1379-1379 1/2 W 36TH PL 90007

Certificate Information: 1379-1379 1/2 W 36TH PL 90007

Application / Permit
22010-10000-05082
Plan Check / Job No.
B22LA19170
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
ePlan ** PROPOSED DUPLEX WITH ATTACHED GARAGE AT REAR OF LOT
Permit Issued
Issued on 7/25/2023
Issuing Office
Current Status
CofO Issued on 2/26/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/6/2022 APPLICANT
Assigned to Plan Check Engineer 10/13/2022 SINA KHOSRAVI
Corrections Issued 10/17/2022 SINA KHOSRAVI
Quality Review Completed 10/25/2022 TEODORO DIAZ RODRIGUEZ
Applicant returned to address corrections 5/19/2023 SINA KHOSRAVI
Applicant returned to address corrections 6/26/2023 SINA KHOSRAVI
Plan Check Approved 7/11/2023 SINA KHOSRAVI
Issued 7/25/2023 APPLICANT
CofO in Progress 2/25/2025 SABAS ALONSO
Permit Finaled 2/26/2025 DEROLD HAUFF
CofO Issued 2/26/2025 DEROLD HAUFF
Permit Finaled 2/26/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 10/28/2022 AMAAN MALIK
Sewer availability Cleared 11/1/2022 AMAAN MALIK
Eng Process Fee Ord 176,300 Cleared 12/15/2022 AMAAN MALIK
Low Impact Development Cleared 1/13/2023 ROGELIO CORTES
Hydrant and Access approval Cleared 1/17/2023 KURT CORRAL
Roof/Waste drainage to street Cleared 2/7/2023 AMAAN MALIK
SB8 RUD Cleared 4/7/2023 CHARLOTTE KINGS
Highway dedication Cleared 4/12/2023 CELINA MORENO

Contact Information

Contractor Emerald Builders And Developers; Lic. No.: 1068007-B 1412 W 22ND STREET      LOS ANGELES, CA 90007
Engineer Salto,, Alvaro; Lic. No.: C83859 2543 E NORMAN AVE      WEST COVINA, CA 91791

Inspector Information

SABAS ALONSO, (213) 202-3468 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 9/25/2023 Partial Approval SABAS ALONSO
Sewer 10/2/2023 Approved SABAS ALONSO
Underground Mechanical 10/2/2023 Partial Approval SABAS ALONSO
METHANE-Barrier 10/5/2023 Approved SABAS ALONSO
METHANE-Subgrade 10/5/2023 Approved SABAS ALONSO
Footing/Foundation/Slab 10/6/2023 Approved SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 11/21/2023 Partial Approval SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 12/12/2023 Partial Approval SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 1/9/2024 Partial Approval SABAS ALONSO
PLUMBING-Rough 2/26/2024 Conditional Approval SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 3/12/2024 Corrections Issued SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 4/3/2024 Approved SABAS ALONSO
ELECTRICAL-Rough 5/23/2024 Approved SABAS ALONSO
HVAC-Rough 5/23/2024 Approved SABAS ALONSO
BUILDING-Rough-Frame 6/5/2024 Approved SABAS ALONSO
Green Building Rough 6/5/2024 Approved SABAS ALONSO
METHANE-Rough 6/5/2024 Approved SABAS ALONSO
Shower Pan 6/5/2024 Partial Approval SABAS ALONSO
Verify Sprinkler Sign Off 6/5/2024 Approved SABAS ALONSO
Insulation 6/11/2024 Approved SABAS ALONSO
Drywall Nailing 6/24/2024 Approved SABAS ALONSO
Shower Pan 6/24/2024 Partial Approval SABAS ALONSO
Interior/Exterior Lathing 8/12/2024 Approved AMY COLIN
Shower Pan 8/12/2024 Approved AMY COLIN
ELECTRICAL-Final 1/21/2025 Approved SABAS ALONSO
HVAC-Final 1/21/2025 Approved SABAS ALONSO
PLUMBING-Final 1/21/2025 Approved SABAS ALONSO
Final 2/13/2025 Corrections Issued SABAS ALONSO
Gas Test 2/13/2025 Approved SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 2/13/2025 SGSOV Approved SABAS ALONSO
Service/Power Release 2/13/2025 Approved SABAS ALONSO
Smoke Detectors 2/13/2025 Approved SABAS ALONSO
ELECTRICAL-Final 2/14/2025 Approved SABAS ALONSO
Green Building Final 2/14/2025 Approved SABAS ALONSO
Final 2/21/2025 OK to Issue CofO SABAS ALONSO