844 W 78TH ST 90044

Certificate Information: 844 W 78TH ST 90044

Application / Permit
22010-10000-05192
Plan Check / Job No.
B22LA21004
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
eplan NEW 2-STORY S.F.D. (26' X 45.5') WITH ATTACHED 4 CAR GARAGE
Permit Issued
Issued on 6/19/2023
Issuing Office
Current Status
CofO Issued on 2/5/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/18/2022 APPLICANT
Assigned to Plan Check Engineer 10/20/2022 NGHI SU
Corrections Issued 10/22/2022 NGHI SU
Quality Review Completed 10/25/2022 GARO TELMI
Applicant returned to address corrections 4/13/2023 NGHI SU
Plan Check Approved 4/20/2023 NGHI SU
Issued 6/19/2023 APPLICANT
CofO in Progress 1/29/2024 MICHAEL LEWIS
Permit Finaled 2/5/2024 DEROLD HAUFF
CofO Issued 2/5/2024 DEROLD HAUFF
Permit Finaled 2/5/2024 DEROLD HAUFF

Permit Application Clearance Information

Frnt yard landscape/Water mgmt Cleared 11/1/2022 DANIEL CORONADO
Trees in Parkway Cleared 11/8/2022 ADALBERTO VERA
Address approval Cleared 11/14/2022 STEVE MELGAR
Permit Cleared 11/14/2022 STEVE MELGAR
Eng Process Fee Ord 176,300 Cleared 11/15/2022 STEVE MELGAR
Sewer availability Cleared 11/15/2022 STEVE MELGAR
Hydrant and Access approval Cleared 11/26/2022 JOHN CONNEALLY
Low Impact Development Cleared 12/1/2022 CHRIS VONG
Roof/Waste drainage to street Cleared 12/7/2022 STEVE MELGAR
SB8 RUD Cleared 4/5/2023 MARITESS GO

Contact Information

Contractor K N Consulting Inc; Lic. No.: 993102-B P O BOX 410      SUNSET BEACH, CA 90742
Engineer Madero,, Fidencio; Lic. No.: C81695 10002 PANGBORN AVE      DOWNEY, CA 90240
Engineer Madero,, Fidencio; Lic. No.: NA81695       ,

Inspector Information

JOHN QUINTANILLA, (213) 792-6055 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 7/24/2023 Approved MICHAEL LEWIS
Footing/Foundation/Slab 7/24/2023 Approved MICHAEL LEWIS
Floor/Roof Diaphrgm/Shear Wall 8/11/2023 Partial Approval MICHAEL LEWIS
Floor/Roof Diaphrgm/Shear Wall 9/5/2023 Approved ALIZAH MAYAGOITIA
HVAC-Rough 10/3/2023 Approved MICHAEL LEWIS
PLUMBING-Rough 10/3/2023 Approved MICHAEL LEWIS
BUILDING-Rough-Frame 10/4/2023 Approved MICHAEL LEWIS
ELECTRICAL-Rough 10/4/2023 Approved MICHAEL LEWIS
Green Building Rough 10/4/2023 Approved MICHAEL LEWIS
Verify Sprinkler Sign Off 10/4/2023 Approved MICHAEL LEWIS
Insulation 10/6/2023 Approved MICHAEL LEWIS
Drywall Nailing 10/18/2023 Approved MICHAEL LEWIS
Interior/Exterior Lathing 10/18/2023 Approved MICHAEL LEWIS
Sewer 11/22/2023 Approved ALEJANDRO DE ARTOLA
Underground Mechanical 11/22/2023 Approved ALEJANDRO DE ARTOLA
ELECTRICAL-Final 12/12/2023 Partial Approval MICHAEL LEWIS
HVAC-Final 1/23/2024 Approved MICHAEL LEWIS
PLUMBING-Final 1/23/2024 Approved MICHAEL LEWIS
ELECTRICAL-Final 1/24/2024 Corrections Issued MICHAEL LEWIS
Final 1/24/2024 Corrections Issued MICHAEL LEWIS
Green Building Final 1/24/2024 Approved MICHAEL LEWIS
SGSOV-Seismic Gas S/O Valve 1/24/2024 SGSOV Approved MICHAEL LEWIS
Service/Power Release 1/24/2024 Approved MICHAEL LEWIS
Smoke Detectors 1/24/2024 Approved MICHAEL LEWIS
Final 1/26/2024 OK to Issue CofO MICHAEL LEWIS
Service/Power Release 1/26/2024 Approved MICHAEL LEWIS