4946 N SUNNYSLOPE AVE 91423

Certificate Information: 4946 N SUNNYSLOPE AVE 91423

Application / Permit
22010-10000-05032
Plan Check / Job No.
B22LA20637
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
eplan *** PROPOSED SINGLE FAMILY DWELLING WITH ATTACHED GARAGE
Permit Issued
Issued on 11/17/2023
Issuing Office
Current Status
CofO Issued on 12/24/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/24/2022 APPLICANT
Assigned to Plan Check Engineer 10/27/2022 SINA KHOSRAVI
Corrections Issued 10/31/2022 SINA KHOSRAVI
Quality Review Completed 11/4/2022 TEODORO DIAZ RODRIGUEZ
Applicant returned to address corrections 2/23/2023 SINA KHOSRAVI
Applicant returned to address corrections 3/29/2023 SINA KHOSRAVI
Plan Check Approved 4/27/2023 SINA KHOSRAVI
Issued 11/17/2023 APPLICANT
CofO in Progress 9/17/2024 MISAEL ESPARZA
CofO in Progress 10/5/2024 MISAEL ESPARZA
No Progress 10/5/2024 MISAEL ESPARZA
CofO in Progress 10/5/2024 MISAEL ESPARZA
CofO in Progress 11/6/2024 MISAEL ESPARZA
Permit Finaled 12/24/2024 RUBEN SALAS
Permit Finaled 12/24/2024 RUBEN SALAS
CofO Issued 12/24/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 11/15/2022 CARLOS AGUILERA
Permit Cleared 11/15/2022 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 11/16/2022 CARLOS AGUILERA
Sewer availability Cleared 11/22/2022 CARLOS AGUILERA
Hydrant and Access approval Cleared 1/16/2023 GILBERT URREA
Low Impact Development Cleared 1/25/2023 ERNEST TSE
Roof/Waste drainage to street Cleared 1/31/2023 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,
Engineer Sin,, John Paul; Lic. No.: C91162 122 N GRAMERCY PL      LOS ANGELES, CA 90004

Inspector Information

MISAEL ESPARZA, (818) 374-1169 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Sewer 12/5/2023 Not Ready for Inspection MISAEL ESPARZA
Excavation/Setback/Form/Re-Bar 12/15/2023 Partial Approval CHRISTOPHER ROJAS
PLUMBING-Rough 12/15/2023 Partial Approval CHRISTOPHER ROJAS
Excavation/Setback/Form/Re-Bar 12/29/2023 Corrections Issued THOMAS FINNILA
Footing/Foundation/Slab 12/29/2023 Not Ready for Inspection THOMAS FINNILA
Footing/Foundation/Slab 1/4/2024 Corrections Issued KIRK SANDERS
Excavation/Setback/Form/Re-Bar 1/9/2024 Approved MISAEL ESPARZA
Footing/Foundation/Slab 1/9/2024 Approved MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 2/7/2024 Partial Inspection MISAEL ESPARZA
Wood Frame 2/7/2024 Corrections Issued MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 2/9/2024 Not Ready for Inspection MISAEL ESPARZA
Green Building Rough 2/9/2024 Not Ready for Inspection MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 3/26/2024 Corrections Issued MISAEL ESPARZA
Wood Frame 3/26/2024 Not Ready for Inspection MISAEL ESPARZA
Deputy Wood Construction 3/28/2024 Conditional Approval JUAN VALENZUELA
ELECTRICAL-Rough 3/29/2024 Corrections Issued MISAEL ESPARZA
HVAC-Rough 3/29/2024 Not Ready for Inspection MISAEL ESPARZA
PLUMBING-Rough 3/29/2024 Not Ready for Inspection MISAEL ESPARZA
ELECTRICAL-Rough 4/4/2024 Partial Inspection MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 4/4/2024 Corrections Issued MISAEL ESPARZA
HVAC-Rough 4/4/2024 Partial Inspection MISAEL ESPARZA
PLUMBING-Rough 4/4/2024 Corrections Issued MISAEL ESPARZA
BUILDING-Rough-Frame 4/5/2024 Not Ready for Inspection MISAEL ESPARZA
ELECTRICAL-Rough 4/5/2024 Not Ready for Inspection MISAEL ESPARZA
Green Building Rough 4/5/2024 Not Ready for Inspection MISAEL ESPARZA
HVAC-Rough 4/5/2024 Not Ready for Inspection MISAEL ESPARZA
PLUMBING-Rough 4/5/2024 Not Ready for Inspection MISAEL ESPARZA
Verify Sprinkler Sign Off 4/5/2024 Not Ready for Inspection MISAEL ESPARZA
BUILDING-Rough-Frame 4/11/2024 Not Ready for Inspection MISAEL ESPARZA
ELECTRICAL-Rough 4/11/2024 Approved MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 4/11/2024 Partial Approval MISAEL ESPARZA
Green Building Rough 4/11/2024 Not Ready for Inspection MISAEL ESPARZA
HVAC-Rough 4/11/2024 Not Ready for Inspection MISAEL ESPARZA
Interior/Exterior Lathing 4/11/2024 Not Ready for Inspection MISAEL ESPARZA
PLUMBING-Rough 4/11/2024 Approved MISAEL ESPARZA
Verify Sprinkler Sign Off 4/11/2024 Approved MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 4/16/2024 Corrections Issued MISAEL ESPARZA
Interior/Exterior Lathing 4/16/2024 Not Ready for Inspection MISAEL ESPARZA
BUILDING-Rough-Frame 4/17/2024 Not Ready for Inspection MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 4/17/2024 Not Ready for Inspection MISAEL ESPARZA
Green Building Rough 4/17/2024 Not Ready for Inspection MISAEL ESPARZA
HVAC-Rough 4/17/2024 Approved MISAEL ESPARZA
Interior/Exterior Lathing 4/17/2024 Not Ready for Inspection MISAEL ESPARZA
Interior/Exterior Lathing 4/23/2024 Partial Approval MISAEL ESPARZA
Green Building Rough 4/25/2024 Approved MISAEL ESPARZA
Interior/Exterior Lathing 4/25/2024 Partial Approval MISAEL ESPARZA
BUILDING-Rough-Frame 5/1/2024 Approved MISAEL ESPARZA
Insulation 5/1/2024 Corrections Issued MISAEL ESPARZA
Insulation 5/3/2024 Approved MISAEL ESPARZA
Shower Pan 5/3/2024 Not Ready for Inspection MISAEL ESPARZA
Drywall Nailing 5/7/2024 Approved MISAEL ESPARZA
Interior/Exterior Lathing 5/7/2024 Approved MISAEL ESPARZA
Sewer 7/19/2024 Approved MISAEL ESPARZA
Underground Mechanical 7/19/2024 Corrections Issued MISAEL ESPARZA
Underground Mechanical 7/23/2024 Approved VINCENT HANLEY
ELECTRICAL-Final 9/5/2024 Not Ready for Inspection MISAEL ESPARZA
HVAC-Final 9/5/2024 Not Ready for Inspection MISAEL ESPARZA
PLUMBING-Final 9/5/2024 Corrections Issued MISAEL ESPARZA
Final 9/10/2024 Corrections Issued MISAEL ESPARZA
Green Building Final 9/10/2024 Not Ready for Inspection MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 9/10/2024 SGSOV Approved MISAEL ESPARZA
Service/Power Release 9/10/2024 Not Ready for Inspection MISAEL ESPARZA
Smoke Detectors 9/10/2024 Approved MISAEL ESPARZA
Final 9/13/2024 Corrections Issued MISAEL ESPARZA
Green Building Final 9/13/2024 Approved MISAEL ESPARZA
Service/Power Release 9/13/2024 Approved MISAEL ESPARZA
Special/Order Compliance 10/7/2024 Corrections Issued MISAEL ESPARZA
Final 11/5/2024 OK to Issue CofO MISAEL ESPARZA