3870 N WEST POINT DR 90065
Certificate Information: 3870 N WEST POINT DR 90065
- Application / Permit
- 22010-10000-05140
- Plan Check / Job No.
- B22LA21133
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- #14010-10000-02299, NEW SINGLE FAMILY DWELLING ON HILLSIDE 3 STORY WITH ATTACHED 2-CAR GARAGE ON SLOPING LOT ON CONRETE PADS. IN MT. WASHINGTON-GLASEL PARK SPECIFIC PLAN. SEE COMMENT.
- Permit Issued
- Issued on 3/31/2023
- Issuing Office
- Current Status
- CofO Issued on 10/23/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/19/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 10/20/2022 | TSE MING HUANG |
| Corrections Issued | 10/26/2022 | TSE MING HUANG |
| Quality Review Completed | 10/26/2022 | KEN GILL |
| Building Plans Picked Up | 10/27/2022 | APPLICANT |
| Plan Check Approved | 3/29/2023 | TSE MING HUANG |
| Issued | 3/31/2023 | APPLICANT |
| CofO in Progress | 10/21/2025 | ALIZAH MAYAGOITIA |
| Permit Finaled | 10/23/2025 | DEROLD HAUFF |
| CofO Issued | 10/23/2025 | DEROLD HAUFF |
| Permit Finaled | 10/23/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 12/28/2022 | TSE MING HUANG |
| Hydrant and Access approval | Cleared | 1/18/2023 | ROBERT DUFF |
| Landscape for retaining wall | Cleared | 1/18/2023 | KENTON TRINH |
| Private street | Cleared | 1/18/2023 | KENTON TRINH |
| Specific Plan | Cleared | 1/18/2023 | KENTON TRINH |
| Low Impact Development | Cleared | 1/26/2023 | AMMAR ELTAWIL |
| BHO/Hillside ordinance | Cleared | 1/30/2023 | STEVE MELGAR |
| BHO/Hillside ordinance | Cleared | 1/30/2023 | STEVE MELGAR |
| BHO/Hillside ordinance | Cleared | 1/30/2023 | STEVE MELGAR |
| BHO/Hillside ordinance | Cleared | 1/30/2023 | STEVE MELGAR |
| Eng Process Fee Ord 176,300 | Cleared | 2/8/2023 | STEVE MELGAR |
| BHO/Hillside ordinance | Cleared | 2/15/2023 | JEANIE LAM |
| Permit | Cleared | 2/15/2023 | AMAAN MALIK |
| Roof/Waste drainage to street | Cleared | 2/15/2023 | AMAAN MALIK |
| Building over 36-ft | Cleared | 3/1/2023 | CALOSHA APPROVED |
| Drainage to Storm Drain | Cleared | 3/22/2023 | ALBERT TAM |
Contact Information
| Architect | Lu,, Johnny C; Lic. No.: C30396 | 16800 ASTON SUITE 275 IRVINE, CA 92606 |
| Contractor | Owner-Builder | , |
| Engineer | Phan,, Phillip Trung Tri; Lic. No.: C76425 | 641 S ALMIRANTE DR WEST COVINA, CA 91791 |
Inspector Information
| OSVALDO PARAMO, (213) 202-9854 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Other (see comments) | 4/18/2023 | Conditional Approval | RUBEN SALAS |
| Piling/Pier/Caisson | 4/19/2023 | Partial Approval | OSVALDO PARAMO |
| Piling/Pier/Caisson | 4/26/2023 | Partial Approval | OSVALDO PARAMO |
| Deputy Reinf. Concrete | 4/27/2023 | Conditional Approval | OSVALDO PARAMO |
| Footing/Foundation/Slab | 7/12/2023 | Not Ready for Inspection | OSVALDO PARAMO |
| Footing/Foundation/Slab | 7/20/2023 | Partial Approval | OSVALDO PARAMO |
| Deputy Reinf. Concrete | 7/21/2023 | Conditional Approval | OSVALDO PARAMO |
| Excavation/Setback/Form/Re-Bar | 9/14/2023 | Partial Approval | OSVALDO PARAMO |
| Deputy Shotcrete | 9/18/2023 | Conditional Approval | OSVALDO PARAMO |
| PLUMBING-Rough | 10/10/2023 | Partial Inspection | AMY COLIN |
| PLUMBING-Rough | 10/11/2023 | Partial Approval | AMY COLIN |
| Excavation/Setback/Form/Re-Bar | 10/27/2023 | Partial Approval | OSVALDO PARAMO |
| Wood Frame | 12/5/2023 | Partial Approval | OSVALDO PARAMO |
| Floor/Roof Diaphrgm/Shear Wall | 12/12/2023 | Partial Approval | OSVALDO PARAMO |
| Footing/Foundation/Slab | 1/8/2024 | Partial Approval | OSVALDO PARAMO |
| Deputy Steel/Welding | 3/12/2024 | Conditional Approval | OSVALDO PARAMO |
| Deputy Steel/Welding | 3/13/2024 | Conditional Approval | OSVALDO PARAMO |
| Floor/Roof Diaphrgm/Shear Wall | 3/26/2024 | Partial Approval | ALIZAH MAYAGOITIA |
| Footing/Foundation/Slab | 4/4/2024 | Not Ready for Inspection | OSVALDO PARAMO |
| Floor/Roof Diaphrgm/Shear Wall | 5/1/2024 | Not Ready for Inspection | OSVALDO PARAMO |
| Deputy Steel/Welding | 5/3/2024 | Conditional Approval | OSVALDO PARAMO |
| Floor/Roof Diaphrgm/Shear Wall | 5/10/2024 | Partial Approval | OSVALDO PARAMO |
| Floor/Roof Diaphrgm/Shear Wall | 5/17/2024 | Corrections Issued | OSVALDO PARAMO |
| Underground Mechanical | 6/28/2024 | Partial Approval | ALIZAH MAYAGOITIA |
| Floor/Roof Diaphrgm/Shear Wall | 7/12/2024 | Not Ready for Inspection | OSVALDO PARAMO |
| HVAC-Rough | 7/12/2024 | Corrections Issued | OSVALDO PARAMO |
| Floor/Roof Diaphrgm/Shear Wall | 7/18/2024 | Approved | OSVALDO PARAMO |
| HVAC-Rough | 7/29/2024 | Approved | OSVALDO PARAMO |
| PLUMBING-Rough | 8/1/2024 | Conditional Approval | OSVALDO PARAMO |
| Excavation/Setback/Form/Re-Bar | 8/15/2024 | Not Ready for Inspection | OSVALDO PARAMO |
| Deputy Reinf. Concrete | 8/16/2024 | Conditional Approval | OSVALDO PARAMO |
| Piling/Pier/Caisson | 8/20/2024 | Partial Approval | OSVALDO PARAMO |
| Deputy Other (see comments) | 8/22/2024 | Approved | OSVALDO PARAMO |
| Deputy Reinf. Concrete | 8/22/2024 | Conditional Approval | OSVALDO PARAMO |
| Piling/Pier/Caisson | 8/22/2024 | Approved | OSVALDO PARAMO |
| Deputy Drilled-In Anchors | 8/29/2024 | Conditional Approval | OSVALDO PARAMO |
| Excavation/Setback/Form/Re-Bar | 9/5/2024 | Partial Approval | OSVALDO PARAMO |
| Deputy Reinf. Concrete | 9/9/2024 | Conditional Approval | OSVALDO PARAMO |
| Excavation/Setback/Form/Re-Bar | 9/11/2024 | Partial Approval | OSVALDO PARAMO |
| Deputy Reinf. Concrete | 9/12/2024 | Conditional Approval | OSVALDO PARAMO |
| BUILDING-Rough-Frame | 10/11/2024 | Not Ready for Inspection | OSVALDO PARAMO |
| ELECTRICAL-Rough | 10/11/2024 | Corrections Issued | OSVALDO PARAMO |
| Green Building Rough | 10/11/2024 | Not Ready for Inspection | OSVALDO PARAMO |
| Shower Pan | 10/11/2024 | Not Ready for Inspection | OSVALDO PARAMO |
| Verify Sprinkler Sign Off | 10/11/2024 | Approved | OSVALDO PARAMO |
| ELECTRICAL-Rough | 10/23/2024 | Approved | OSVALDO PARAMO |
| Green Building Rough | 10/23/2024 | Not Ready for Inspection | OSVALDO PARAMO |
| Shower Pan | 10/23/2024 | Approved | OSVALDO PARAMO |
| BUILDING-Rough-Frame | 11/20/2024 | Approved | ALIZAH MAYAGOITIA |
| Green Building Rough | 11/20/2024 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Sewer | 11/20/2024 | Approved | ALIZAH MAYAGOITIA |
| Interior/Exterior Lathing | 12/9/2024 | Not Ready for Inspection | ROY SPAULDING |
| Insulation | 12/11/2024 | Approved | ALIZAH MAYAGOITIA |
| Interior/Exterior Lathing | 12/11/2024 | Partial Approval | ALIZAH MAYAGOITIA |
| Insulation | 12/12/2024 | Conditional Approval | JOSH MEISTER |
| Drywall Nailing | 12/19/2024 | Approved | BRENDAN MORELLI |
| Green Building Rough | 12/19/2024 | Approved | BRENDAN MORELLI |
| Special/Order Compliance | 3/18/2025 | Partial Approval | ALIZAH MAYAGOITIA |
| ELECTRICAL-Final | 3/21/2025 | Not Ready for Inspection | OSVALDO PARAMO |
| ELECTRICAL-Final | 4/1/2025 | Corrections Issued | ALIZAH MAYAGOITIA |
| PLUMBING-Final | 4/1/2025 | Partial Approval | ALIZAH MAYAGOITIA |
| HVAC-Final | 4/4/2025 | Not Ready for Inspection | OSVALDO PARAMO |
| PLUMBING-Final | 4/4/2025 | Approved | OSVALDO PARAMO |
| HVAC-Final | 4/9/2025 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| HVAC-Final | 4/15/2025 | Corrections Issued | ALIZAH MAYAGOITIA |
| ELECTRICAL-Final | 4/30/2025 | Approved | ALIZAH MAYAGOITIA |
| HVAC-Final | 4/30/2025 | Approved | ALIZAH MAYAGOITIA |
| Service/Power Release | 4/30/2025 | Approved | ALIZAH MAYAGOITIA |
| Final | 8/20/2025 | Corrections Issued | ALIZAH MAYAGOITIA |
| Footing/Foundation/Slab | 8/20/2025 | Approved | ALIZAH MAYAGOITIA |
| Green Building Final | 8/20/2025 | Approved | ALIZAH MAYAGOITIA |
| SGSOV-Seismic Gas S/O Valve | 8/20/2025 | SGSOV Approved | ALIZAH MAYAGOITIA |
| Smoke Detectors | 8/20/2025 | Approved | ALIZAH MAYAGOITIA |
| Final | 10/20/2025 | OK to Issue CofO | ALIZAH MAYAGOITIA |