2516-2516 1/2 E FAIRMOUNT ST 90033
Certificate Information: 2516-2516 1/2 E FAIRMOUNT ST 90033
- Application / Permit
- 22010-10000-04888
- Plan Check / Job No.
- B22LA19948
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- ePlan: (N) 3-STORY DUPLEX
- Permit Issued
- Issued on 4/19/2023
- Issuing Office
- Current Status
- CofO Issued on 2/7/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/6/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 10/20/2022 | DANIEL YIP |
| Corrections Issued | 10/24/2022 | DANIEL YIP |
| Quality Review Completed | 11/4/2022 | PRANITA SHAH |
| Plan Check Approved | 4/19/2023 | DANIEL YIP |
| Issued | 4/19/2023 | APPLICANT |
| CofO in Progress | 1/30/2024 | ALIZAH MAYAGOITIA |
| Permit Finaled | 2/7/2024 | DEROLD HAUFF |
| CofO Issued | 2/7/2024 | DEROLD HAUFF |
| Permit Finaled | 2/7/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 11/9/2022 | CELINA MORENO |
| Clean Up Green Up | Cleared | 11/15/2022 | SHASHA YU |
| Frnt yard landscape/Water mgmt | Cleared | 11/15/2022 | SHASHA YU |
| Sewer availability | Cleared | 11/17/2022 | CHRISTOPHER ROCHA |
| Eng Process Fee Ord 176,300 | Cleared | 11/22/2022 | CHRISTOPHER ROCHA |
| Hydrant and Access approval | Cleared | 11/23/2022 | LAVEON RIDER |
| Low Impact Development | Cleared | 2/14/2023 | ERNEST TSE |
| Roof/Waste drainage to street | Cleared | 2/16/2023 | CHRISTOPHER ROCHA |
| SB8 RUD | Cleared | 4/13/2023 | KENNETH LE |
| GPI Written Notices | Cleared | 4/19/2023 | DANIEL YIP |
| Grading Pre-Inspection | Cleared | 4/19/2023 | DANIEL YIP |
Contact Information
| Contractor | Lajoma Construction Inc; Lic. No.: 864461-B | , |
Inspector Information
| OSVALDO PARAMO, (213) 202-9854 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 5/25/2023 | Partial Approval | OSVALDO PARAMO |
| PLUMBING-Rough | 5/25/2023 | Partial Approval | OSVALDO PARAMO |
| Excavation/Setback/Form/Re-Bar | 6/6/2023 | Approved | OSVALDO PARAMO |
| Footing/Foundation/Slab | 6/6/2023 | Partial Approval | OSVALDO PARAMO |
| Floor/Roof Diaphrgm/Shear Wall | 7/5/2023 | Partial Approval | OSVALDO PARAMO |
| Floor/Roof Diaphrgm/Shear Wall | 7/11/2023 | Partial Approval | RUBEN SALAS |
| HVAC-Rough | 8/31/2023 | Approved | OSVALDO PARAMO |
| PLUMBING-Rough | 8/31/2023 | Approved | OSVALDO PARAMO |
| ELECTRICAL-Rough | 9/1/2023 | Approved | OSVALDO PARAMO |
| Floor/Roof Diaphrgm/Shear Wall | 9/1/2023 | Not Ready for Inspection | OSVALDO PARAMO |
| BUILDING-Rough-Frame | 9/5/2023 | Approved | OSVALDO PARAMO |
| Floor/Roof Diaphrgm/Shear Wall | 9/5/2023 | Approved | OSVALDO PARAMO |
| Green Building Rough | 9/5/2023 | Approved | OSVALDO PARAMO |
| Verify Sprinkler Sign Off | 9/5/2023 | Approved | OSVALDO PARAMO |
| Interior/Exterior Lathing | 9/13/2023 | Approved | OSVALDO PARAMO |
| Insulation | 9/14/2023 | Approved | JOSH MEISTER |
| Drywall Nailing | 9/29/2023 | Approved | JOSH MEISTER |
| Gas Test | 1/11/2024 | Approved | OSVALDO PARAMO |
| HVAC-Final | 1/11/2024 | Approved | OSVALDO PARAMO |
| PLUMBING-Final | 1/11/2024 | Approved | OSVALDO PARAMO |
| ELECTRICAL-Final | 1/18/2024 | Approved | OSVALDO PARAMO |
| Final | 1/18/2024 | Corrections Issued | OSVALDO PARAMO |
| Footing/Foundation/Slab | 1/18/2024 | Approved | OSVALDO PARAMO |
| Green Building Final | 1/18/2024 | Approved | OSVALDO PARAMO |
| SGSOV-Seismic Gas S/O Valve | 1/18/2024 | SGSOV Approved | OSVALDO PARAMO |
| Service/Power Release | 1/18/2024 | Approved | OSVALDO PARAMO |
| Smoke Detectors | 1/18/2024 | Approved | OSVALDO PARAMO |
| Verify Rec and Parks Fee Memo | 1/18/2024 | Approved | OSVALDO PARAMO |
| Service/Power Release | 1/22/2024 | Approved | OSVALDO PARAMO |
| Final | 1/29/2024 | OK to Issue CofO | ALIZAH MAYAGOITIA |