE
- Permit Issued
- Issued on 6/19/2023
- Issuing Office
- Current Status
- CofO Issued on 2/5/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/18/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 10/20/2022 | NGHI SU |
| Corrections Issued | 10/22/2022 | NGHI SU |
| Quality Review Completed | 10/25/2022 | GARO TELMI |
| Applicant returned to address corrections | 4/13/2023 | NGHI SU |
| Plan Check Approved | 4/20/2023 | NGHI SU |
| Issued | 6/19/2023 | APPLICANT |
| CofO in Progress | 1/29/2024 | MICHAEL LEWIS |
| Permit Finaled | 2/5/2024 | DEROLD HAUFF |
| CofO Issued | 2/5/2024 | DEROLD HAUFF |
| Permit Finaled | 2/5/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Frnt yard landscape/Water mgmt | Cleared | 11/1/2022 | DANIEL CORONADO |
| Trees in Parkway | Cleared | 11/8/2022 | ADALBERTO VERA |
| Address approval | Cleared | 11/14/2022 | STEVE MELGAR |
| Permit | Cleared | 11/14/2022 | STEVE MELGAR |
| Eng Process Fee Ord 176,300 | Cleared | 11/15/2022 | STEVE MELGAR |
| Sewer availability | Cleared | 11/15/2022 | STEVE MELGAR |
| Hydrant and Access approval | Cleared | 11/26/2022 | JOHN CONNEALLY |
| Low Impact Development | Cleared | 12/1/2022 | CHRIS VONG |
| Roof/Waste drainage to street | Cleared | 12/7/2022 | STEVE MELGAR |
| SB8 RUD | Cleared | 4/5/2023 | MARITESS GO |
Contact Information
| Contractor | K N Consulting Inc; Lic. No.: 993102-B | P O BOX 410 SUNSET BEACH, CA 90742 |
| Engineer | Madero,, Fidencio; Lic. No.: C81695 | 10002 PANGBORN AVE DOWNEY, CA 90240 |
| Engineer | Madero,, Fidencio; Lic. No.: NA81695 | , |
Inspector Information
| JOHN QUINTANILLA, (213) 792-6055 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 7/24/2023 | Approved | MICHAEL LEWIS |
| Footing/Foundation/Slab | 7/24/2023 | Approved | MICHAEL LEWIS |
| Floor/Roof Diaphrgm/Shear Wall | 8/11/2023 | Partial Approval | MICHAEL LEWIS |
| Floor/Roof Diaphrgm/Shear Wall | 9/5/2023 | Approved | ALIZAH MAYAGOITIA |
| HVAC-Rough | 10/3/2023 | Approved | MICHAEL LEWIS |
| PLUMBING-Rough | 10/3/2023 | Approved | MICHAEL LEWIS |
| BUILDING-Rough-Frame | 10/4/2023 | Approved | MICHAEL LEWIS |
| ELECTRICAL-Rough | 10/4/2023 | Approved | MICHAEL LEWIS |
| Green Building Rough | 10/4/2023 | Approved | MICHAEL LEWIS |
| Verify Sprinkler Sign Off | 10/4/2023 | Approved | MICHAEL LEWIS |
| Insulation | 10/6/2023 | Approved | MICHAEL LEWIS |
| Drywall Nailing | 10/18/2023 | Approved | MICHAEL LEWIS |
| Interior/Exterior Lathing | 10/18/2023 | Approved | MICHAEL LEWIS |
| Sewer | 11/22/2023 | Approved | ALEJANDRO DE ARTOLA |
| Underground Mechanical | 11/22/2023 | Approved | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 12/12/2023 | Partial Approval | MICHAEL LEWIS |
| HVAC-Final | 1/23/2024 | Approved | MICHAEL LEWIS |
| PLUMBING-Final | 1/23/2024 | Approved | MICHAEL LEWIS |
| ELECTRICAL-Final | 1/24/2024 | Corrections Issued | MICHAEL LEWIS |
| Final | 1/24/2024 | Corrections Issued | MICHAEL LEWIS |
| Green Building Final | 1/24/2024 | Approved | MICHAEL LEWIS |
| SGSOV-Seismic Gas S/O Valve | 1/24/2024 | SGSOV Approved | MICHAEL LEWIS |
| Service/Power Release | 1/24/2024 | Approved | MICHAEL LEWIS |
| Smoke Detectors | 1/24/2024 | Approved | MICHAEL LEWIS |
| Final | 1/26/2024 | OK to Issue CofO | MICHAEL LEWIS |
| Service/Power Release | 1/26/2024 | Approved | MICHAEL LEWIS |