5257 N COLLEGE VIEW AVE 90041

Certificate Information: 5257 N COLLEGE VIEW AVE 90041

Application / Permit
22010-10000-04801
Plan Check / Job No.
B22LA19407
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan - (n) 1-story detached ADU per GCS 65852.2(e)(1)(B) and LAMC 12.22 A.33(c)(d)(g) R3 occupancy
Permit Issued
Issued on 12/5/2023
Issuing Office
Current Status
CofO Issued on 8/5/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/28/2022 APPLICANT
Assigned to Plan Check Engineer 11/3/2022 KELVIN CHUONG
Corrections Issued 11/8/2022 KELVIN CHUONG
Quality Review Completed 11/9/2022 RODOLFO ARIAS
Applicant returned to address corrections 8/8/2023 KELVIN CHUONG
Applicant returned to address corrections 9/22/2023 KELVIN CHUONG
Applicant returned to address corrections 11/29/2023 KELVIN CHUONG
Plan Check Approved 12/1/2023 KELVIN CHUONG
Issued 12/5/2023 APPLICANT
CofO in Progress 7/22/2024 CRAIG VAUGHAN
CofO Issued 8/5/2024 DEROLD HAUFF
Permit Finaled 8/5/2024 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 5/4/2023 JEANIE LAM
Roof/Waste drainage to street Cleared 5/4/2023 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 5/5/2023 JEANIE LAM
Sewer availability Cleared 5/5/2023 JEANIE LAM
Grading Pre-Inspection Cleared 7/26/2023 ROBERT HUGHES
GPI Written Notices Cleared 9/12/2023 KELVIN CHUONG
Low Impact Development (LID) Cleared 9/13/2023 ROGELIO CORTES
Construction near power lines Cleared 11/29/2023 RIDWAN HARDY

Contact Information

Contractor H T A Construction & Development; Lic. No.: 1044038-B       ,
Contractor Hta Construction & Development; Lic. No.: 1044038-B       ,
Engineer Crosby,, Paul; Lic. No.: NA5635       ,

Inspector Information

RONNIE MEDINA, (213) 469-5852 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 12/20/2023 Not Ready for Inspection ROY SPAULDING
Pre-Inspection 12/22/2023 Partial Approval ROY SPAULDING
Excavation/Setback/Form/Re-Bar 1/11/2024 Not Ready for Inspection CRAIG VAUGHAN
PLUMBING-Rough 1/11/2024 Partial Approval CRAIG VAUGHAN
Excavation/Setback/Form/Re-Bar 1/18/2024 Corrections Issued CRAIG VAUGHAN
Footing/Foundation/Slab 1/18/2024 Not Ready for Inspection CRAIG VAUGHAN
Excavation/Setback/Form/Re-Bar 1/23/2024 Approved CRAIG VAUGHAN
Excavation/Setback/Form/Re-Bar 1/24/2024 Approved CRAIG VAUGHAN
Footing/Foundation/Slab 1/24/2024 Approved CRAIG VAUGHAN
Pre-Inspection 1/24/2024 Partial Approval CRAIG VAUGHAN
Floor/Roof Diaphrgm/Shear Wall 2/7/2024 Approved ROY SPAULDING
ELECTRICAL-Rough 2/22/2024 Corrections Issued CRAIG VAUGHAN
HVAC-Rough 2/22/2024 Approved CRAIG VAUGHAN
PLUMBING-Rough 2/22/2024 Corrections Issued CRAIG VAUGHAN
Special/Order Compliance 2/22/2024 Approved CHARLES BOGHOSKHAN
ELECTRICAL-Rough 2/29/2024 Approved CRAIG VAUGHAN
HVAC-Rough 2/29/2024 Approved CRAIG VAUGHAN
PLUMBING-Rough 2/29/2024 Not Ready for Inspection CRAIG VAUGHAN
Wood Frame 2/29/2024 Partial Approval CRAIG VAUGHAN
BUILDING-Rough-Frame 3/6/2024 Partial Approval CRAIG VAUGHAN
Interior/Exterior Lathing 3/6/2024 Partial Approval CRAIG VAUGHAN
Wood Frame 3/6/2024 Approved CRAIG VAUGHAN
Insulation 3/12/2024 Approved BRIAN SULLIVAN
Drywall Nailing 3/19/2024 Approved CRAIG VAUGHAN
Interior/Exterior Lathing 3/19/2024 Approved CRAIG VAUGHAN
Sewer 4/23/2024 Not Ready for Inspection CRAIG VAUGHAN
Sewer 4/29/2024 Not Ready for Inspection CRAIG VAUGHAN
Sewer 5/7/2024 Partial Approval CRAIG VAUGHAN
Sewer 5/9/2024 Approved CHARLES BOGHOSKHAN
Underground Mechanical 5/21/2024 Approved CRAIG VAUGHAN
ELECTRICAL-Final 5/29/2024 Corrections Issued CRAIG VAUGHAN
HVAC-Final 5/29/2024 Approved CRAIG VAUGHAN
PLUMBING-Final 5/29/2024 Corrections Issued CRAIG VAUGHAN
Service/Power Release 5/29/2024 Not Ready for Inspection CRAIG VAUGHAN
ELECTRICAL-Final 7/8/2024 Not Ready for Inspection CRAIG VAUGHAN
Service/Power Release 7/8/2024 Corrections Issued CRAIG VAUGHAN
BUILDING-Rough-Frame 7/16/2024 Partial Approval SCOTT FINNILA
ELECTRICAL-Final 7/16/2024 Not Ready for Inspection SCOTT FINNILA
Final 7/16/2024 Not Ready for Inspection SCOTT FINNILA
SGSOV-Seismic Gas S/O Valve 7/16/2024 SGSOV Not Required SCOTT FINNILA
Service/Power Release 7/16/2024 Not Ready for Inspection SCOTT FINNILA
Smoke Detectors 7/16/2024 Approved SCOTT FINNILA
Verify Sprinkler Sign Off 7/16/2024 Partial Inspection SCOTT FINNILA
BUILDING-Rough-Frame 7/19/2024 Approved CRAIG VAUGHAN
ELECTRICAL-Final 7/19/2024 Approved CRAIG VAUGHAN
Final 7/19/2024 OK to Issue CofO CRAIG VAUGHAN
Service/Power Release 7/19/2024 Approved CRAIG VAUGHAN
Verify Sprinkler Sign Off 7/19/2024 Approved CRAIG VAUGHAN
Pre-Inspection 7/22/2024 Corrections Issued CRAIG VAUGHAN