3728 N LOMITAS DR 90032

Certificate Information: 3728 N LOMITAS DR 90032

Application / Permit
22010-10000-04831
Plan Check / Job No.
B22LA19610
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW (28' X 31.5)' IRREGULAR SHAPED) ACCESSORY DWELLING UNIT PER CA GOVT CODE 65852.2(E)(1)(B) AND APPLICABLE PART OF LAMC 12.22 A.33 (c)-(d), (g). NFPA 13D FIRE SPRINKLER SYSTEM IS REQUIRED.
Permit Issued
Issued on 3/21/2024
Issuing Office
Metro
Current Status
CofO Issued on 7/14/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/29/2022 APPLICANT
Assigned to Plan Check Engineer 10/13/2022 NGHI SU
Corrections Issued 10/18/2022 NGHI SU
Quality Review Completed 10/20/2022 FARUK SEZER
Building Plans Picked Up 10/21/2022 APPLICANT
Applicant returned to address corrections 11/16/2023 NGHI SU
Plan Check Approved 3/11/2024 NGHI SU
Issued 3/21/2024 APPLICANT
CofO in Progress 7/9/2025 LILIANA PORTILLO
CofO Issued 7/14/2025 DEROLD HAUFF
Permit Finaled 7/14/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 11/3/2022 AMAAN MALIK
BHO/Hillside ordinance Cleared 11/3/2022 AMAAN MALIK
BHO/Hillside ordinance Cleared 11/3/2022 AMAAN MALIK
BHO/Hillside ordinance Cleared 11/3/2022 AMAAN MALIK
BHO/Hillside ordinance Cleared 11/3/2022 AMAAN MALIK
BHO/Hillside ordinance Cleared 11/3/2022 AMAAN MALIK
Eng Process Fee Ord 176,300 Cleared 11/8/2022 AMAAN MALIK
Sewer availability Cleared 11/8/2022 AMAAN MALIK
Hydrant and Access approval Cleared 11/19/2022 GILBERT URREA
Low Impact Development Cleared 4/20/2023 LUIS LUVANO
Roof/Waste drainage to street Cleared 5/13/2023 STEVE MELGAR
"D" conditions Cleared 9/13/2023 JAZMIN ROQUE
"Q" conditions Cleared 9/13/2023 JAZMIN ROQUE
ZI Cleared 9/13/2023 JAZMIN ROQUE
GPI Written Notices Cleared 11/16/2023 NGHI SU
Grading Pre-Inspection Cleared 11/16/2023 NGHI SU
Excavation more than 5-ft deep Cleared 3/11/2024 CALOSHA APPROVED

Contact Information

Contractor Owner-Builder       ,
Engineer Alson,, Ken; Lic. No.: C41697 9744 MAPLE ST 201      BELLFLOWER, CA 90706
Engineer Hamilton,, John O; Lic. No.: C53284 P O BOX 866      HAWTHORNE, CA 90251
Engineer Khatibloo,, Babak; Lic. No.: M27855 98 HAVENWOOD      IRVINE, CA 92614
Engineer Koh,, Timothy; Lic. No.: L8669 9853 MAPLE STREET      BELLFLOWER, CA 90706
Engineer Lee,, Allen C; Lic. No.: GE2781 11823 SLAUSON AVE STE 46      SANTA FE SPRINGS, CA 90670
Geologist Eastman,, Ray Alan; Lic. No.: EG423 1850 FAIRWAY DRIVE SP 49      CHINO HILLS, CA 91709

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 6/3/2024 Partial Approval LILIANA PORTILLO
Masonry Wall/Backfill 6/12/2024 Partial Approval LILIANA PORTILLO
Masonry Wall/Backfill 6/27/2024 Partial Approval LILIANA PORTILLO
Footing/Foundation/Slab 7/16/2024 Partial Approval LILIANA PORTILLO
Underground Mechanical 7/25/2024 Partial Approval OSVALDO PARAMO
Excavation/Setback/Form/Re-Bar 7/29/2024 Approved BRENDAN MORELLI
Footing/Foundation/Slab 7/29/2024 Approved BRENDAN MORELLI
Sewer 12/5/2024 Approved BRENDAN MORELLI
BUILDING-Rough-Frame 12/12/2024 Corrections Issued LILIANA PORTILLO
ELECTRICAL-Rough 12/12/2024 Approved LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 12/12/2024 Corrections Issued LILIANA PORTILLO
HVAC-Rough 12/12/2024 Approved LILIANA PORTILLO
PLUMBING-Rough 12/12/2024 Approved LILIANA PORTILLO
Verify Sprinkler Sign Off 12/12/2024 Approved LILIANA PORTILLO
Insulation 12/17/2024 Corrections Issued LILIANA PORTILLO
Interior/Exterior Lathing 12/17/2024 Partial Approval LILIANA PORTILLO
Drywall Nailing 12/20/2024 Not Ready for Inspection LILIANA PORTILLO
Green Building Rough 12/20/2024 Approved LILIANA PORTILLO
BUILDING-Rough-Frame 12/24/2024 Approved LILIANA PORTILLO
Drywall Nailing 12/24/2024 Approved LILIANA PORTILLO
Insulation 12/24/2024 Approved LILIANA PORTILLO
Shower Pan 12/24/2024 Approved LILIANA PORTILLO
Interior/Exterior Lathing 1/13/2025 Approved LILIANA PORTILLO
Final 6/24/2025 Corrections Issued LILIANA PORTILLO
Green Building Final 6/24/2025 Not Ready for Inspection LILIANA PORTILLO
SGSOV-Seismic Gas S/O Valve 6/24/2025 SGSOV Not Required LILIANA PORTILLO
Service/Power Release 6/24/2025 Not Ready for Inspection LILIANA PORTILLO
Smoke Detectors 6/24/2025 Approved LILIANA PORTILLO
ELECTRICAL-Final 7/7/2025 Approved LILIANA PORTILLO
Final 7/7/2025 OK to Issue CofO LILIANA PORTILLO
Green Building Final 7/7/2025 Approved LILIANA PORTILLO
HVAC-Final 7/7/2025 Approved LILIANA PORTILLO
PLUMBING-Final 7/7/2025 Approved LILIANA PORTILLO
Service/Power Release 7/7/2025 Approved LILIANA PORTILLO