4906 N GAVIOTA AVE 91436

Certificate Information: 4906 N GAVIOTA AVE 91436

Application / Permit
22010-10000-05034
Plan Check / Job No.
B22LA20645
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW TWO STORY SFD WITH ATTACHED GARAGE.
Permit Issued
Issued on 3/8/2023
Issuing Office
Current Status
CofO in Progress on 4/22/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 10/13/2022 APPLICANT
Assigned to Plan Check Engineer 10/13/2022 JOE VO
Corrections Issued 10/15/2022 JOE VO
Quality Review Completed 10/17/2022 GARO TELMI
Plan Check Approved 3/6/2023 JOE VO
Issued 3/8/2023 APPLICANT
CofO in Progress 4/22/2026 SEAN WIRCH

Permit Application Clearance Information

Permit Cleared 11/14/2022 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 11/15/2022 CARLOS AGUILERA
Sewer availability Cleared 11/15/2022 CARLOS AGUILERA
Hydrant and Access approval Cleared 11/23/2022 LAVEON RIDER
Low Impact Development Cleared 2/8/2023 LUIS LUVANO
Roof/Waste drainage to street Cleared 2/9/2023 RYAN KIM

Contact Information

Contractor Owner-Builder       ,
Engineer Helou,, Dawn Renee; Lic. No.: C52361 22701 ERWIN ST      WOODLAND HILLS, CA 91367

Inspector Information

THOMAS FINNILA, (818) 774-4324 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 3/20/2024 Partial Approval VINCENT HANLEY
Sewer 3/20/2024 Approved VINCENT HANLEY
Underground Mechanical 3/20/2024 Partial Approval VINCENT HANLEY
Footing/Foundation/Slab 4/19/2024 Approved VINCENT HANLEY
Deputy Reinf. Concrete 4/24/2024 Partial Approval VINCENT HANLEY
Deputy Drilled-In Anchors 5/13/2024 Conditional Approval THOMAS FINNILA
Deputy Steel/Welding 5/13/2024 Conditional Approval THOMAS FINNILA
Wood Frame 5/21/2024 Conditional Approval THOMAS FINNILA
Wood Frame 6/20/2024 Not Ready for Inspection THOMAS FINNILA
Deputy Drilled-In Anchors 6/24/2024 Conditional Approval THOMAS FINNILA
Floor/Roof Diaphrgm/Shear Wall 7/5/2024 Corrections Issued THOMAS FINNILA
PLUMBING-Rough 7/5/2024 Approved THOMAS FINNILA
Floor/Roof Diaphrgm/Shear Wall 7/15/2024 Partial Approval THOMAS FINNILA
ELECTRICAL-Rough 7/25/2024 Not Ready for Inspection THOMAS FINNILA
HVAC-Rough 7/25/2024 Approved THOMAS FINNILA
Shower Pan 7/31/2024 Corrections Issued JON MCHUGH
Shower Pan 8/5/2024 Approved JOHN KIDWELL
Floor/Roof Diaphrgm/Shear Wall 10/21/2024 Not Ready for Inspection GEVORK IPCHYAN
Floor/Roof Diaphrgm/Shear Wall 10/28/2024 Partial Approval THOMAS FINNILA
ELECTRICAL-Rough 10/31/2024 Corrections Issued THOMAS FINNILA
Floor/Roof Diaphrgm/Shear Wall 10/31/2024 Partial Approval THOMAS FINNILA
BUILDING-Rough-Frame 11/5/2024 Partial Approval MORRIS JACKSON
ELECTRICAL-Rough 11/5/2024 Approved MORRIS JACKSON
Green Building Rough 11/5/2024 Approved MORRIS JACKSON
Interior/Exterior Lathing 11/5/2024 Partial Approval MORRIS JACKSON
Verify Sprinkler Sign Off 11/5/2024 Approved MORRIS JACKSON
ELECTRICAL-Final 11/14/2024 Not Ready for Inspection MORRIS JACKSON
Interior/Exterior Lathing 11/14/2024 Partial Approval MORRIS JACKSON
Masonry Wall/Backfill 11/14/2024 Partial Inspection MORRIS JACKSON
Insulation 11/19/2024 Approved MORRIS JACKSON
Interior/Exterior Lathing 11/19/2024 Approved MORRIS JACKSON
Drywall Nailing 11/26/2024 Approved MORRIS JACKSON
BUILDING-Rough-Frame 4/17/2026 Approved SEAN WIRCH
ELECTRICAL-Final 4/17/2026 Approved SEAN WIRCH
HVAC-Final 4/17/2026 Approved SEAN WIRCH
PLUMBING-Final 4/17/2026 Approved SEAN WIRCH
Service/Power Release 4/17/2026 Approved SEAN WIRCH
Smoke Detectors 4/17/2026 Approved SEAN WIRCH
Final 4/21/2026 OK to Issue CofO SEAN WIRCH
Green Building Final 4/21/2026 Approved SEAN WIRCH
SGSOV-Seismic Gas S/O Valve 4/21/2026 SGSOV Approved SEAN WIRCH