5257 N COLLEGE VIEW AVE 90041
Certificate Information: 5257 N COLLEGE VIEW AVE 90041
- Application / Permit
- 22010-10000-04801
- Plan Check / Job No.
- B22LA19407
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan - (n) 1-story detached ADU per GCS 65852.2(e)(1)(B) and LAMC 12.22 A.33(c)(d)(g) R3 occupancy
- Permit Issued
- Issued on 12/5/2023
- Issuing Office
- Current Status
- CofO Issued on 8/5/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/28/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 11/3/2022 | KELVIN CHUONG |
| Corrections Issued | 11/8/2022 | KELVIN CHUONG |
| Quality Review Completed | 11/9/2022 | RODOLFO ARIAS |
| Applicant returned to address corrections | 8/8/2023 | KELVIN CHUONG |
| Applicant returned to address corrections | 9/22/2023 | KELVIN CHUONG |
| Applicant returned to address corrections | 11/29/2023 | KELVIN CHUONG |
| Plan Check Approved | 12/1/2023 | KELVIN CHUONG |
| Issued | 12/5/2023 | APPLICANT |
| CofO in Progress | 7/22/2024 | CRAIG VAUGHAN |
| CofO Issued | 8/5/2024 | DEROLD HAUFF |
| Permit Finaled | 8/5/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 5/4/2023 | JEANIE LAM |
| Roof/Waste drainage to street | Cleared | 5/4/2023 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 5/5/2023 | JEANIE LAM |
| Sewer availability | Cleared | 5/5/2023 | JEANIE LAM |
| Grading Pre-Inspection | Cleared | 7/26/2023 | ROBERT HUGHES |
| GPI Written Notices | Cleared | 9/12/2023 | KELVIN CHUONG |
| Low Impact Development (LID) | Cleared | 9/13/2023 | ROGELIO CORTES |
| Construction near power lines | Cleared | 11/29/2023 | RIDWAN HARDY |
Contact Information
| Contractor | H T A Construction & Development; Lic. No.: 1044038-B | , |
| Contractor | Hta Construction & Development; Lic. No.: 1044038-B | , |
| Engineer | Crosby,, Paul; Lic. No.: NA5635 | , |
Inspector Information
| RONNIE MEDINA, (213) 469-5852 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 12/20/2023 | Not Ready for Inspection | ROY SPAULDING |
| Pre-Inspection | 12/22/2023 | Partial Approval | ROY SPAULDING |
| Excavation/Setback/Form/Re-Bar | 1/11/2024 | Not Ready for Inspection | CRAIG VAUGHAN |
| PLUMBING-Rough | 1/11/2024 | Partial Approval | CRAIG VAUGHAN |
| Excavation/Setback/Form/Re-Bar | 1/18/2024 | Corrections Issued | CRAIG VAUGHAN |
| Footing/Foundation/Slab | 1/18/2024 | Not Ready for Inspection | CRAIG VAUGHAN |
| Excavation/Setback/Form/Re-Bar | 1/23/2024 | Approved | CRAIG VAUGHAN |
| Excavation/Setback/Form/Re-Bar | 1/24/2024 | Approved | CRAIG VAUGHAN |
| Footing/Foundation/Slab | 1/24/2024 | Approved | CRAIG VAUGHAN |
| Pre-Inspection | 1/24/2024 | Partial Approval | CRAIG VAUGHAN |
| Floor/Roof Diaphrgm/Shear Wall | 2/7/2024 | Approved | ROY SPAULDING |
| ELECTRICAL-Rough | 2/22/2024 | Corrections Issued | CRAIG VAUGHAN |
| HVAC-Rough | 2/22/2024 | Approved | CRAIG VAUGHAN |
| PLUMBING-Rough | 2/22/2024 | Corrections Issued | CRAIG VAUGHAN |
| Special/Order Compliance | 2/22/2024 | Approved | CHARLES BOGHOSKHAN |
| ELECTRICAL-Rough | 2/29/2024 | Approved | CRAIG VAUGHAN |
| HVAC-Rough | 2/29/2024 | Approved | CRAIG VAUGHAN |
| PLUMBING-Rough | 2/29/2024 | Not Ready for Inspection | CRAIG VAUGHAN |
| Wood Frame | 2/29/2024 | Partial Approval | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 3/6/2024 | Partial Approval | CRAIG VAUGHAN |
| Interior/Exterior Lathing | 3/6/2024 | Partial Approval | CRAIG VAUGHAN |
| Wood Frame | 3/6/2024 | Approved | CRAIG VAUGHAN |
| Insulation | 3/12/2024 | Approved | BRIAN SULLIVAN |
| Drywall Nailing | 3/19/2024 | Approved | CRAIG VAUGHAN |
| Interior/Exterior Lathing | 3/19/2024 | Approved | CRAIG VAUGHAN |
| Sewer | 4/23/2024 | Not Ready for Inspection | CRAIG VAUGHAN |
| Sewer | 4/29/2024 | Not Ready for Inspection | CRAIG VAUGHAN |
| Sewer | 5/7/2024 | Partial Approval | CRAIG VAUGHAN |
| Sewer | 5/9/2024 | Approved | CHARLES BOGHOSKHAN |
| Underground Mechanical | 5/21/2024 | Approved | CRAIG VAUGHAN |
| ELECTRICAL-Final | 5/29/2024 | Corrections Issued | CRAIG VAUGHAN |
| HVAC-Final | 5/29/2024 | Approved | CRAIG VAUGHAN |
| PLUMBING-Final | 5/29/2024 | Corrections Issued | CRAIG VAUGHAN |
| Service/Power Release | 5/29/2024 | Not Ready for Inspection | CRAIG VAUGHAN |
| ELECTRICAL-Final | 7/8/2024 | Not Ready for Inspection | CRAIG VAUGHAN |
| Service/Power Release | 7/8/2024 | Corrections Issued | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 7/16/2024 | Partial Approval | SCOTT FINNILA |
| ELECTRICAL-Final | 7/16/2024 | Not Ready for Inspection | SCOTT FINNILA |
| Final | 7/16/2024 | Not Ready for Inspection | SCOTT FINNILA |
| SGSOV-Seismic Gas S/O Valve | 7/16/2024 | SGSOV Not Required | SCOTT FINNILA |
| Service/Power Release | 7/16/2024 | Not Ready for Inspection | SCOTT FINNILA |
| Smoke Detectors | 7/16/2024 | Approved | SCOTT FINNILA |
| Verify Sprinkler Sign Off | 7/16/2024 | Partial Inspection | SCOTT FINNILA |
| BUILDING-Rough-Frame | 7/19/2024 | Approved | CRAIG VAUGHAN |
| ELECTRICAL-Final | 7/19/2024 | Approved | CRAIG VAUGHAN |
| Final | 7/19/2024 | OK to Issue CofO | CRAIG VAUGHAN |
| Service/Power Release | 7/19/2024 | Approved | CRAIG VAUGHAN |
| Verify Sprinkler Sign Off | 7/19/2024 | Approved | CRAIG VAUGHAN |
| Pre-Inspection | 7/22/2024 | Corrections Issued | CRAIG VAUGHAN |