1639 S AMHERST AVE 90025
Certificate Information: 1639 S AMHERST AVE 90025
- Application / Permit
- 22010-10000-05057
- Plan Check / Job No.
- B22LA20691
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePlan - (n) 2-story SFD w/ attached garage, landscaping
- Permit Issued
- Issued on 4/3/2023
- Issuing Office
- Current Status
- CofO Issued on 11/21/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/13/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 10/20/2022 | KELVIN CHUONG |
| Corrections Issued | 10/27/2022 | KELVIN CHUONG |
| Quality Review Completed | 11/3/2022 | RODOLFO ARIAS |
| Applicant returned to address corrections | 11/22/2022 | KELVIN CHUONG |
| Applicant returned to address corrections | 11/29/2022 | KELVIN CHUONG |
| Applicant returned to address corrections | 12/6/2022 | KELVIN CHUONG |
| Applicant returned to address corrections | 12/15/2022 | KELVIN CHUONG |
| Applicant returned to address corrections | 1/5/2023 | KELVIN CHUONG |
| Plan Check Approved | 2/8/2023 | KELVIN CHUONG |
| Issued | 4/3/2023 | APPLICANT |
| CofO in Progress | 11/16/2024 | KIRK SANDERS |
| Permit Finaled | 11/21/2024 | RICHARD STEINBACH |
| CofO Issued | 11/21/2024 | RICHARD STEINBACH |
| Permit Finaled | 11/21/2024 | RICHARD STEINBACH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 11/9/2022 | JENSON LEE |
| Low Impact Development | Cleared | 11/9/2022 | ANDRES COVARRUBIAS |
| Permit | Cleared | 11/10/2022 | JENSON LEE |
| Roof/Waste drainage to street | Cleared | 11/10/2022 | JENSON LEE |
| Sewer availability | Cleared | 11/10/2022 | JENSON LEE |
| Trees in Parkway | Cleared | 11/16/2022 | ADALBERTO VERA |
| Hydrant and Access approval | Cleared | 11/26/2022 | JOHN CONNEALLY |
| Specific Plan | Cleared | 12/1/2022 | FREDDY GARCIA |
Contact Information
| Architect | Niemerski,, Kenneth Chester; Lic. No.: C23971 | 52 DAWNWOOD LADERA RANCH, CA 92694 |
| Architect | Niemerski,, Kenneth Chester; Lic. No.: NA23971 | , |
| Contractor | T J C Home Builders Llc; Lic. No.: 1025507-B | 26880 ALISO VIEJO PKWY STE 200 ALISO VIEJO, CA 92656 |
| Engineer | Nguyen,, Huan; Lic. No.: NA64238 | , |
Inspector Information
| ANTHONY EGSON, (310) 914-3893 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 9/18/2023 | Partial Inspection | KENNETH NAGLE |
| Sewer | 9/29/2023 | Approved | CARLOS MATAMOROS |
| Underground Mechanical | 9/29/2023 | Approved | CARLOS MATAMOROS |
| BUILDING-Rough-Frame | 10/6/2023 | Corrections Issued | CLAYTON GRAHAM |
| Excavation/Setback/Form/Re-Bar | 10/6/2023 | Approved | CLAYTON GRAHAM |
| Deputy Pre-Stress Concrete | 11/9/2023 | Conditional Approval | BEN MOLSTAD |
| Floor/Roof Diaphrgm/Shear Wall | 11/22/2023 | Partial Approval | BEN MOLSTAD |
| Floor/Roof Diaphrgm/Shear Wall | 12/8/2023 | Conditional Approval | BEN MOLSTAD |
| ELECTRICAL-Rough | 1/5/2024 | Corrections Issued | BEN MOLSTAD |
| Gas Test | 1/5/2024 | Approved | BEN MOLSTAD |
| PLUMBING-Rough | 1/5/2024 | Approved | BEN MOLSTAD |
| Pre-Inspection | 1/5/2024 | Not Ready for Inspection | BEN MOLSTAD |
| HVAC-Rough | 1/8/2024 | Approved | JESUS RODRIGUEZ |
| Shower Pan | 1/8/2024 | Corrections Issued | JESUS RODRIGUEZ |
| BUILDING-Rough-Frame | 1/9/2024 | Not Ready for Inspection | BEN MOLSTAD |
| Green Building Rough | 1/9/2024 | Not Ready for Inspection | BEN MOLSTAD |
| Pre-Inspection | 1/9/2024 | Not Ready for Inspection | BEN MOLSTAD |
| Shower Pan | 1/9/2024 | Approved | BEN MOLSTAD |
| Verify Sprinkler Sign Off | 1/9/2024 | Not Ready for Inspection | BEN MOLSTAD |
| ELECTRICAL-Rough | 1/12/2024 | Approved | BEN MOLSTAD |
| BUILDING-Rough-Frame | 1/22/2024 | Conditional Approval | BEN MOLSTAD |
| Green Building Rough | 1/22/2024 | Not Ready for Inspection | BEN MOLSTAD |
| Verify Sprinkler Sign Off | 1/22/2024 | Approved | BEN MOLSTAD |
| BUILDING-Rough-Frame | 1/26/2024 | Conditional Approval | BEN MOLSTAD |
| Green Building Rough | 1/26/2024 | Not Ready for Inspection | BEN MOLSTAD |
| Interior/Exterior Lathing | 1/30/2024 | Approved | BEN MOLSTAD |
| Special/Order Compliance | 1/30/2024 | Partial Approval | ASHLEY THOMPSON |
| Insulation | 2/1/2024 | Approved | EVAN COOPER |
| BUILDING-Rough-Frame | 2/6/2024 | Approved | STEPHANIE SWANSON |
| Drywall Nailing | 2/6/2024 | Approved | STEPHANIE SWANSON |
| Green Building Rough | 2/6/2024 | Approved | STEPHANIE SWANSON |
| Interior/Exterior Lathing | 2/29/2024 | Approved | ASHLEY THOMPSON |
| PLUMBING-Final | 7/16/2024 | Not Ready for Inspection | KIRK SANDERS |
| SGSOV-Seismic Gas S/O Valve | 7/16/2024 | SGSOV Not Ready | KIRK SANDERS |
| Gas Test | 7/23/2024 | Approved | KIRK SANDERS |
| PLUMBING-Final | 7/23/2024 | Approved | KIRK SANDERS |
| SGSOV-Seismic Gas S/O Valve | 7/23/2024 | SGSOV Approved | KIRK SANDERS |
| ELECTRICAL-Final | 8/5/2024 | Corrections Issued | KIRK SANDERS |
| Green Building Final | 8/5/2024 | Not Ready for Inspection | KIRK SANDERS |
| Service/Power Release | 8/5/2024 | Not Ready for Inspection | KIRK SANDERS |
| ELECTRICAL-Final | 8/7/2024 | Partial Approval | KIRK SANDERS |
| ELECTRICAL-Final | 8/22/2024 | Partial Approval | KIRK SANDERS |
| Green Building Final | 8/22/2024 | Approved | KIRK SANDERS |
| HVAC-Final | 8/22/2024 | Approved | KIRK SANDERS |
| Smoke Detectors | 8/22/2024 | Approved | KIRK SANDERS |
| ELECTRICAL-Final | 9/4/2024 | Partial Approval | KIRK SANDERS |
| ELECTRICAL-Final | 9/17/2024 | Corrections Issued | KIRK SANDERS |
| Final | 9/20/2024 | Corrections Issued | KIRK SANDERS |
| Footing/Foundation/Slab | 9/20/2024 | Approved | KIRK SANDERS |
| Service/Power Release | 9/20/2024 | Not Ready for Inspection | KIRK SANDERS |
| ELECTRICAL-Final | 10/9/2024 | Approved | KIRK SANDERS |
| Service/Power Release | 10/9/2024 | Approved | KIRK SANDERS |
| Final | 11/15/2024 | OK to Issue CofO | KIRK SANDERS |