8700-8702 S ORCHARD AVE 90044

Certificate Information: 8700-8702 S ORCHARD AVE 90044

Application / Permit
22010-10000-04834
Plan Check / Job No.
B22LA19625
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
NEW TWO STORY DUPLEX W/ OPEN PARKING
Permit Issued
Issued on 7/12/2024
Issuing Office
Current Status
CofO Issued on 11/6/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/4/2022 APPLICANT
Assigned to Plan Check Engineer 10/20/2022 JOE VO
Corrections Issued 10/22/2022 JOE VO
Quality Review Completed 10/24/2022 GARO TELMI
Applicant returned to address corrections 2/14/2024 JOE VO
Plan Check Approved 7/10/2024 JOE VO
Issued 7/12/2024 APPLICANT
CofO in Progress 11/6/2025 RAUL BARAJAS
Permit Finaled 11/6/2025 DANIEL ORRANTE
CofO Issued 11/6/2025 DANIEL ORRANTE
Permit Finaled 11/6/2025 DANIEL ORRANTE

Permit Application Clearance Information

Highway dedication Cleared 1/25/2024 DAVID VO
Public Works-Highway Ded. Cleared 1/25/2024 DAVID VO
DAS Clearance Cleared 2/13/2024 Luke Gonzales
Green Code Cleared 2/13/2024 Luke Gonzales
Hydrant and Access approval Cleared 3/29/2024 KURT CORRAL
Eng Process Fee Ord 176,300 Cleared 4/19/2024 WALLIE JONG
Sewer availability Cleared 4/19/2024 WALLIE JONG
Low Impact Development Cleared 6/24/2024 LUIS LUVANO
Address approval Cleared 6/25/2024 TREVOR QUAN
Roof/Waste drainage to street Cleared 6/25/2024 TREVOR QUAN

Contact Information

Contractor Nwabuzor Construction; Lic. No.: 1073216-B       ,
Contractor R N Investments And Community Services Inc; Lic. No.: 1073216-B       ,
Engineer Adefeso,, Wole; Lic. No.: C63361 1620 CENTINELA AVE 304B      INGLEWOOD, CA 90302

Inspector Information

JOHN QUINTANILLA, (213) 792-6055 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 8/26/2024 Approved MICHAEL LEWIS
Footing/Foundation/Slab 8/26/2024 Approved MICHAEL LEWIS
Floor/Roof Diaphrgm/Shear Wall 9/9/2024 Partial Approval MICHAEL LEWIS
PLUMBING-Rough 9/9/2024 Partial Approval MICHAEL LEWIS
Floor/Roof Diaphrgm/Shear Wall 9/10/2024 Partial Approval MICHAEL LEWIS
Insulation 9/10/2024 Partial Approval MICHAEL LEWIS
Floor/Roof Diaphrgm/Shear Wall 9/11/2024 Partial Inspection MICHAEL LEWIS
Drywall Nailing 9/24/2024 Not Ready for Inspection MICHAEL LEWIS
Floor/Roof Diaphrgm/Shear Wall 9/24/2024 Partial Approval MICHAEL LEWIS
Floor/Roof Diaphrgm/Shear Wall 11/27/2024 Partial Approval CRAIG DAVIS
BUILDING-Rough-Frame 12/30/2024 Not Ready for Inspection JOHN QUINTANILLA
ELECTRICAL-Rough 12/30/2024 Corrections Issued JOHN QUINTANILLA
Green Building Rough 12/30/2024 Not Ready for Inspection JOHN QUINTANILLA
HVAC-Rough 12/30/2024 Corrections Issued JOHN QUINTANILLA
PLUMBING-Rough 12/30/2024 Corrections Issued JOHN QUINTANILLA
Verify Sprinkler Sign Off 12/30/2024 Not Ready for Inspection JOHN QUINTANILLA
Deputy Wood Construction 1/2/2025 Conditional Approval NICHOLAS LOPEZ
BUILDING-Rough-Frame 2/7/2025 Approved JOHN QUINTANILLA
ELECTRICAL-Rough 2/7/2025 Approved JOHN QUINTANILLA
Green Building Rough 2/7/2025 Approved JOHN QUINTANILLA
HVAC-Rough 2/7/2025 Approved JOHN QUINTANILLA
PLUMBING-Rough 2/7/2025 Approved JOHN QUINTANILLA
Verify Sprinkler Sign Off 2/7/2025 Approved JOHN QUINTANILLA
Interior/Exterior Lathing 2/28/2025 Partial Approval ANTHONY RAMOS
Insulation 3/4/2025 Conditional Approval JOHN QUINTANILLA
Service/Power Release 3/4/2025 Not Ready for Inspection JOHN QUINTANILLA
Drywall Nailing 3/13/2025 Approved ANTHONY RAMOS
Insulation 3/13/2025 Approved ANTHONY RAMOS
Interior/Exterior Lathing 3/21/2025 Approved JOHN QUINTANILLA
Sewer 5/5/2025 Partial Approval JOHN QUINTANILLA
Final 6/27/2025 Not Ready for Inspection JOHN QUINTANILLA
Green Building Final 6/27/2025 Not Ready for Inspection JOHN QUINTANILLA
SGSOV-Seismic Gas S/O Valve 6/27/2025 SGSOV Not Required JOHN QUINTANILLA
Service/Power Release 6/27/2025 Not Ready for Inspection JOHN QUINTANILLA
Smoke Detectors 6/27/2025 Approved JOHN QUINTANILLA
ELECTRICAL-Final 7/3/2025 Approved JOHN QUINTANILLA
HVAC-Final 7/3/2025 Not Ready for Inspection JOHN QUINTANILLA
PLUMBING-Final 7/3/2025 Approved JOHN QUINTANILLA
HVAC-Final 7/31/2025 Not Ready for Inspection LUIS CASTRO
Service/Power Release 7/31/2025 Approved LUIS CASTRO
HVAC-Final 9/9/2025 Approved JOHN QUINTANILLA
Final 10/10/2025 Not Ready for Inspection JOHN QUINTANILLA
Green Building Final 10/10/2025 Approved JOHN QUINTANILLA
Final 11/3/2025 Corrections Issued BARRY HACHE
Final 11/6/2025 OK to Issue CofO RAUL BARAJAS