2352 N BOWMONT DR 90210
Certificate Information: 2352 N BOWMONT DR 90210
- Application / Permit
- 22010-10000-05124
- Plan Check / Job No.
- B22LA21100
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 1 of 3 (N) two-story SFD over basement
- Permit Issued
- Issued on 7/28/2023
- Issuing Office
- Valley
- Current Status
- Issued on 7/28/2023
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 10/19/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 11/3/2022 | TSE MING HUANG |
| Corrections Issued | 11/9/2022 | TSE MING HUANG |
| Quality Review Completed | 11/16/2022 | KEN GILL |
| Building Plans Picked Up | 11/21/2022 | APPLICANT |
| Plan Check Approved | 7/26/2023 | TSE MING HUANG |
| Issued | 7/28/2023 | APPLICANT |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 11/9/2022 | TSE MING HUANG |
| BHO/Hillside ordinance | Cleared | 1/10/2023 | JENSON LEE |
| BHO/Hillside ordinance | Cleared | 1/10/2023 | JENSON LEE |
| BHO/Hillside ordinance | Cleared | 1/10/2023 | JENSON LEE |
| Eng Process Fee Ord 176,300 | Cleared | 1/12/2023 | JENSON LEE |
| Sewer availability | Cleared | 2/1/2023 | JENSON LEE |
| Hydrant and Access approval | Cleared | 3/23/2023 | KURT CORRAL |
| Low Impact Development | Cleared | 4/12/2023 | TOMMY YIN |
| Landscape for retaining wall | Cleared | 4/24/2023 | DALIA MOKAYED |
| Miscellaneous | Cleared | 4/24/2023 | DALIA MOKAYED |
| Specific Plan | Cleared | 4/24/2023 | DALIA MOKAYED |
| BHO/Hillside ordinance | Cleared | 5/1/2023 | AHMED AMARRAGY |
| BHO/Hillside ordinance | Cleared | 5/1/2023 | AHMED AMARRAGY |
| Trees in Parkway | Cleared | 5/2/2023 | ADALBERTO VERA |
| Disturb/Remove Protected Trees | Cleared | 6/12/2023 | ADALBERTO VERA |
| Roof/Waste drainage to street | Cleared | 7/21/2023 | DINAH GARIN |
| Excavation more than 5-ft deep | Cleared | 7/26/2023 | CALOSHA APPROVED |
| Zoning Information File | Cleared | 7/26/2023 | TSE MING HUANG |
Contact Information
| Contractor | Artech Construction; Lic. No.: 848955-B | 1136 N-KENTER AVENUE LOS ANGELES, CA 90049 |
| Engineer | Lee,, Shyan-Chyun Tony; Lic. No.: C44045 | 17834 BAILEY DRIVE TORRANCE, CA 90504 |
| Engineer | Moeini,, Soheil; Lic. No.: C84000 | 11022 SANTA MONICA BLVD STE 440 LOS ANGELES, CA 90025 |
| Geologist | Jong,, Hank Hsing-Lian; Lic. No.: EG1646 | 11819 GOLDRING RD UNIT A ARCADIA, CA 91006 |
Inspector Information
| BRENDAN MORELLI, (213) 202-3412 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 12/20/2023 | Partial Approval | RAUL BARAJAS |
| Footing/Foundation/Slab | 1/19/2024 | Partial Approval | RAUL BARAJAS |
| Protected Tree Letter | 1/19/2024 | Not Ready for Inspection | RAUL BARAJAS |
| Deputy Reinf. Concrete | 1/24/2024 | Conditional Approval | RAUL BARAJAS |
| Gas Test | 2/13/2024 | Partial Approval | RAUL BARAJAS |
| PLUMBING-Rough | 2/13/2024 | Partial Approval | RAUL BARAJAS |
| Underground Mechanical | 2/13/2024 | Partial Approval | RAUL BARAJAS |
| Deputy Shotcrete | 3/19/2024 | Conditional Approval | RAUL BARAJAS |
| Deputy Shotcrete | 3/20/2024 | Conditional Approval | RAUL BARAJAS |
| Green Building Final | 3/20/2024 | Not Ready for Inspection | RAUL BARAJAS |
| Reinforced Concrete Frame | 3/20/2024 | Not Ready for Inspection | RAUL BARAJAS |
| Reinforced Concrete Frame | 3/26/2024 | Corrections Issued | JOAQUIN GREENOUGH |
| Reinforced Concrete Frame | 4/2/2024 | Approved | ALIZAH MAYAGOITIA |
| Deputy Shotcrete | 4/10/2024 | Conditional Approval | RAUL BARAJAS |
| Deputy Shotcrete | 4/11/2024 | Conditional Approval | RAUL BARAJAS |
| Deputy Shotcrete | 4/12/2024 | Conditional Approval | RAUL BARAJAS |
| Deputy Reinf. Concrete | 5/1/2024 | Conditional Approval | RAUL BARAJAS |
| Underground Mechanical | 5/13/2024 | Approved | ROY SPAULDING |
| Footing/Foundation/Slab | 5/21/2024 | Partial Approval | RAUL BARAJAS |
| Protected Tree Letter | 5/21/2024 | Not Ready for Inspection | RAUL BARAJAS |
| Deputy Reinf. Concrete | 5/30/2024 | Conditional Approval | RAUL BARAJAS |
| Footing/Foundation/Slab | 7/2/2024 | Partial Approval | RAUL BARAJAS |
| Protected Tree Letter | 7/2/2024 | Not Ready for Inspection | RAUL BARAJAS |
| Footing/Foundation/Slab | 7/30/2024 | Corrections Issued | RAUL BARAJAS |
| Protected Tree Letter | 7/30/2024 | Not Ready for Inspection | RAUL BARAJAS |
| Deputy Reinf. Concrete | 7/31/2024 | Conditional Approval | RAUL BARAJAS |
| Deputy Wood Construction | 8/1/2024 | Conditional Approval | ANTHONY RAMOS |
| Deputy Reinf. Concrete | 8/2/2024 | Conditional Approval | RAUL BARAJAS |
| Sewer | 8/12/2024 | Partial Approval | ALEX COLIN |
| Deputy Reinf. Concrete | 8/28/2024 | Conditional Approval | RAUL BARAJAS |
| Floor/Roof Diaphrgm/Shear Wall | 10/11/2024 | Partial Approval | RAUL BARAJAS |
| Floor/Roof Diaphrgm/Shear Wall | 11/19/2024 | Corrections Issued | CRAIG VAUGHAN |
| Floor/Roof Diaphrgm/Shear Wall | 1/3/2025 | Partial Inspection | RAUL BARAJAS |
| Deputy Reinf. Concrete | 1/22/2025 | Conditional Approval | RAUL BARAJAS |
| Deputy Wood Construction | 4/9/2025 | Conditional Approval | ALIZAH MAYAGOITIA |
| ELECTRICAL-Rough | 4/9/2025 | Approved | ALIZAH MAYAGOITIA |
| PLUMBING-Rough | 4/9/2025 | Approved | ALIZAH MAYAGOITIA |
| Floor/Roof Diaphrgm/Shear Wall | 4/15/2025 | Partial Approval | RAUL BARAJAS |
| BUILDING-Rough-Frame | 7/1/2025 | Not Ready for Inspection | RAUL BARAJAS |
| Floor/Roof Diaphrgm/Shear Wall | 7/1/2025 | Not Ready for Inspection | RAUL BARAJAS |
| Green Building Rough | 7/1/2025 | Not Ready for Inspection | RAUL BARAJAS |
| Verify Sprinkler Sign Off | 7/1/2025 | Not Ready for Inspection | RAUL BARAJAS |
| Wood Frame | 7/1/2025 | Not Ready for Inspection | RAUL BARAJAS |
| BUILDING-Rough-Frame | 7/2/2025 | Partial Inspection | RAUL BARAJAS |
| Green Building Rough | 7/2/2025 | Partial Inspection | RAUL BARAJAS |
| Verify Sprinkler Sign Off | 7/2/2025 | Not Ready for Inspection | RAUL BARAJAS |
| BUILDING-Rough-Frame | 7/14/2025 | Corrections Issued | RAUL BARAJAS |
| Green Building Rough | 7/14/2025 | Corrections Issued | RAUL BARAJAS |
| HVAC-Rough | 7/14/2025 | Corrections Issued | RAUL BARAJAS |
| Verify Sprinkler Sign Off | 7/14/2025 | Approved | RAUL BARAJAS |
| Wood Frame | 7/14/2025 | Partial Inspection | RAUL BARAJAS |
| Insulation | 7/23/2025 | Not Ready for Inspection | JOSH MEISTER |
| BUILDING-Rough-Frame | 7/30/2025 | Conditional Approval | BRENDAN MORELLI |
| Green Building Rough | 7/30/2025 | Approved | BRENDAN MORELLI |
| HVAC-Rough | 7/30/2025 | Not Ready for Inspection | BRENDAN MORELLI |
| Insulation | 7/30/2025 | Corrections Issued | BRENDAN MORELLI |
| Interior/Exterior Lathing | 7/30/2025 | Partial Approval | BRENDAN MORELLI |
| Shower Pan | 8/7/2025 | Approved | DAVID WILLIAMS |
| Drywall Nailing | 8/28/2025 | Approved | ROY SPAULDING |
| Interior/Exterior Lathing | 8/28/2025 | Approved | ROY SPAULDING |
| Interior/Exterior Lathing | 10/21/2025 | Approved | BRIAN SULLIVAN |