8614 W FENNELL PL 90069
Certificate Information: 8614 W FENNELL PL 90069
- Application / Permit
- 22010-10000-04912
- Plan Check / Job No.
- B22LA20072
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- eplan Construction of New 2-story Single Family Residence with 1 level of basement garage of 5-cars NFPA 13R SPRINKLERD THROUGH OUT TYPE VA CONSTRUCTION
- Permit Issued
- Issued on 2/11/2025
- Issuing Office
- Current Status
- Issued on 2/11/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 10/13/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 10/27/2022 | JAD BASMA |
| Corrections Issued | 10/29/2022 | JAD BASMA |
| Quality Review Completed | 11/4/2022 | TEODORO DIAZ RODRIGUEZ |
| Applicant returned to address corrections | 2/14/2024 | JAD BASMA |
| Applicant returned to address corrections | 6/14/2024 | JAD BASMA |
| Applicant returned to address corrections | 6/28/2024 | JAD BASMA |
| Applicant returned to address corrections | 7/11/2024 | JAD BASMA |
| Applicant returned to address corrections | 7/30/2024 | JAD BASMA |
| Applicant returned to address corrections | 8/23/2024 | JAD BASMA |
| Applicant returned to address corrections | 1/8/2025 | JAD BASMA |
| Plan Check Approved | 1/9/2025 | JAD BASMA |
| Plan Check Approved | 1/17/2025 | JAD BASMA |
| Issued | 2/11/2025 | APPLICANT |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 11/29/2022 | CINDY QI |
| BHO/Hillside ordinance | Cleared | 11/29/2022 | CINDY QI |
| BHO/Hillside ordinance | Cleared | 11/29/2022 | CINDY QI |
| BHO/Hillside ordinance | Cleared | 11/29/2022 | CINDY QI |
| Eng Process Fee Ord 176,300 | Cleared | 2/7/2023 | CINDY QI |
| Sewer availability | Cleared | 2/9/2023 | CINDY QI |
| Hydrant and Access approval | Cleared | 6/3/2024 | KURT CORRAL |
| Excavation more than 5-ft deep | Cleared | 6/26/2024 | CALOSHA APPROVED |
| GPI Written Notices | Cleared | 6/26/2024 | JAD BASMA |
| Grading Pre-Inspection | Cleared | 6/26/2024 | JAD BASMA |
| Haul Route | Cleared | 6/26/2024 | JAD BASMA |
| ZA Case | Cleared | 7/3/2024 | YINGSHI HUANG |
| Low Impact Development | Cleared | 8/23/2024 | LUIS LUVANO |
| BHO/Hillside ordinance | Cleared | 8/27/2024 | ALBERT TAM |
| Roof/Waste drainage to street | Cleared | 8/28/2024 | CELINA MORENO |
| Hold | Cleared | 3/19/2025 | TERESA RIVAS |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 2/20/2025 | Not Ready for Inspection | ROY SPAULDING |
| Pre-Inspection | 2/20/2025 | Not Ready for Inspection | ROY SPAULDING |
| Excavation/Setback/Form/Re-Bar | 2/21/2025 | Partial Approval | ROY SPAULDING |
| Pre-Inspection | 2/21/2025 | Not Ready for Inspection | ROY SPAULDING |
| Excavation/Setback/Form/Re-Bar | 3/20/2025 | Partial Approval | ROY SPAULDING |
| Piling/Pier/Caisson | 3/20/2025 | Partial Approval | ROY SPAULDING |
| Deputy Reinf. Concrete | 3/21/2025 | Conditional Approval | ROY SPAULDING |
| Excavation/Setback/Form/Re-Bar | 4/3/2025 | Partial Approval | ROY SPAULDING |
| Piling/Pier/Caisson | 4/11/2025 | Not Ready for Inspection | CRAIG VAUGHAN |
| Piling/Pier/Caisson | 4/16/2025 | Partial Approval | CRAIG VAUGHAN |
| Excavation/Setback/Form/Re-Bar | 5/7/2025 | Not Ready for Inspection | ROY SPAULDING |
| Footing/Foundation/Slab | 5/7/2025 | Not Ready for Inspection | ROY SPAULDING |
| Footing/Foundation/Slab | 5/21/2025 | Not Ready for Inspection | BRENDAN MORELLI |
| PLUMBING-Rough | 5/21/2025 | Partial Approval | BRENDAN MORELLI |
| Footing/Foundation/Slab | 5/27/2025 | Partial Approval | ROY SPAULDING |
| Excavation/Setback/Form/Re-Bar | 6/10/2025 | Partial Approval | BRENDAN MORELLI |
| Excavation/Setback/Form/Re-Bar | 6/26/2025 | Partial Approval | BRENDAN MORELLI |
| Excavation/Setback/Form/Re-Bar | 7/23/2025 | Partial Approval | ROY SPAULDING |
| Excavation/Setback/Form/Re-Bar | 8/27/2025 | Partial Approval | ROY SPAULDING |
| Excavation/Setback/Form/Re-Bar | 9/17/2025 | Not Ready for Inspection | ROY SPAULDING |
| Excavation/Setback/Form/Re-Bar | 9/18/2025 | Partial Approval | ROY SPAULDING |
| Footing/Foundation/Slab | 9/18/2025 | Partial Approval | ROY SPAULDING |
| Excavation/Setback/Form/Re-Bar | 10/3/2025 | Partial Approval | ROY SPAULDING |
| Excavation/Setback/Form/Re-Bar | 10/6/2025 | Partial Approval | ROY SPAULDING |
| Excavation/Setback/Form/Re-Bar | 10/8/2025 | Partial Approval | ROY SPAULDING |
| Deputy Steel/Welding | 10/24/2025 | Conditional Approval | ROY SPAULDING |
| Excavation/Setback/Form/Re-Bar | 10/29/2025 | Partial Approval | ROY SPAULDING |
| Excavation/Setback/Form/Re-Bar | 11/20/2025 | Conditional Approval | ROBERT PINA |
| Piling/Pier/Caisson | 11/20/2025 | Conditional Approval | ROBERT PINA |
| Excavation/Setback/Form/Re-Bar | 11/25/2025 | Partial Approval | ROY SPAULDING |
| Excavation/Setback/Form/Re-Bar | 12/19/2025 | Partial Approval | ROY SPAULDING |
| Footing/Foundation/Slab | 12/19/2025 | Partial Approval | ROY SPAULDING |
| Special/Order Compliance | 1/21/2026 | Corrections Issued | ROY SPAULDING |
| Underground Mechanical | 1/23/2026 | Not Ready for Inspection | ROBERT PINA |
| Floor/Roof Diaphrgm/Shear Wall | 1/28/2026 | Partial Approval | ROY SPAULDING |
| Wood Frame | 1/28/2026 | Partial Approval | ROY SPAULDING |
| Special/Order Compliance | 2/6/2026 | Corrections Issued | SCOTT FINNILA |
| Underground Mechanical | 2/26/2026 | Partial Approval | ROY SPAULDING |
| Floor/Roof Diaphrgm/Shear Wall | 3/17/2026 | Not Ready for Inspection | ROY SPAULDING |
| Floor/Roof Diaphrgm/Shear Wall | 3/19/2026 | Partial Approval | ROY SPAULDING |