3362 W GARDEN AVE 90039

Certificate Information: 3362 W GARDEN AVE 90039

Application / Permit
22010-10000-04919
Plan Check / Job No.
B22LA20095
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW ACCESSORY BUILDING, RECROOM AND DETACHED ADU PER ORDINANCE (1-STORY)
Permit Issued
Issued on 9/19/2023
Issuing Office
Metro
Current Status
CofO Issued on 5/10/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/5/2022 APPLICANT
Assigned to Plan Check Engineer 10/20/2022 CARLOS MONTES
Corrections Issued 10/27/2022 CARLOS MONTES
Quality Review Completed 11/2/2022 KEN GILL
Building Plans Picked Up 11/7/2022 APPLICANT
Plan Check Approved 5/25/2023 CARLOS MONTES
Issued 9/19/2023 APPLICANT
CofO in Progress 5/7/2025 NICHOLAS LOPEZ
Permit Finaled 5/10/2025 DEROLD HAUFF
CofO Issued 5/10/2025 DEROLD HAUFF
Permit Finaled 5/10/2025 DEROLD HAUFF

Permit Application Clearance Information

Miscellaneous Cleared 11/23/2022 KIRK LINKLATER
Address approval Cleared 12/29/2022 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 1/5/2023 CELINA MORENO
Sewer availability Cleared 1/5/2023 CELINA MORENO
Construction near power lines Cleared 2/3/2023 RIDWAN HARDY
ZI Cleared 2/6/2023 LOUIS ORTEGA
Low Impact Development Cleared 4/24/2023 ANTHONY VARGAS
Roof/Waste drainage to street Cleared 4/27/2023 CELINA MORENO

Contact Information

Contractor Owner-Builder       ,
Engineer Phan,, Phillip Trung Tri; Lic. No.: C76425 641 S ALMIRANTE DR      WEST COVINA, CA 91791

Inspector Information

NICHOLAS LOPEZ, (213) 202-3224 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 1/3/2024 Partial Approval HAMIK HARTOUNIAN
Footing/Foundation/Slab 1/9/2024 Approved HAMIK HARTOUNIAN
Pre-Inspection 2/1/2024 Not Ready for Inspection HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 2/9/2024 Partial Approval HAMIK HARTOUNIAN
PLUMBING-Rough 2/9/2024 Approved HAMIK HARTOUNIAN
BUILDING-Rough-Frame 3/13/2024 Partial Approval SCOTT FINNILA
ELECTRICAL-Rough 3/13/2024 Approved SCOTT FINNILA
Green Building Rough 3/13/2024 Approved SCOTT FINNILA
Underground Mechanical 3/13/2024 Partial Approval SCOTT FINNILA
Insulation 4/22/2024 Approved HAMIK HARTOUNIAN
Interior/Exterior Lathing 4/22/2024 Partial Approval HAMIK HARTOUNIAN
Drywall Nailing 5/16/2024 Corrections Issued THOMAS LOGRASSO
Shower Pan 5/16/2024 Approved THOMAS LOGRASSO
Drywall Nailing 5/21/2024 Approved THOMAS LOGRASSO
Interior/Exterior Lathing 5/21/2024 Approved THOMAS LOGRASSO
BUILDING-Rough-Frame 4/3/2025 Approved NICHOLAS LOPEZ
Final 4/3/2025 Corrections Issued NICHOLAS LOPEZ
Green Building Final 4/3/2025 Corrections Issued NICHOLAS LOPEZ
SGSOV-Seismic Gas S/O Valve 4/3/2025 SGSOV Not Ready NICHOLAS LOPEZ
Service/Power Release 4/3/2025 Not Ready for Inspection NICHOLAS LOPEZ
Smoke Detectors 4/3/2025 Approved NICHOLAS LOPEZ
Final 4/18/2025 Corrections Issued NICHOLAS LOPEZ
Green Building Final 4/18/2025 Approved NICHOLAS LOPEZ
SGSOV-Seismic Gas S/O Valve 4/18/2025 SGSOV Approved NICHOLAS LOPEZ
Service/Power Release 4/18/2025 Not Ready for Inspection NICHOLAS LOPEZ
Final 5/7/2025 OK to Issue CofO NICHOLAS LOPEZ
Service/Power Release 5/7/2025 Not Required NICHOLAS LOPEZ