5501 1/2 E POPLAR BLVD 90032

Certificate Information: 5501 1/2 E POPLAR BLVD 90032

Application / Permit
22010-10000-04935
Plan Check / Job No.
B22LA20143
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
eplan (N) DETACHED ADU PER GCS 65852.2(e)(1)(B) & LAMC 12.22 A.33(c),(d),(g).
Permit Issued
Issued on 3/28/2023
Issuing Office
Current Status
CofO Issued on 7/24/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/7/2022 APPLICANT
Assigned to Plan Check Engineer 10/13/2022 MAHNAZ NOURHASHEMI
Corrections Issued 11/19/2022 MAHNAZ NOURHASHEMI
Quality Review Completed 11/23/2022 GARO TELMI
Applicant returned to address corrections 1/4/2023 MAHNAZ NOURHASHEMI
Plan Check Approved 1/10/2023 MAHNAZ NOURHASHEMI
Issued 3/28/2023 APPLICANT
CofO in Progress 7/17/2025 ALIZAH MAYAGOITIA
Permit Finaled 7/24/2025 DEROLD HAUFF
CofO Issued 7/24/2025 DEROLD HAUFF
Permit Finaled 7/24/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 11/23/2022 CINDY QI
Roof/Waste drainage to street Cleared 11/23/2022 CINDY QI
Hydrant and Access approval Cleared 12/3/2022 JOHN CONNEALLY
Eng Process Fee Ord 176,300 Cleared 12/5/2022 CINDY QI
Sewer availability Cleared 12/5/2022 CINDY QI
GPI Written Notices Cleared 1/4/2023 MAHNAZ NOURHASHEMI
Grading Pre-Inspection Cleared 1/4/2023 MAHNAZ NOURHASHEMI

Contact Information

Contractor Owner-Builder       ,
Engineer Phillips,, Craig; Lic. No.: NA69673       ,

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 9/18/2023 Partial Inspection AMY COLIN
Excavation/Setback/Form/Re-Bar 11/3/2023 Corrections Issued AMY COLIN
Footing/Foundation/Slab 11/3/2023 Corrections Issued AMY COLIN
PLUMBING-Rough 11/3/2023 Partial Approval AMY COLIN
Underground Mechanical 11/3/2023 Not Ready for Inspection AMY COLIN
Footing/Foundation/Slab 11/8/2023 Not Ready for Inspection HAMIK HARTOUNIAN
Footing/Foundation/Slab 11/13/2023 Approved ROY SPAULDING
Pre-Inspection 11/13/2023 Partial Approval ROY SPAULDING
Floor/Roof Diaphrgm/Shear Wall 12/14/2023 Partial Approval AMY COLIN
BUILDING-Rough-Frame 1/30/2024 Partial Approval CRAIG VAUGHAN
ELECTRICAL-Rough 1/30/2024 Not Ready for Inspection CRAIG VAUGHAN
Floor/Roof Diaphrgm/Shear Wall 1/30/2024 Partial Approval CRAIG VAUGHAN
HVAC-Rough 1/30/2024 Not Ready for Inspection CRAIG VAUGHAN
PLUMBING-Rough 1/30/2024 Approved CRAIG VAUGHAN
Sewer 1/30/2024 Approved CRAIG VAUGHAN
Verify Sprinkler Sign Off 1/30/2024 Approved CRAIG VAUGHAN
BUILDING-Rough-Frame 2/28/2024 Not Ready for Inspection CRAIG VAUGHAN
ELECTRICAL-Rough 2/28/2024 Not Ready for Inspection CRAIG VAUGHAN
HVAC-Rough 2/28/2024 Not Ready for Inspection CRAIG VAUGHAN
ELECTRICAL-Rough 3/1/2024 Corrections Issued LILIANA PORTILLO
HVAC-Rough 3/1/2024 Corrections Issued LILIANA PORTILLO
BUILDING-Rough-Frame 3/22/2024 Approved LILIANA PORTILLO
ELECTRICAL-Rough 3/22/2024 Partial Approval LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 3/22/2024 Approved LILIANA PORTILLO
HVAC-Rough 3/22/2024 Approved LILIANA PORTILLO
Insulation 4/2/2024 Approved JOSH MEISTER
Drywall Nailing 4/10/2024 Approved LILIANA PORTILLO
Interior/Exterior Lathing 4/10/2024 Partial Approval LILIANA PORTILLO
Underground Mechanical 4/10/2024 Approved LILIANA PORTILLO
Interior/Exterior Lathing 4/24/2024 Approved LILIANA PORTILLO
ELECTRICAL-Final 1/24/2025 Not Ready for Inspection LILIANA PORTILLO
Final 1/24/2025 Corrections Issued LILIANA PORTILLO
HVAC-Final 1/24/2025 Not Ready for Inspection LILIANA PORTILLO
PLUMBING-Final 1/24/2025 Not Ready for Inspection LILIANA PORTILLO
SGSOV-Seismic Gas S/O Valve 1/24/2025 SGSOV Not Required LILIANA PORTILLO
Service/Power Release 1/24/2025 Not Ready for Inspection LILIANA PORTILLO
Smoke Detectors 1/24/2025 Not Ready for Inspection LILIANA PORTILLO
ELECTRICAL-Final 6/17/2025 Corrections Issued LILIANA PORTILLO
Final 6/17/2025 Corrections Issued LILIANA PORTILLO
HVAC-Final 6/17/2025 Approved LILIANA PORTILLO
PLUMBING-Final 6/17/2025 Approved LILIANA PORTILLO
Service/Power Release 6/17/2025 Not Ready for Inspection LILIANA PORTILLO
Smoke Detectors 6/17/2025 Approved LILIANA PORTILLO
ELECTRICAL-Final 7/16/2025 Approved ALIZAH MAYAGOITIA
Final 7/16/2025 OK to Issue CofO ALIZAH MAYAGOITIA