1165 W 36TH PL 1-8 90007

Certificate Information: 1165 W 36TH PL 1-8 90007

Application / Permit
22010-10000-05003
Plan Check / Job No.
B22LA20505
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
NEW 6 STORY WITH ROOF DECK 7 UNITS (11% ELI = 1) AND ONE ACCESSORY DWELLING UNIT AFFORDABLE HOUSING APARTMENT TO INCLUDE 5 STORY TYPE IIIA APARTMENT OVER 1 STORY TYPE IA PARKING, TIER 3 TOC WITH ADDITIONAL INCENTIVE
Permit Issued
Issued on 3/9/2024
Issuing Office
Current Status
Issued on 3/9/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 10/12/2022 APPLICANT
Assigned to Plan Check Engineer 10/27/2022 STARR CHEN
Corrections Issued 11/4/2022 STARR CHEN
Quality Review Completed 11/7/2022 EUGENE BARBEAU
Applicant returned to address corrections 12/6/2022 STARR CHEN
Applicant returned to address corrections 3/3/2023 MANUEL MONTUFAR
Applicant returned to address corrections 6/13/2023 MANUEL MONTUFAR
Plan Check Approved 3/7/2024 MANUEL MONTUFAR
Issued 3/9/2024 APPLICANT

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 2/23/2023 WALLIE JONG
Address approval Cleared 3/23/2023 WALLIE JONG
Hydrant and Access approval Cleared 6/7/2023 LAVEON RIDER
Highway dedication Cleared 7/27/2023 WALLIE JONG
Permit Cleared 7/27/2023 WALLIE JONG
Sewer availability Cleared 10/3/2023 WALLIE JONG
Building over 36-ft Cleared 10/10/2023 CALOSHA APPROVED
Density Bonus 12.22.A.31 Cleared 10/23/2023 KE ZHANG
SB8 RUD Cleared 10/23/2023 KE ZHANG
Trees in Parkway Cleared 11/2/2023 ADALBERTO VERA
Fire Marshal Fire Life Safety Cleared 11/15/2023 WILLIAM JOHNS
Green Code Cleared 11/26/2023 STARR CHEN
Low Impact Development Cleared 11/27/2023 MARCO SANCHEZ
Roof/Waste drainage to street Cleared 11/30/2023 JUSTIN BICOL
DAS Clearance Cleared 1/25/2024 ELIZABETH TOMS
CPC Cleared 2/2/2024 DANIEL CORONADO
Miscellaneous Cleared 2/2/2024 DANIEL CORONADO
Miscellaneous Cleared 2/2/2024 DANIEL CORONADO
Miscellaneous Cleared 2/2/2024 DANIEL CORONADO
ZA Case Cleared 2/2/2024 DANIEL CORONADO
ZA Case Cleared 2/2/2024 DANIEL CORONADO
ZI Cleared 2/2/2024 DANIEL CORONADO
Frnt yard landscape/Water mgmt Cleared 3/4/2024 DANIEL CORONADO
Miscellaneous Cleared 3/4/2024 DANIEL CORONADO
Opn space landscape/Water mgmt Cleared 3/4/2024 DANIEL CORONADO

Contact Information

Architect Chang,, Winston L; Lic. No.: C25009 1476 VIA CORONEL      PALOS VERDES ESTATES, CA 90274
Contractor Owner-Builder       ,
Engineer Aboufadel,, Nicholas Fadlo; Lic. No.: C50588 4000 PARK NEWPORT SUITE 303      NEWPORT BEACH, CA 92660
Engineer Au,, Chi-Ming; Lic. No.: C44491 8857 ARDENDALE AVE      SAN GABRIEL, CA 91775
Engineer Smith,, Melvin Bruce; Lic. No.: GE2673 2165 N MARVEL AVE      SIMI VALLEY, CA 93065
Landscape Architect Kim,, Samuel Kyun; Lic. No.: LA3249 2669 SATURN ST      BREA, CA 92821

Inspector Information

ALFREDO LOPEZ, (213) 482-0361 Office Hours: 7:00-8:00 AM MON-FRI
JAMES POWERS, (213) 482-0361 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 7/30/2024 Partial Approval JAMES POWERS
Special/Order Compliance 8/14/2024 Partial Inspection JAMES POWERS
Deputy Reinf. Concrete 9/18/2024 Partial Approval JAMES POWERS
Excavation/Setback/Form/Re-Bar 9/19/2024 Partial Approval JAMES POWERS
Footing/Foundation/Slab 9/19/2024 Partial Approval JAMES POWERS
METHANE-Barrier 9/19/2024 Not Ready for Inspection JAMES POWERS
METHANE-Subgrade 9/19/2024 Not Ready for Inspection JAMES POWERS
Deputy Reinf. Concrete 9/23/2024 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 10/9/2024 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 10/9/2024 Not Ready for Inspection JAMES POWERS
Green Building Rough 10/9/2024 Not Ready for Inspection JAMES POWERS
METHANE-Rough 10/9/2024 Not Ready for Inspection JAMES POWERS
Reinforced Concrete Frame 10/9/2024 Partial Approval JAMES POWERS
Verify Sprinkler Sign Off 10/9/2024 Not Ready for Inspection JAMES POWERS
Deputy Reinf. Concrete 10/17/2024 Partial Approval JAMES POWERS
Excavation/Setback/Form/Re-Bar 10/18/2024 Partial Approval JAMES POWERS
Green Building Rough 10/18/2024 Not Ready for Inspection JAMES POWERS
METHANE-Rough 10/18/2024 Not Ready for Inspection JAMES POWERS
Reinforced Concrete Frame 10/18/2024 Partial Approval JAMES POWERS
Verify Sprinkler Sign Off 10/18/2024 Not Ready for Inspection JAMES POWERS
Deputy Reinf. Concrete 10/22/2024 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 10/25/2024 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 10/25/2024 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 10/30/2024 Partial Approval JAMES POWERS
Reinforced Concrete Frame 10/30/2024 Partial Approval JAMES POWERS
Reinforced Masonry Frame 10/30/2024 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 11/1/2024 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 11/1/2024 Partial Approval JAMES POWERS
Deputy Methane Barrier 12/10/2024 Partial Approval JAMES POWERS
Deputy Methane Barrier 12/19/2024 Partial Approval JAMES POWERS
Footing/Foundation/Slab 12/23/2024 Partial Approval RAMAZANALI ALMASI
METHANE-Barrier 12/23/2024 Partial Approval RAMAZANALI ALMASI
METHANE-Subgrade 12/23/2024 Partial Approval RAMAZANALI ALMASI
Excavation/Setback/Form/Re-Bar 1/27/2025 Not Ready for Inspection LARRY ARNICK
Footing/Foundation/Slab 1/27/2025 Not Ready for Inspection LARRY ARNICK
Green Building Rough 1/27/2025 Not Ready for Inspection LARRY ARNICK
METHANE-Barrier 1/27/2025 Not Ready for Inspection LARRY ARNICK
METHANE-Rough 1/27/2025 Not Ready for Inspection LARRY ARNICK
METHANE-Subgrade 1/27/2025 Not Ready for Inspection LARRY ARNICK
Reinforced Concrete Frame 1/27/2025 Not Ready for Inspection LARRY ARNICK
Verify Sprinkler Sign Off 1/27/2025 Not Ready for Inspection LARRY ARNICK
Deputy Reinf. Concrete 2/4/2025 Partial Approval JAMES POWERS
Footing/Foundation/Slab 2/4/2025 Partial Approval JAMES POWERS
Green Building Rough 2/4/2025 Not Ready for Inspection JAMES POWERS
METHANE-Barrier 2/4/2025 Not Ready for Inspection JAMES POWERS
METHANE-Rough 2/4/2025 Not Ready for Inspection JAMES POWERS
METHANE-Subgrade 2/4/2025 Not Ready for Inspection JAMES POWERS
Reinforced Concrete Frame 2/4/2025 Partial Approval JAMES POWERS
Verify Sprinkler Sign Off 2/4/2025 Not Ready for Inspection JAMES POWERS
Deputy Reinf. Concrete 2/18/2025 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 3/3/2025 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 3/5/2025 Partial Approval JAMES POWERS
Excavation/Setback/Form/Re-Bar 3/5/2025 Not Ready for Inspection JAMES POWERS
Green Building Rough 3/5/2025 Not Ready for Inspection JAMES POWERS
METHANE-Rough 3/5/2025 Not Ready for Inspection JAMES POWERS
Reinforced Concrete Frame 3/5/2025 Not Ready for Inspection JAMES POWERS
Verify Sprinkler Sign Off 3/5/2025 Not Ready for Inspection JAMES POWERS
Reinforced Concrete Frame 3/7/2025 Partial Approval JAMES POWERS
Wood Frame 3/13/2025 Not Ready for Inspection JAMES POWERS
Deputy Wood Construction 3/14/2025 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 3/21/2025 Partial Approval JAMES POWERS
Deputy Wood Construction 4/1/2025 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 4/2/2025 Partial Approval JAMES POWERS
Deputy Wood Construction 4/24/2025 Conditional Approval LARRY ARNICK
Floor/Roof Diaphrgm/Shear Wall 4/24/2025 Partial Approval LARRY ARNICK
Deputy Wood Construction 5/22/2025 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 5/23/2025 Partial Approval JAMES POWERS
Deputy Wood Construction 7/10/2025 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 7/11/2025 Partial Approval JAMES POWERS
Deputy Wood Construction 9/8/2025 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 9/9/2025 Not Ready for Inspection JAMES POWERS
Deputy Wood Construction 9/18/2025 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 9/19/2025 Partial Approval JAMES POWERS
Deputy Wood Construction 10/3/2025 Partial Approval JAMES POWERS
Drywall Nailing 10/6/2025 Not Ready for Inspection JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 10/6/2025 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 10/9/2025 Partial Approval JAMES POWERS
Drywall Nailing 10/21/2025 Partial Approval JOEY BUCHANAN
Floor/Roof Diaphrgm/Shear Wall 10/21/2025 Partial Approval JOEY BUCHANAN
Drywall Nailing 10/29/2025 Partial Approval JAMES POWERS
Deputy Other (see comments) 11/6/2025 Partial Approval SCOTT SOBEL
Deputy Wood Construction 11/6/2025 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 11/7/2025 Partial Approval JAMES POWERS
Insulation 11/19/2025 Partial Approval JAMES POWERS
Insulation 12/2/2025 Partial Approval JAMES POWERS
Insulation 1/7/2026 Partial Approval JAMES POWERS
Insulation 1/9/2026 Partial Approval JAMES POWERS
Wood Frame 3/6/2026 Approved JAMES POWERS
Drywall Nailing 3/26/2026 Partial Approval JAMES POWERS
Drywall Nailing 4/21/2026 Partial Approval JAMES POWERS
Light Gage Steel Frame 4/21/2026 Partial Approval JAMES POWERS
Drywall Nailing 5/20/2026 Partial Approval JAMES POWERS
Interior/Exterior Lathing 5/20/2026 Not Ready for Inspection JAMES POWERS
Interior/Exterior Lathing 6/18/2026 Approved JAMES POWERS
Verify Rec and Parks Fee Memo 6/29/2026 Not Ready for Inspection JAMES POWERS