15408 W LULL ST 91406
Certificate Information: 15408 W LULL ST 91406
- Application / Permit
- 22010-10000-04936
- Plan Check / Job No.
- B22VN13509
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN NEW DET. 2-STORY ADU PER LAMC 12.22 A.33 (c)-(d) (REAR LOT)
- Permit Issued
- Issued on 10/16/2023
- Issuing Office
- Current Status
- CofO Issued on 4/15/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/9/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 9/29/2022 | MAHNAZ NOURHASHEMI |
| Corrections Issued | 10/6/2022 | MAHNAZ NOURHASHEMI |
| Quality Review Completed | 10/19/2022 | TEODORO DIAZ RODRIGUEZ |
| Applicant returned to address corrections | 4/18/2023 | MAHNAZ NOURHASHEMI |
| Applicant returned to address corrections | 6/5/2023 | MAHNAZ NOURHASHEMI |
| Plan Check Approved | 10/4/2023 | MAHNAZ NOURHASHEMI |
| Plan Check Approved | 10/16/2023 | MAHNAZ NOURHASHEMI |
| Issued | 10/16/2023 | APPLICANT |
| CofO in Progress | 3/27/2025 | VINCENT HANLEY |
| Permit Finaled | 4/15/2025 | RUBEN SALAS |
| CofO Issued | 4/15/2025 | RUBEN SALAS |
| Permit Finaled | 4/15/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 5/24/2023 | LEE GUILBEAUX |
| Miscellaneous | Cleared | 5/24/2023 | LEE GUILBEAUX |
| Hydrant and Access approval | Cleared | 7/20/2023 | KURT CORRAL |
| Eng Process Fee Ord 176,300 | Cleared | 9/25/2023 | NIKKI ZULUETA |
| Sewer availability | Cleared | 9/25/2023 | NIKKI ZULUETA |
| Low Impact Development | Cleared | 9/26/2023 | TOMMY YIN |
| Roof/Waste drainage to street | Cleared | 9/26/2023 | COLIN LOREDO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Um,, Bin; Lic. No.: C59287 | 2708 FOOTHILL BLVD #205 LA CRESCENTA, CA 91214 |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 3/13/2024 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Pre-Inspection | 3/13/2024 | Partial Approval | CHRISTOPHER ROJAS |
| Excavation/Setback/Form/Re-Bar | 3/22/2024 | Not Ready for Inspection | JOHN COLEMAN |
| Underground Mechanical | 3/22/2024 | Conditional Approval | JOHN COLEMAN |
| Footing/Foundation/Slab | 3/29/2024 | Approved | KIRK SANDERS |
| PLUMBING-Rough | 4/4/2024 | Partial Approval | MATTHEW NELSON |
| Floor/Roof Diaphrgm/Shear Wall | 4/15/2024 | Corrections Issued | KIRK SANDERS |
| BUILDING-Rough-Frame | 4/17/2024 | Not Ready for Inspection | DAVID ANDERSON |
| Floor/Roof Diaphrgm/Shear Wall | 4/17/2024 | Partial Approval | DAVID ANDERSON |
| Green Building Rough | 4/17/2024 | Not Ready for Inspection | DAVID ANDERSON |
| Verify Sprinkler Sign Off | 4/17/2024 | Approved | DAVID ANDERSON |
| Floor/Roof Diaphrgm/Shear Wall | 4/25/2024 | Corrections Issued | WILLIAM WREN |
| Green Building Rough | 4/25/2024 | Not Ready for Inspection | WILLIAM WREN |
| Floor/Roof Diaphrgm/Shear Wall | 5/1/2024 | Corrections Issued | KIRK SANDERS |
| Green Building Rough | 5/1/2024 | Not Ready for Inspection | KIRK SANDERS |
| PLUMBING-Rough | 5/3/2024 | Corrections Issued | KIRK SANDERS |
| HVAC-Final | 5/10/2024 | Corrections Issued | KIRK SANDERS |
| PLUMBING-Rough | 5/10/2024 | Approved | KIRK SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 5/28/2024 | Corrections Issued | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 6/3/2024 | Partial Approval | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 7/9/2024 | Not Ready for Inspection | VINCENT HANLEY |
| Interior/Exterior Lathing | 7/9/2024 | Corrections Issued | VINCENT HANLEY |
| ELECTRICAL-Rough | 8/16/2024 | Corrections Issued | DAVID ANDERSON |
| Wood Frame | 8/16/2024 | Not Ready for Inspection | DAVID ANDERSON |
| ELECTRICAL-Rough | 8/28/2024 | Approved | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 8/28/2024 | Approved | VINCENT HANLEY |
| Green Building Rough | 8/28/2024 | Not Ready for Inspection | VINCENT HANLEY |
| HVAC-Rough | 8/28/2024 | Not Ready for Inspection | VINCENT HANLEY |
| BUILDING-Rough-Frame | 10/1/2024 | Approved | VINCENT HANLEY |
| Green Building Rough | 10/1/2024 | Approved | VINCENT HANLEY |
| HVAC-Rough | 10/1/2024 | Approved | VINCENT HANLEY |
| Interior/Exterior Lathing | 10/1/2024 | Partial Approval | VINCENT HANLEY |
| Insulation | 10/15/2024 | Approved | MICHAEL CORTEZ |
| Drywall Nailing | 11/7/2024 | Approved | VINCENT HANLEY |
| Shower Pan | 11/7/2024 | Approved | VINCENT HANLEY |
| Interior/Exterior Lathing | 11/14/2024 | Approved | VINCENT HANLEY |
| Final | 3/25/2025 | Corrections Issued | VINCENT HANLEY |
| Green Building Final | 3/25/2025 | Approved | VINCENT HANLEY |
| SGSOV-Seismic Gas S/O Valve | 3/25/2025 | SGSOV Approved | VINCENT HANLEY |
| Service/Power Release | 3/25/2025 | Approved | VINCENT HANLEY |
| Smoke Detectors | 3/25/2025 | Approved | VINCENT HANLEY |
| Service/Power Release | 3/26/2025 | Approved | VINCENT HANLEY |
| Verify Rec and Parks Fee Memo | 3/26/2025 | Approved | VINCENT HANLEY |
| Final | 3/27/2025 | OK to Issue CofO | VINCENT HANLEY |