3569 N CANADA ST 90065

Certificate Information: 3569 N CANADA ST 90065

Application / Permit
22010-10000-04984
Plan Check / Job No.
B22LA20378
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW SFD PER SB9 TWO UNIT DEVELOPMENT (1-STORY)
Permit Issued
Issued on 1/23/2025
Issuing Office
Current Status
Issued on 1/23/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 10/10/2022 APPLICANT
Assigned to Plan Check Engineer 10/27/2022 CARLOS MONTES
Corrections Issued 10/31/2022 CARLOS MONTES
Quality Review Completed 11/8/2022 GARO TELMI
Applicant returned to address corrections 2/3/2023 CARLOS MONTES
Plan Check Approved 2/14/2024 CARLOS MONTES
Issued 1/23/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 11/12/2022 CHRISTOPHER ROCHA
BHO/Hillside ordinance Cleared 11/12/2022 CHRISTOPHER ROCHA
BHO/Hillside ordinance Cleared 11/12/2022 CHRISTOPHER ROCHA
BHO/Hillside ordinance Cleared 11/12/2022 CHRISTOPHER ROCHA
BHO/Hillside ordinance Cleared 11/12/2022 CHRISTOPHER ROCHA
BHO/Hillside ordinance Cleared 11/12/2022 CHRISTOPHER ROCHA
Distance to fire station Cleared 11/26/2022 JOHN CONNEALLY
Hydrant and Access approval Cleared 11/26/2022 JOHN CONNEALLY
Eng Process Fee Ord 176,300 Cleared 11/30/2022 CHRISTOPHER ROCHA
Sewer availability Cleared 11/30/2022 CHRISTOPHER ROCHA
Senate Bill 9 Cleared 9/8/2023 JASON CHAN
Low Impact Development Cleared 12/11/2023 ROGELIO CORTES
Roof/Waste drainage to street Cleared 12/20/2023 ARNULFO CHAMU
Specific Plan Cleared 1/17/2024 PABLO ESTRADA
GPI Written Notices Cleared 2/14/2024 CARLOS MONTES
Grading Pre-Inspection Cleared 2/14/2024 ROBERT HUGHES

Contact Information

Architect Kajer,, Georgia; Lic. No.: NA21712       ,
Contractor Owner-Builder       ,
Engineer Lu,, Ining; Lic. No.: NA3042       ,

Inspector Information

NICHOLAS LOPEZ, (213) 202-3224 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 4/7/2025 Not Ready for Inspection NICHOLAS LOPEZ
Pre-Inspection 4/7/2025 Partial Inspection NICHOLAS LOPEZ
Excavation/Setback/Form/Re-Bar 4/9/2025 Partial Approval NICHOLAS LOPEZ
Piling/Pier/Caisson 4/9/2025 Approved NICHOLAS LOPEZ
Footing/Foundation/Slab 6/12/2025 Conditional Approval NICHOLAS LOPEZ
Footing/Foundation/Slab 7/17/2025 No Access for Inspection NICHOLAS LOPEZ
Excavation/Setback/Form/Re-Bar 7/18/2025 Corrections Issued NICHOLAS LOPEZ
Footing/Foundation/Slab 7/22/2025 Approved NICHOLAS LOPEZ
Floor/Roof Diaphrgm/Shear Wall 10/15/2025 Corrections Issued NICHOLAS LOPEZ
Deputy Wood Construction 10/22/2025 Conditional Approval NICHOLAS LOPEZ
BUILDING-Rough-Frame 1/29/2026 Approved NICHOLAS LOPEZ
ELECTRICAL-Rough 1/29/2026 Approved NICHOLAS LOPEZ
Floor/Roof Diaphrgm/Shear Wall 1/29/2026 Approved NICHOLAS LOPEZ
Green Building Rough 1/29/2026 Approved NICHOLAS LOPEZ
HVAC-Rough 1/29/2026 Corrections Issued NICHOLAS LOPEZ
Interior/Exterior Lathing 1/29/2026 Partial Approval NICHOLAS LOPEZ
PLUMBING-Rough 1/29/2026 Approved NICHOLAS LOPEZ
Verify Sprinkler Sign Off 1/29/2026 Approved NICHOLAS LOPEZ
HVAC-Rough 2/10/2026 Approved NICHOLAS LOPEZ
Insulation 2/10/2026 Approved NICHOLAS LOPEZ
Drywall Nailing 2/17/2026 Approved NICHOLAS LOPEZ
Gas Test 3/9/2026 Approved NICHOLAS LOPEZ
Underground Mechanical 3/19/2026 Partial Approval NICHOLAS LOPEZ
Sewer 4/2/2026 Approved NICHOLAS LOPEZ
Underground Mechanical 4/2/2026 Approved NICHOLAS LOPEZ