5060 N RUBIO AVE 91436
Certificate Information: 5060 N RUBIO AVE 91436
- Application / Permit
- 22010-10000-05183
- Plan Check / Job No.
- B22LA20922
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- (N) DETACHED ADU PER LAMC 12.22 A 33(c) and (d) FIRE SPRINKLERED TTHROUGH OUT
- Permit Issued
- Issued on 3/3/2023
- Issuing Office
- Current Status
- CofO Issued on 5/16/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/19/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 10/20/2022 | VARAND SARKISIAN |
| Corrections Issued | 10/23/2022 | VARAND SARKISIAN |
| Quality Review Completed | 11/3/2022 | HANS SANTIAGO |
| Plan Check Approved | 2/28/2023 | VARAND SARKISIAN |
| Issued | 3/3/2023 | APPLICANT |
| CofO in Progress | 4/18/2024 | VINCENT HANLEY |
| Permit Finaled | 5/16/2024 | JOHN JANSON |
| CofO Issued | 5/16/2024 | JOHN JANSON |
| Permit Finaled | 5/16/2024 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 12/20/2022 | LEE GUILBEAUX |
| Sewer availability | Cleared | 12/21/2022 | LEE GUILBEAUX |
| Miscellaneous | Cleared | 12/29/2022 | VARAND SARKISIAN |
| Eng Process Fee Ord 176,300 | Cleared | 1/23/2023 | LEE GUILBEAUX |
| Low Impact Development | Cleared | 1/31/2023 | ERNEST TSE |
| Roof/Waste drainage to street | Cleared | 2/1/2023 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Yuzon,, Benigno Sari; Lic. No.: S3454 | 2511 PEACHWOOD PLACE WESTLAKE VILLAGE, CA 91361 |
Inspector Information
| THOMAS FINNILA, (818) 774-4324 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/7/2023 | Approved | VINCENT HANLEY |
| Underground Mechanical | 4/12/2023 | Partial Approval | VINCENT HANLEY |
| Excavation/Setback/Form/Re-Bar | 4/27/2023 | Approved | VINCENT HANLEY |
| Footing/Foundation/Slab | 4/27/2023 | Approved | VINCENT HANLEY |
| Deputy Reinf. Concrete | 5/3/2023 | Approved | VINCENT HANLEY |
| Deputy Wood Construction | 6/15/2023 | Approved | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 6/21/2023 | Partial Approval | JOHN KIDWELL |
| PLUMBING-Rough | 6/29/2023 | Approved | VINCENT HANLEY |
| Shower Pan | 7/26/2023 | Approved | VINCENT HANLEY |
| ELECTRICAL-Rough | 7/27/2023 | Approved | VINCENT HANLEY |
| HVAC-Rough | 7/27/2023 | Approved | VINCENT HANLEY |
| Insulation | 9/1/2023 | Approved | VINCENT HANLEY |
| Interior/Exterior Lathing | 9/1/2023 | Approved | VINCENT HANLEY |
| Drywall Nailing | 9/8/2023 | Approved | MORRIS JACKSON |
| ELECTRICAL-Final | 1/18/2024 | Approved | VINCENT HANLEY |
| BUILDING-Rough-Frame | 2/9/2024 | Approved | VINCENT HANLEY |
| Final | 2/9/2024 | Corrections Issued | VINCENT HANLEY |
| Green Building Final | 2/9/2024 | Approved | VINCENT HANLEY |
| Green Building Rough | 2/9/2024 | Approved | VINCENT HANLEY |
| HVAC-Final | 2/9/2024 | Corrections Issued | VINCENT HANLEY |
| MERV13>=Final | 2/9/2024 | Corrections Issued | VINCENT HANLEY |
| MERV13>=Rough | 2/9/2024 | Approved | VINCENT HANLEY |
| PLUMBING-Final | 2/9/2024 | Approved | VINCENT HANLEY |
| SGSOV-Seismic Gas S/O Valve | 2/9/2024 | SGSOV Approved | VINCENT HANLEY |
| Service/Power Release | 2/9/2024 | Approved | VINCENT HANLEY |
| Smoke Detectors | 2/9/2024 | Approved | VINCENT HANLEY |
| Verify Sprinkler Sign Off | 2/9/2024 | Approved | VINCENT HANLEY |
| Final | 4/12/2024 | Corrections Issued | VINCENT HANLEY |
| HVAC-Final | 4/12/2024 | Approved | VINCENT HANLEY |
| MERV13>=Final | 4/12/2024 | Approved | VINCENT HANLEY |
| Final | 4/16/2024 | OK to Issue CofO | VINCENT HANLEY |
| Service/Power Release | 4/16/2024 | Approved | VINCENT HANLEY |