1929 W 22ND ST 1-4 90018
Certificate Information: 1929 W 22ND ST 1-4 90018
- Application / Permit
- 22010-10000-05115
- Plan Check / Job No.
- B22LA21055
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- NEW 3 STORY 4 UNIT APARTMENT BUILDING (PRIVATELY FUNDED) 1 OF 2 **** BUILDING TO BE FULLY EQUIPPED WITH NFPA-13R FIRE SPRINKLERS****
- Permit Issued
- Issued on 12/2/2024
- Issuing Office
- Metro
- Current Status
- Issued on 12/2/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 10/19/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 10/20/2022 | CRYSTEL MAALOUF |
| Disabled Access Plans Picked Up | 10/28/2022 | APPLICANT |
| Green Plans Picked Up | 10/28/2022 | APPLICANT |
| Corrections Issued | 11/7/2022 | CRYSTEL MAALOUF |
| Quality Review Completed | 11/10/2022 | KEN GILL |
| Building Plans Picked Up | 12/7/2022 | APPLICANT |
| Applicant returned to address corrections | 3/3/2023 | CRYSTEL MAALOUF |
| Applicant returned to address corrections | 7/26/2023 | CRYSTEL MAALOUF |
| Plan Check Approved | 4/24/2024 | CRYSTEL MAALOUF |
| Issued | 12/2/2024 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 11/17/2022 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 11/18/2022 | WALLIE JONG |
| Construction near power lines | Cleared | 1/31/2023 | RIDWAN HARDY |
| Hydrant and Access approval | Cleared | 2/16/2023 | KURT CORRAL |
| Sewer availability | Cleared | 2/21/2023 | WALLIE JONG |
| Community Plan Implem. Overlay | Cleared | 2/28/2023 | RAFAEL FONTES |
| ZI | Cleared | 2/28/2023 | RAFAEL FONTES |
| DAS Clearance | Cleared | 6/12/2023 | SHINE LIN |
| Green Code | Cleared | 6/15/2023 | AARON COSTA |
| Low Impact Development | Cleared | 7/6/2023 | SARAH YOUSSEF |
| Roof/Waste drainage to street | Cleared | 7/6/2023 | JEANIE LAM |
| Frnt yard landscape/Water mgmt | Cleared | 8/2/2023 | MAYELA VILLA |
| Opn space landscape/Water mgmt | Cleared | 8/2/2023 | MAYELA VILLA |
| Fire Marshal Fire Life Safety | Cleared | 8/17/2023 | FIRE DEPARTMENT |
| SB8 RUD | Cleared | 4/23/2024 | MICHAEL ZIRBES |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Alson,, Ken; Lic. No.: C41697 | 9744 MAPLE ST 201 BELLFLOWER, CA 90706 |
| Engineer | Shmeit,, Ayman; Lic. No.: C93325 | 9744 MAPLE ST #101 BELLFLOWER, CA 90706 |
Inspector Information
| ALFREDO LOPEZ, (213) 482-0361 | Office Hours: 7:00-8:00 AM MON-FRI |
| JAMES POWERS, (213) 482-0361 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 12/4/2024 | Not Ready for Inspection | JAMES POWERS |
| METHANE-Barrier | 12/4/2024 | Not Ready for Inspection | JAMES POWERS |
| METHANE-Subgrade | 12/4/2024 | Not Ready for Inspection | JAMES POWERS |
| Pre-Inspection | 12/4/2024 | Not Ready for Inspection | JAMES POWERS |
| Footing/Foundation/Slab | 12/23/2024 | Not Ready for Inspection | RAMAZANALI ALMASI |
| METHANE-Barrier | 12/23/2024 | Not Ready for Inspection | RAMAZANALI ALMASI |
| METHANE-Subgrade | 12/23/2024 | Not Ready for Inspection | RAMAZANALI ALMASI |
| Footing/Foundation/Slab | 12/27/2024 | Partial Approval | JAMES POWERS |
| METHANE-Barrier | 12/27/2024 | Approved | JAMES POWERS |
| METHANE-Subgrade | 12/27/2024 | Approved | JAMES POWERS |
| Floor/Roof Diaphrgm/Shear Wall | 1/23/2025 | Partial Approval | JAMES POWERS |
| Green Building Rough | 1/23/2025 | Not Ready for Inspection | JAMES POWERS |
| METHANE-Rough | 1/23/2025 | Approved | JAMES POWERS |
| Verify Sprinkler Sign Off | 1/23/2025 | Not Ready for Inspection | JAMES POWERS |
| Floor/Roof Diaphrgm/Shear Wall | 2/3/2025 | Partial Approval | JAMES POWERS |
| Green Building Rough | 2/3/2025 | Not Ready for Inspection | JAMES POWERS |
| Verify Sprinkler Sign Off | 2/3/2025 | Not Ready for Inspection | JAMES POWERS |
| Green Building Rough | 4/3/2025 | Not Ready for Inspection | ALFREDO LOPEZ |
| Verify Sprinkler Sign Off | 4/3/2025 | Not Ready for Inspection | ALFREDO LOPEZ |
| Wood Frame | 4/3/2025 | Partial Approval | ALFREDO LOPEZ |
| Interior/Exterior Lathing | 5/20/2025 | Approved | JAMES POWERS |
| Insulation | 2/25/2026 | Not Ready for Inspection | RAFAEL CORTES |
| Green Building Rough | 6/22/2026 | Approved | JAMES POWERS |
| Insulation | 6/22/2026 | Approved | JAMES POWERS |
| Verify Sprinkler Sign Off | 6/22/2026 | Not Ready for Inspection | JAMES POWERS |
| Wood Frame | 6/22/2026 | Partial Approval | JAMES POWERS |