1600-1602 W 35TH ST 90018
Certificate Information: 1600-1602 W 35TH ST 90018
- Application / Permit
- 22010-10000-04875
- Plan Check / Job No.
- B22LA19846
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- NEW DUPLEX WITH ATTACHED 2 CAR GARAGE (3-STORY)
- Permit Issued
- Issued on 5/2/2023
- Issuing Office
- Current Status
- CofO Issued on 9/3/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/4/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 10/6/2022 | CARLOS MONTES |
| Corrections Issued | 10/9/2022 | CARLOS MONTES |
| Quality Review Completed | 10/11/2022 | GARO TELMI |
| Applicant returned to address corrections | 1/31/2023 | CARLOS MONTES |
| Plan Check Approved | 2/9/2023 | CARLOS MONTES |
| Issued | 5/2/2023 | APPLICANT |
| CofO in Progress | 8/23/2024 | ANTHONY EGSON |
| CofO Issued | 9/3/2024 | RUBEN SALAS |
| Permit Finaled | 9/3/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 10/23/2022 | JEANETTE VONG |
| Eng Process Fee Ord 176,300 | Cleared | 10/27/2022 | STEVE MELGAR |
| Hydrant and Access approval | Cleared | 11/21/2022 | LAVEON RIDER |
| Low Impact Development | Cleared | 11/30/2022 | ROGELIO CORTES |
| Roof/Waste drainage to street | Cleared | 12/2/2022 | AMAAN MALIK |
| Sewer availability | Cleared | 12/15/2022 | CHRISTOPHER ROCHA |
| SB8 RUD | Cleared | 1/5/2023 | JESSICA WANG |
Contact Information
| Architect | Wang,, Yang; Lic. No.: C35954 | 1935 GRAYDON AVENUE MONROVIA, CA 91016 |
| Contractor | Tre Development Llc; Lic. No.: 1075573-B | , |
| Engineer | Gao,, Jianfeng; Lic. No.: C88478 | 18825 ELMHURST ST ROWLAND HEIGHTS, CA 91748 |
| Engineer | Jones,, Ryan Keith; Lic. No.: GE2852 | 1253 W MASLINE ST COVINA, CA 91722 |
| Geologist | Kaligi,, Adam Azad; Lic. No.: GEO9287 | 19197 GOLDEN VALLEY RD #709 SANTA CLARITA, CA 91387 |
Inspector Information
| SABAS ALONSO, (213) 202-3468 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 9/14/2023 | Partial Approval | SABAS ALONSO |
| Sewer | 9/26/2023 | Approved | MICHAEL LEWIS |
| Underground Mechanical | 9/26/2023 | Approved | MICHAEL LEWIS |
| METHANE-Subgrade | 10/5/2023 | Approved | SABAS ALONSO |
| Deputy Reinf. Concrete | 10/19/2023 | Conditional Approval | BRENDAN MORELLI |
| Excavation/Setback/Form/Re-Bar | 10/20/2023 | Approved | ANTHONY EGSON |
| Footing/Foundation/Slab | 10/20/2023 | Approved | ANTHONY EGSON |
| METHANE-Barrier | 10/20/2023 | Approved | ANTHONY EGSON |
| Excavation/Setback/Form/Re-Bar | 10/23/2023 | Not Ready for Inspection | SABAS ALONSO |
| Deputy Reinf. Concrete | 10/24/2023 | Conditional Approval | SABAS ALONSO |
| Deputy Other (see comments) | 10/31/2023 | Conditional Approval | SABAS ALONSO |
| Deputy Wood Construction | 11/20/2023 | Conditional Approval | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 11/20/2023 | Partial Approval | MICHAEL LEWIS |
| Floor/Roof Diaphrgm/Shear Wall | 12/4/2023 | Partial Approval | SABAS ALONSO |
| Deputy Wood Construction | 12/5/2023 | Conditional Approval | SABAS ALONSO |
| Deputy Wood Construction | 12/22/2023 | Conditional Approval | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 12/22/2023 | Corrections Issued | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 12/27/2023 | Partial Approval | SABAS ALONSO |
| Deputy Wood Construction | 1/9/2024 | Conditional Approval | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 1/10/2024 | Approved | SABAS ALONSO |
| HVAC-Rough | 1/31/2024 | Approved | SABAS ALONSO |
| ELECTRICAL-Rough | 2/20/2024 | Corrections Issued | SABAS ALONSO |
| ELECTRICAL-Rough | 2/23/2024 | Corrections Issued | SABAS ALONSO |
| Interior/Exterior Lathing | 2/27/2024 | Partial Approval | SABAS ALONSO |
| BUILDING-Rough-Frame | 2/28/2024 | Approved | SABAS ALONSO |
| ELECTRICAL-Rough | 2/28/2024 | Approved | SABAS ALONSO |
| Green Building Rough | 2/28/2024 | Approved | SABAS ALONSO |
| METHANE-Rough | 2/28/2024 | Approved | SABAS ALONSO |
| PLUMBING-Rough | 2/28/2024 | Approved | SABAS ALONSO |
| Verify Sprinkler Sign Off | 2/28/2024 | Approved | SABAS ALONSO |
| Insulation | 3/22/2024 | Approved | SABAS ALONSO |
| Drywall Nailing | 4/12/2024 | Approved | SABAS ALONSO |
| Underground Mechanical | 5/20/2024 | Partial Approval | SABAS ALONSO |
| ELECTRICAL-Final | 7/11/2024 | Corrections Issued | SABAS ALONSO |
| HVAC-Final | 7/11/2024 | Corrections Issued | SABAS ALONSO |
| ELECTRICAL-Final | 8/1/2024 | Approved | SABAS ALONSO |
| Gas Test | 8/1/2024 | Approved | SABAS ALONSO |
| Green Building Final | 8/1/2024 | Not Ready for Inspection | SABAS ALONSO |
| HVAC-Final | 8/1/2024 | Approved | SABAS ALONSO |
| PLUMBING-Final | 8/1/2024 | Approved | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 8/1/2024 | SGSOV Approved | SABAS ALONSO |
| Service/Power Release | 8/1/2024 | Not Ready for Inspection | SABAS ALONSO |
| Smoke Detectors | 8/1/2024 | Approved | SABAS ALONSO |
| Final | 8/7/2024 | Corrections Issued | SABAS ALONSO |
| Final | 8/9/2024 | OK to Issue CofO | ANTHONY EGSON |
| Green Building Final | 8/9/2024 | Approved | ANTHONY EGSON |
| Service/Power Release | 8/9/2024 | Approved | ANTHONY EGSON |