4906 N GAVIOTA AVE 91436
Certificate Information: 4906 N GAVIOTA AVE 91436
- Application / Permit
- 22010-10000-05034
- Plan Check / Job No.
- B22LA20645
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW TWO STORY SFD WITH ATTACHED GARAGE.
- Permit Issued
- Issued on 3/8/2023
- Issuing Office
- Current Status
- CofO in Progress on 4/22/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 10/13/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 10/13/2022 | JOE VO |
| Corrections Issued | 10/15/2022 | JOE VO |
| Quality Review Completed | 10/17/2022 | GARO TELMI |
| Plan Check Approved | 3/6/2023 | JOE VO |
| Issued | 3/8/2023 | APPLICANT |
| CofO in Progress | 4/22/2026 | SEAN WIRCH |
Permit Application Clearance Information
| Permit | Cleared | 11/14/2022 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 11/15/2022 | CARLOS AGUILERA |
| Sewer availability | Cleared | 11/15/2022 | CARLOS AGUILERA |
| Hydrant and Access approval | Cleared | 11/23/2022 | LAVEON RIDER |
| Low Impact Development | Cleared | 2/8/2023 | LUIS LUVANO |
| Roof/Waste drainage to street | Cleared | 2/9/2023 | RYAN KIM |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Helou,, Dawn Renee; Lic. No.: C52361 | 22701 ERWIN ST WOODLAND HILLS, CA 91367 |
Inspector Information
| THOMAS FINNILA, (818) 774-4324 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 3/20/2024 | Partial Approval | VINCENT HANLEY |
| Sewer | 3/20/2024 | Approved | VINCENT HANLEY |
| Underground Mechanical | 3/20/2024 | Partial Approval | VINCENT HANLEY |
| Footing/Foundation/Slab | 4/19/2024 | Approved | VINCENT HANLEY |
| Deputy Reinf. Concrete | 4/24/2024 | Partial Approval | VINCENT HANLEY |
| Deputy Drilled-In Anchors | 5/13/2024 | Conditional Approval | THOMAS FINNILA |
| Deputy Steel/Welding | 5/13/2024 | Conditional Approval | THOMAS FINNILA |
| Wood Frame | 5/21/2024 | Conditional Approval | THOMAS FINNILA |
| Wood Frame | 6/20/2024 | Not Ready for Inspection | THOMAS FINNILA |
| Deputy Drilled-In Anchors | 6/24/2024 | Conditional Approval | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 7/5/2024 | Corrections Issued | THOMAS FINNILA |
| PLUMBING-Rough | 7/5/2024 | Approved | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 7/15/2024 | Partial Approval | THOMAS FINNILA |
| ELECTRICAL-Rough | 7/25/2024 | Not Ready for Inspection | THOMAS FINNILA |
| HVAC-Rough | 7/25/2024 | Approved | THOMAS FINNILA |
| Shower Pan | 7/31/2024 | Corrections Issued | JON MCHUGH |
| Shower Pan | 8/5/2024 | Approved | JOHN KIDWELL |
| Floor/Roof Diaphrgm/Shear Wall | 10/21/2024 | Not Ready for Inspection | GEVORK IPCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/28/2024 | Partial Approval | THOMAS FINNILA |
| ELECTRICAL-Rough | 10/31/2024 | Corrections Issued | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 10/31/2024 | Partial Approval | THOMAS FINNILA |
| BUILDING-Rough-Frame | 11/5/2024 | Partial Approval | MORRIS JACKSON |
| ELECTRICAL-Rough | 11/5/2024 | Approved | MORRIS JACKSON |
| Green Building Rough | 11/5/2024 | Approved | MORRIS JACKSON |
| Interior/Exterior Lathing | 11/5/2024 | Partial Approval | MORRIS JACKSON |
| Verify Sprinkler Sign Off | 11/5/2024 | Approved | MORRIS JACKSON |
| ELECTRICAL-Final | 11/14/2024 | Not Ready for Inspection | MORRIS JACKSON |
| Interior/Exterior Lathing | 11/14/2024 | Partial Approval | MORRIS JACKSON |
| Masonry Wall/Backfill | 11/14/2024 | Partial Inspection | MORRIS JACKSON |
| Insulation | 11/19/2024 | Approved | MORRIS JACKSON |
| Interior/Exterior Lathing | 11/19/2024 | Approved | MORRIS JACKSON |
| Drywall Nailing | 11/26/2024 | Approved | MORRIS JACKSON |
| BUILDING-Rough-Frame | 4/17/2026 | Approved | SEAN WIRCH |
| ELECTRICAL-Final | 4/17/2026 | Approved | SEAN WIRCH |
| HVAC-Final | 4/17/2026 | Approved | SEAN WIRCH |
| PLUMBING-Final | 4/17/2026 | Approved | SEAN WIRCH |
| Service/Power Release | 4/17/2026 | Approved | SEAN WIRCH |
| Smoke Detectors | 4/17/2026 | Approved | SEAN WIRCH |
| Final | 4/21/2026 | OK to Issue CofO | SEAN WIRCH |
| Green Building Final | 4/21/2026 | Approved | SEAN WIRCH |
| SGSOV-Seismic Gas S/O Valve | 4/21/2026 | SGSOV Approved | SEAN WIRCH |