1346-1346 1/2 W 35TH ST 90007

Certificate Information: 1346-1346 1/2 W 35TH ST 90007

Application / Permit
22010-10000-05083
Plan Check / Job No.
B22LA19774
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
ePlan. PROPOSED DUPLEX WITH ATTACHED GARAGE AT REAR OF LOT
Permit Issued
Issued on 8/22/2023
Issuing Office
Current Status
CofO Issued on 12/26/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/6/2022 APPLICANT
Assigned to Plan Check Engineer 10/13/2022 SINA KHOSRAVI
Corrections Issued 10/17/2022 SINA KHOSRAVI
Quality Review Completed 10/25/2022 TEODORO DIAZ RODRIGUEZ
Applicant returned to address corrections 8/3/2023 SINA KHOSRAVI
Plan Check Approved 8/17/2023 SINA KHOSRAVI
Issued 8/22/2023 APPLICANT
CofO in Progress 12/21/2024 SABAS ALONSO
Permit Finaled 12/26/2024 DEROLD HAUFF
CofO Issued 12/26/2024 DEROLD HAUFF
Permit Finaled 12/26/2024 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 10/29/2022 AMAAN MALIK
Eng Process Fee Ord 176,300 Cleared 1/27/2023 AMAAN MALIK
Sewer availability Cleared 1/27/2023 AMAAN MALIK
Hydrant and Access approval Cleared 4/12/2023 KURT CORRAL
Low Impact Development Cleared 4/19/2023 TOMMY YIN
Roof/Waste drainage to street Cleared 5/13/2023 STEVE MELGAR
SB8 RUD Cleared 7/19/2023 BLAKE BOULIGNY

Contact Information

Contractor Emerald Builders And Developers; Lic. No.: 1068007-B 1412 W 22ND STREET      LOS ANGELES, CA 90007
Engineer Salto,, Alvaro; Lic. No.: C83859 2543 E NORMAN AVE      WEST COVINA, CA 91791

Inspector Information

SABAS ALONSO, (213) 202-3468 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 10/31/2023 Partial Approval SABAS ALONSO
METHANE-Subgrade 10/31/2023 Approved SABAS ALONSO
Sewer 10/31/2023 Approved SABAS ALONSO
Underground Mechanical 10/31/2023 Partial Approval SABAS ALONSO
Excavation/Setback/Form/Re-Bar 11/1/2023 Approved SABAS ALONSO
Footing/Foundation/Slab 11/1/2023 Not Ready for Inspection SABAS ALONSO
METHANE-Barrier 11/1/2023 Approved SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 12/28/2023 Partial Approval SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 1/22/2024 Partial Approval SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 2/13/2024 Partial Approval SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 3/22/2024 Approved SABAS ALONSO
PLUMBING-Rough 4/9/2024 Conditional Approval SABAS ALONSO
ELECTRICAL-Rough 5/10/2024 Approved SABAS ALONSO
Green Building Rough 5/10/2024 Approved SABAS ALONSO
HVAC-Rough 5/10/2024 Approved SABAS ALONSO
METHANE-Rough 5/10/2024 Approved SABAS ALONSO
BUILDING-Rough-Frame 6/4/2024 Conditional Approval SABAS ALONSO
Verify Sprinkler Sign Off 6/4/2024 Not Ready for Inspection SABAS ALONSO
BUILDING-Rough-Frame 6/7/2024 Approved SABAS ALONSO
Insulation 6/7/2024 Approved SABAS ALONSO
Verify Sprinkler Sign Off 6/7/2024 Approved SABAS ALONSO
Drywall Nailing 6/18/2024 Approved JOSH MEISTER
Interior/Exterior Lathing 7/18/2024 Approved SABAS ALONSO
Shower Pan 7/18/2024 Approved SABAS ALONSO
Final 12/6/2024 Corrections Issued SABAS ALONSO
Footing/Foundation/Slab 12/6/2024 Approved SABAS ALONSO
Green Building Final 12/6/2024 Approved SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 12/6/2024 SGSOV Approved SABAS ALONSO
Service/Power Release 12/6/2024 Not Ready for Inspection SABAS ALONSO
Smoke Detectors 12/6/2024 Approved SABAS ALONSO
Final 12/18/2024 OK to Issue CofO SABAS ALONSO
Service/Power Release 12/18/2024 Approved SABAS ALONSO