4946 N SUNNYSLOPE AVE 91423
Certificate Information: 4946 N SUNNYSLOPE AVE 91423
- Application / Permit
- 22010-10000-05032
- Plan Check / Job No.
- B22LA20637
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- eplan *** PROPOSED SINGLE FAMILY DWELLING WITH ATTACHED GARAGE
- Permit Issued
- Issued on 11/17/2023
- Issuing Office
- Current Status
- CofO Issued on 12/24/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/24/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 10/27/2022 | SINA KHOSRAVI |
| Corrections Issued | 10/31/2022 | SINA KHOSRAVI |
| Quality Review Completed | 11/4/2022 | TEODORO DIAZ RODRIGUEZ |
| Applicant returned to address corrections | 2/23/2023 | SINA KHOSRAVI |
| Applicant returned to address corrections | 3/29/2023 | SINA KHOSRAVI |
| Plan Check Approved | 4/27/2023 | SINA KHOSRAVI |
| Issued | 11/17/2023 | APPLICANT |
| CofO in Progress | 9/17/2024 | MISAEL ESPARZA |
| CofO in Progress | 10/5/2024 | MISAEL ESPARZA |
| No Progress | 10/5/2024 | MISAEL ESPARZA |
| CofO in Progress | 10/5/2024 | MISAEL ESPARZA |
| CofO in Progress | 11/6/2024 | MISAEL ESPARZA |
| Permit Finaled | 12/24/2024 | RUBEN SALAS |
| Permit Finaled | 12/24/2024 | RUBEN SALAS |
| CofO Issued | 12/24/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 11/15/2022 | CARLOS AGUILERA |
| Permit | Cleared | 11/15/2022 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 11/16/2022 | CARLOS AGUILERA |
| Sewer availability | Cleared | 11/22/2022 | CARLOS AGUILERA |
| Hydrant and Access approval | Cleared | 1/16/2023 | GILBERT URREA |
| Low Impact Development | Cleared | 1/25/2023 | ERNEST TSE |
| Roof/Waste drainage to street | Cleared | 1/31/2023 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Sin,, John Paul; Lic. No.: C91162 | 122 N GRAMERCY PL LOS ANGELES, CA 90004 |
Inspector Information
| MISAEL ESPARZA, (818) 374-1169 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Sewer | 12/5/2023 | Not Ready for Inspection | MISAEL ESPARZA |
| Excavation/Setback/Form/Re-Bar | 12/15/2023 | Partial Approval | CHRISTOPHER ROJAS |
| PLUMBING-Rough | 12/15/2023 | Partial Approval | CHRISTOPHER ROJAS |
| Excavation/Setback/Form/Re-Bar | 12/29/2023 | Corrections Issued | THOMAS FINNILA |
| Footing/Foundation/Slab | 12/29/2023 | Not Ready for Inspection | THOMAS FINNILA |
| Footing/Foundation/Slab | 1/4/2024 | Corrections Issued | KIRK SANDERS |
| Excavation/Setback/Form/Re-Bar | 1/9/2024 | Approved | MISAEL ESPARZA |
| Footing/Foundation/Slab | 1/9/2024 | Approved | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 2/7/2024 | Partial Inspection | MISAEL ESPARZA |
| Wood Frame | 2/7/2024 | Corrections Issued | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 2/9/2024 | Not Ready for Inspection | MISAEL ESPARZA |
| Green Building Rough | 2/9/2024 | Not Ready for Inspection | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 3/26/2024 | Corrections Issued | MISAEL ESPARZA |
| Wood Frame | 3/26/2024 | Not Ready for Inspection | MISAEL ESPARZA |
| Deputy Wood Construction | 3/28/2024 | Conditional Approval | JUAN VALENZUELA |
| ELECTRICAL-Rough | 3/29/2024 | Corrections Issued | MISAEL ESPARZA |
| HVAC-Rough | 3/29/2024 | Not Ready for Inspection | MISAEL ESPARZA |
| PLUMBING-Rough | 3/29/2024 | Not Ready for Inspection | MISAEL ESPARZA |
| ELECTRICAL-Rough | 4/4/2024 | Partial Inspection | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 4/4/2024 | Corrections Issued | MISAEL ESPARZA |
| HVAC-Rough | 4/4/2024 | Partial Inspection | MISAEL ESPARZA |
| PLUMBING-Rough | 4/4/2024 | Corrections Issued | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 4/5/2024 | Not Ready for Inspection | MISAEL ESPARZA |
| ELECTRICAL-Rough | 4/5/2024 | Not Ready for Inspection | MISAEL ESPARZA |
| Green Building Rough | 4/5/2024 | Not Ready for Inspection | MISAEL ESPARZA |
| HVAC-Rough | 4/5/2024 | Not Ready for Inspection | MISAEL ESPARZA |
| PLUMBING-Rough | 4/5/2024 | Not Ready for Inspection | MISAEL ESPARZA |
| Verify Sprinkler Sign Off | 4/5/2024 | Not Ready for Inspection | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 4/11/2024 | Not Ready for Inspection | MISAEL ESPARZA |
| ELECTRICAL-Rough | 4/11/2024 | Approved | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 4/11/2024 | Partial Approval | MISAEL ESPARZA |
| Green Building Rough | 4/11/2024 | Not Ready for Inspection | MISAEL ESPARZA |
| HVAC-Rough | 4/11/2024 | Not Ready for Inspection | MISAEL ESPARZA |
| Interior/Exterior Lathing | 4/11/2024 | Not Ready for Inspection | MISAEL ESPARZA |
| PLUMBING-Rough | 4/11/2024 | Approved | MISAEL ESPARZA |
| Verify Sprinkler Sign Off | 4/11/2024 | Approved | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 4/16/2024 | Corrections Issued | MISAEL ESPARZA |
| Interior/Exterior Lathing | 4/16/2024 | Not Ready for Inspection | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 4/17/2024 | Not Ready for Inspection | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 4/17/2024 | Not Ready for Inspection | MISAEL ESPARZA |
| Green Building Rough | 4/17/2024 | Not Ready for Inspection | MISAEL ESPARZA |
| HVAC-Rough | 4/17/2024 | Approved | MISAEL ESPARZA |
| Interior/Exterior Lathing | 4/17/2024 | Not Ready for Inspection | MISAEL ESPARZA |
| Interior/Exterior Lathing | 4/23/2024 | Partial Approval | MISAEL ESPARZA |
| Green Building Rough | 4/25/2024 | Approved | MISAEL ESPARZA |
| Interior/Exterior Lathing | 4/25/2024 | Partial Approval | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 5/1/2024 | Approved | MISAEL ESPARZA |
| Insulation | 5/1/2024 | Corrections Issued | MISAEL ESPARZA |
| Insulation | 5/3/2024 | Approved | MISAEL ESPARZA |
| Shower Pan | 5/3/2024 | Not Ready for Inspection | MISAEL ESPARZA |
| Drywall Nailing | 5/7/2024 | Approved | MISAEL ESPARZA |
| Interior/Exterior Lathing | 5/7/2024 | Approved | MISAEL ESPARZA |
| Sewer | 7/19/2024 | Approved | MISAEL ESPARZA |
| Underground Mechanical | 7/19/2024 | Corrections Issued | MISAEL ESPARZA |
| Underground Mechanical | 7/23/2024 | Approved | VINCENT HANLEY |
| ELECTRICAL-Final | 9/5/2024 | Not Ready for Inspection | MISAEL ESPARZA |
| HVAC-Final | 9/5/2024 | Not Ready for Inspection | MISAEL ESPARZA |
| PLUMBING-Final | 9/5/2024 | Corrections Issued | MISAEL ESPARZA |
| Final | 9/10/2024 | Corrections Issued | MISAEL ESPARZA |
| Green Building Final | 9/10/2024 | Not Ready for Inspection | MISAEL ESPARZA |
| SGSOV-Seismic Gas S/O Valve | 9/10/2024 | SGSOV Approved | MISAEL ESPARZA |
| Service/Power Release | 9/10/2024 | Not Ready for Inspection | MISAEL ESPARZA |
| Smoke Detectors | 9/10/2024 | Approved | MISAEL ESPARZA |
| Final | 9/13/2024 | Corrections Issued | MISAEL ESPARZA |
| Green Building Final | 9/13/2024 | Approved | MISAEL ESPARZA |
| Service/Power Release | 9/13/2024 | Approved | MISAEL ESPARZA |
| Special/Order Compliance | 10/7/2024 | Corrections Issued | MISAEL ESPARZA |
| Final | 11/5/2024 | OK to Issue CofO | MISAEL ESPARZA |