3307-3307 1/2 W 48TH ST 90043

Certificate Information: 3307-3307 1/2 W 48TH ST 90043

Application / Permit
22010-10000-04915
Plan Check / Job No.
B22LA17351
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
NEW DUPLEX WITH RECROOM (3-STORY) AT REAR
Permit Issued
Issued on 6/25/2025
Issuing Office
Current Status
Issued on 6/25/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 9/12/2022 APPLICANT
Assigned to Plan Check Engineer 9/29/2022 CARLOS MONTES
Corrections Issued 10/5/2022 CARLOS MONTES
Quality Review Completed 10/9/2022 PRANITA SHAH
Applicant returned to address corrections 2/23/2023 CARLOS MONTES
Applicant returned to address corrections 9/21/2023 CARLOS MONTES
Plan Check Approved 11/30/2023 CARLOS MONTES
Issued 6/25/2025 APPLICANT

Permit Application Clearance Information

Miscellaneous Cleared 10/20/2022 SPENCER WEJROWSKI
ZA Case Cleared 10/20/2022 SPENCER WEJROWSKI
Highway dedication Cleared 1/3/2023 TREVOR QUAN
Address approval Cleared 2/14/2023 TREVOR QUAN
Community Plan Implem. Overlay Cleared 2/14/2023 TREVOR QUAN
Low Impact Development Cleared 5/11/2023 SUNG JOON WON
Hydrant and Access approval Cleared 8/11/2023 KURT CORRAL
Eng Process Fee Ord 176,300 Cleared 8/15/2023 TREVOR QUAN
Sewer availability Cleared 8/15/2023 TREVOR QUAN
Roof/Waste drainage to street Cleared 8/29/2023 AHMED AMARRAGY
Building over 36-ft Cleared 9/21/2023 CALOSHA APPROVED
Community Plan Implem. Overlay Cleared 10/6/2023 KYLE WINSTON
SB8 RUD Cleared 10/7/2023 RICHARD TRUONG
Community Plan Implem. Overlay Cleared 10/10/2023 TAIMOUR TANAVOLI
Frnt yard landscape/Water mgmt Cleared 11/13/2023 RUBEN VASQUEZ
Opn space landscape/Water mgmt Cleared 11/13/2023 RUBEN VASQUEZ

Contact Information

Contractor D C L S Construction Corporation; Lic. No.: 1077284-B       ,
Engineer Kim,, Hosang; Lic. No.: NA67288       ,

Inspector Information

LUIS CASTRO, (213) 202-3436 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 9/2/2025 Partial Approval LUIS CASTRO
Excavation/Setback/Form/Re-Bar 9/5/2025 Approved LUIS CASTRO
Footing/Foundation/Slab 9/5/2025 Partial Approval LUIS CASTRO
Floor/Roof Diaphrgm/Shear Wall 9/30/2025 Partial Approval LUIS CASTRO
Floor/Roof Diaphrgm/Shear Wall 10/21/2025 Partial Approval LUIS CASTRO
Floor/Roof Diaphrgm/Shear Wall 11/3/2025 Partial Approval LUIS CASTRO
Floor/Roof Diaphrgm/Shear Wall 2/2/2026 Not Ready for Inspection LUIS CASTRO
ELECTRICAL-Rough 3/26/2026 Corrections Issued LUIS CASTRO
Interior/Exterior Lathing 3/26/2026 Partial Approval LUIS CASTRO
PLUMBING-Rough 4/20/2026 Approved LUIS CASTRO
HVAC-Rough 4/27/2026 Approved LUIS CASTRO
Shower Pan 5/4/2026 Approved LUIS CASTRO
Interior/Exterior Lathing 5/18/2026 Approved RAUL BARAJAS
BUILDING-Rough-Frame 5/29/2026 Corrections Issued LUIS CASTRO
ELECTRICAL-Rough 5/29/2026 Approved LUIS CASTRO
Green Building Rough 5/29/2026 Approved LUIS CASTRO
Verify Sprinkler Sign Off 5/29/2026 Approved LUIS CASTRO
Insulation 6/9/2026 Conditional Approval LUIS CASTRO
Drywall Nailing 7/2/2026 Approved LUIS CASTRO