3432 W 75TH ST 90043
Certificate Information: 3432 W 75TH ST 90043
- Application / Permit
- 22010-10000-04872
- Plan Check / Job No.
- B22LA19813
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePLAN. NEW 2 STORY DETACHED ACCESSORY DWELLING UNIT WITH AN ATTACHED STORAGE PER LAMC 12.22 A.33 (c)-(d)
- Permit Issued
- Issued on 5/25/2023
- Issuing Office
- Current Status
- CofO Issued on 12/14/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/6/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 10/13/2022 | KEVIN MORALES |
| Corrections Issued | 10/18/2022 | KEVIN MORALES |
| Quality Review Completed | 10/18/2022 | EUGENE BARBEAU |
| Applicant returned to address corrections | 11/15/2022 | KEVIN MORALES |
| Applicant returned to address corrections | 12/23/2022 | KEVIN MORALES |
| Applicant returned to address corrections | 2/7/2023 | KEVIN MORALES |
| Plan Check Approved | 5/5/2023 | KEVIN MORALES |
| Issued | 5/25/2023 | APPLICANT |
| CofO in Progress | 12/4/2024 | AMIR NAZARIAN |
| Permit Finaled | 12/14/2024 | DEROLD HAUFF |
| Permit Finaled | 12/14/2024 | DEROLD HAUFF |
| CofO Issued | 12/14/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 10/21/2022 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 11/17/2022 | CELINA MORENO |
| Sewer availability | Cleared | 11/17/2022 | CELINA MORENO |
| Construction near power lines | Cleared | 12/30/2022 | RIDWAN HARDY |
| Low Impact Development | Cleared | 3/28/2023 | TOMMY YIN |
| Roof/Waste drainage to street | Cleared | 3/29/2023 | JEANIE LAM |
Contact Information
| Contractor | Adu Concepts; Lic. No.: 1018294-B | , |
| Contractor | Green Source Energy Inc; Lic. No.: 1018294-B | , |
| Engineer | Hernandez, Sotomayor, Daniel; Lic. No.: C93095 | 15755 SATICOY ST APT#306 VAN NUYS, CA 91406 |
Inspector Information
| SALVADOR MARTINEZ, (213) 202-3479 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 8/8/2023 | Approved | ENRIQUE MIRELES |
| Footing/Foundation/Slab | 8/10/2023 | Approved | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 9/12/2023 | Corrections Issued | MICHAEL LEWIS |
| Deputy Wood Construction | 9/15/2023 | Conditional Approval | DAVID FEILER |
| ELECTRICAL-Rough | 10/11/2023 | Approved | ENRIQUE MIRELES |
| PLUMBING-Rough | 10/17/2023 | Approved | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 11/8/2023 | Approved | ENRIQUE MIRELES |
| HVAC-Rough | 11/13/2023 | No Access for Inspection | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 11/15/2023 | Approved | ENRIQUE MIRELES |
| Insulation | 11/15/2023 | Approved | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 11/15/2023 | Approved | ENRIQUE MIRELES |
| Verify Sprinkler Sign Off | 11/15/2023 | Approved | ENRIQUE MIRELES |
| Drywall Nailing | 11/21/2023 | Approved | ENRIQUE MIRELES |
| Sewer | 1/23/2024 | Corrections Issued | ALIZAH MAYAGOITIA |
| Sewer | 3/1/2024 | Approved | JOSE MACIAS |
| Underground Mechanical | 3/1/2024 | Approved | JOSE MACIAS |
| ELECTRICAL-Final | 6/12/2024 | Corrections Issued | JOSE MACIAS |
| Final | 6/12/2024 | Corrections Issued | JOSE MACIAS |
| HVAC-Final | 6/12/2024 | Not Ready for Inspection | JOSE MACIAS |
| PLUMBING-Final | 6/12/2024 | Not Ready for Inspection | JOSE MACIAS |
| SGSOV-Seismic Gas S/O Valve | 6/12/2024 | SGSOV Not Ready | JOSE MACIAS |
| Service/Power Release | 6/12/2024 | Not Ready for Inspection | JOSE MACIAS |
| Smoke Detectors | 6/12/2024 | Approved | JOSE MACIAS |
| ELECTRICAL-Final | 6/27/2024 | Approved | JOSE MACIAS |
| Final | 6/27/2024 | Not Ready for Inspection | JOSE MACIAS |
| Gas Test | 6/27/2024 | Approved | JOSE MACIAS |
| SGSOV-Seismic Gas S/O Valve | 6/27/2024 | SGSOV Approved | JOSE MACIAS |
| Service/Power Release | 6/27/2024 | Not Ready for Inspection | JOSE MACIAS |
| Final | 7/19/2024 | Corrections Issued | JOSE MACIAS |
| HVAC-Final | 7/19/2024 | Corrections Issued | JOSE MACIAS |
| PLUMBING-Final | 7/19/2024 | Approved | JOSE MACIAS |
| Service/Power Release | 7/19/2024 | Corrections Issued | JOSE MACIAS |
| Final | 7/25/2024 | Corrections Issued | JOSE MACIAS |
| HVAC-Final | 7/25/2024 | Approved | JOSE MACIAS |
| Service/Power Release | 7/25/2024 | Not Ready for Inspection | JOSE MACIAS |
| Final | 10/15/2024 | Corrections Issued | AMIR NAZARIAN |
| Service/Power Release | 10/15/2024 | Not Ready for Inspection | AMIR NAZARIAN |
| Final | 11/6/2024 | Corrections Issued | AMIR NAZARIAN |
| Service/Power Release | 11/6/2024 | Approved | AMIR NAZARIAN |
| Final | 12/3/2024 | OK to Issue CofO | AMIR NAZARIAN |