5060 N RUBIO AVE 91436

Certificate Information: 5060 N RUBIO AVE 91436

Application / Permit
22010-10000-05183
Plan Check / Job No.
B22LA20922
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(N) DETACHED ADU PER LAMC 12.22 A 33(c) and (d) FIRE SPRINKLERED TTHROUGH OUT
Permit Issued
Issued on 3/3/2023
Issuing Office
Current Status
CofO Issued on 5/16/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/19/2022 APPLICANT
Assigned to Plan Check Engineer 10/20/2022 VARAND SARKISIAN
Corrections Issued 10/23/2022 VARAND SARKISIAN
Quality Review Completed 11/3/2022 HANS SANTIAGO
Plan Check Approved 2/28/2023 VARAND SARKISIAN
Issued 3/3/2023 APPLICANT
CofO in Progress 4/18/2024 VINCENT HANLEY
Permit Finaled 5/16/2024 JOHN JANSON
CofO Issued 5/16/2024 JOHN JANSON
Permit Finaled 5/16/2024 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 12/20/2022 LEE GUILBEAUX
Sewer availability Cleared 12/21/2022 LEE GUILBEAUX
Miscellaneous Cleared 12/29/2022 VARAND SARKISIAN
Eng Process Fee Ord 176,300 Cleared 1/23/2023 LEE GUILBEAUX
Low Impact Development Cleared 1/31/2023 ERNEST TSE
Roof/Waste drainage to street Cleared 2/1/2023 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,
Engineer Yuzon,, Benigno Sari; Lic. No.: S3454 2511 PEACHWOOD PLACE      WESTLAKE VILLAGE, CA 91361

Inspector Information

THOMAS FINNILA, (818) 774-4324 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 4/7/2023 Approved VINCENT HANLEY
Underground Mechanical 4/12/2023 Partial Approval VINCENT HANLEY
Excavation/Setback/Form/Re-Bar 4/27/2023 Approved VINCENT HANLEY
Footing/Foundation/Slab 4/27/2023 Approved VINCENT HANLEY
Deputy Reinf. Concrete 5/3/2023 Approved VINCENT HANLEY
Deputy Wood Construction 6/15/2023 Approved VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 6/21/2023 Partial Approval JOHN KIDWELL
PLUMBING-Rough 6/29/2023 Approved VINCENT HANLEY
Shower Pan 7/26/2023 Approved VINCENT HANLEY
ELECTRICAL-Rough 7/27/2023 Approved VINCENT HANLEY
HVAC-Rough 7/27/2023 Approved VINCENT HANLEY
Insulation 9/1/2023 Approved VINCENT HANLEY
Interior/Exterior Lathing 9/1/2023 Approved VINCENT HANLEY
Drywall Nailing 9/8/2023 Approved MORRIS JACKSON
ELECTRICAL-Final 1/18/2024 Approved VINCENT HANLEY
BUILDING-Rough-Frame 2/9/2024 Approved VINCENT HANLEY
Final 2/9/2024 Corrections Issued VINCENT HANLEY
Green Building Final 2/9/2024 Approved VINCENT HANLEY
Green Building Rough 2/9/2024 Approved VINCENT HANLEY
HVAC-Final 2/9/2024 Corrections Issued VINCENT HANLEY
MERV13>=Final 2/9/2024 Corrections Issued VINCENT HANLEY
MERV13>=Rough 2/9/2024 Approved VINCENT HANLEY
PLUMBING-Final 2/9/2024 Approved VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 2/9/2024 SGSOV Approved VINCENT HANLEY
Service/Power Release 2/9/2024 Approved VINCENT HANLEY
Smoke Detectors 2/9/2024 Approved VINCENT HANLEY
Verify Sprinkler Sign Off 2/9/2024 Approved VINCENT HANLEY
Final 4/12/2024 Corrections Issued VINCENT HANLEY
HVAC-Final 4/12/2024 Approved VINCENT HANLEY
MERV13>=Final 4/12/2024 Approved VINCENT HANLEY
Final 4/16/2024 OK to Issue CofO VINCENT HANLEY
Service/Power Release 4/16/2024 Approved VINCENT HANLEY