3313 W 48TH ST 90043
Certificate Information: 3313 W 48TH ST 90043
- Application / Permit
- 22010-10000-04916
- Plan Check / Job No.
- B22LA17351
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW DETACHED ADU PER ORDINANCE (2-STORY)
- Permit Issued
- Issued on 6/25/2025
- Issuing Office
- Current Status
- Issued on 6/25/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 9/12/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 9/29/2022 | CARLOS MONTES |
| Corrections Issued | 10/5/2022 | CARLOS MONTES |
| Quality Review Completed | 10/9/2022 | PRANITA SHAH |
| Applicant returned to address corrections | 2/23/2023 | CARLOS MONTES |
| Applicant returned to address corrections | 9/21/2023 | CARLOS MONTES |
| Plan Check Approved | 11/30/2023 | CARLOS MONTES |
| Issued | 6/25/2025 | APPLICANT |
Permit Application Clearance Information
| Miscellaneous | Cleared | 10/20/2022 | SPENCER WEJROWSKI |
| ZA Case | Cleared | 10/20/2022 | SPENCER WEJROWSKI |
| Community Plan Implem. Overlay | Cleared | 11/15/2022 | TREVOR QUAN |
| Construction near power lines | Cleared | 12/17/2022 | RIDWAN HARDY |
| Address approval | Cleared | 4/3/2023 | TREVOR QUAN |
| Low Impact Development | Cleared | 5/11/2023 | SUNG JOON WON |
| Eng Process Fee Ord 176,300 | Cleared | 8/15/2023 | TREVOR QUAN |
| Sewer availability | Cleared | 8/15/2023 | TREVOR QUAN |
| Roof/Waste drainage to street | Cleared | 8/20/2023 | AHMED AMARRAGY |
| Community Plan Implem. Overlay | Cleared | 10/6/2023 | KYLE WINSTON |
| SB8 RUD | Cleared | 10/7/2023 | RICHARD TRUONG |
| Community Plan Implem. Overlay | Cleared | 10/10/2023 | TAIMOUR TANAVOLI |
| Opn space landscape/Water mgmt | Cleared | 11/14/2023 | RUBEN VASQUEZ |
Contact Information
| Contractor | D C L S Construction Corporation; Lic. No.: 1077284-B | , |
| Engineer | Kim,, Hosang; Lic. No.: NA67288 | , |
Inspector Information
| LUIS CASTRO, (213) 202-3436 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 8/28/2025 | Partial Approval | LUIS CASTRO |
| Excavation/Setback/Form/Re-Bar | 9/5/2025 | Approved | LUIS CASTRO |
| Footing/Foundation/Slab | 9/5/2025 | Approved | LUIS CASTRO |
| Wood Frame | 12/31/2025 | Partial Approval | ANTHONY RAMOS |
| Floor/Roof Diaphrgm/Shear Wall | 1/13/2026 | Partial Approval | LUIS CASTRO |
| Floor/Roof Diaphrgm/Shear Wall | 1/26/2026 | Partial Approval | LUIS CASTRO |
| Floor/Roof Diaphrgm/Shear Wall | 2/2/2026 | Not Ready for Inspection | LUIS CASTRO |
| Floor/Roof Diaphrgm/Shear Wall | 2/3/2026 | Corrections Issued | LUIS CASTRO |
| ELECTRICAL-Rough | 3/26/2026 | Corrections Issued | LUIS CASTRO |
| Interior/Exterior Lathing | 3/26/2026 | Partial Approval | LUIS CASTRO |
| Special/Order Compliance | 3/31/2026 | Approved | LUIS CASTRO |
| HVAC-Rough | 4/29/2026 | Corrections Issued | LUIS CASTRO |
| Shower Pan | 5/4/2026 | Not Ready for Inspection | LUIS CASTRO |
| Interior/Exterior Lathing | 5/18/2026 | Approved | RAUL BARAJAS |
| PLUMBING-Rough | 5/18/2026 | Approved | RAUL BARAJAS |
| BUILDING-Rough-Frame | 5/29/2026 | Approved | LUIS CASTRO |
| ELECTRICAL-Rough | 5/29/2026 | Approved | LUIS CASTRO |
| Green Building Rough | 5/29/2026 | Approved | LUIS CASTRO |
| HVAC-Rough | 5/29/2026 | Approved | LUIS CASTRO |
| Verify Sprinkler Sign Off | 5/29/2026 | Approved | LUIS CASTRO |