5231 1/2 N LOLETA AVE 90041

Certificate Information: 5231 1/2 N LOLETA AVE 90041

Application / Permit
22010-10000-04784
Plan Check / Job No.
B22LA19320
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
eplan NEW ADU per ordinance
Permit Issued
Issued on 12/23/2022
Issuing Office
Current Status
CofO Issued on 5/15/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/26/2022 APPLICANT
Assigned to Plan Check Engineer 9/29/2022 JAD BASMA
Corrections Issued 10/2/2022 JAD BASMA
Quality Review Completed 10/19/2022 TEODORO DIAZ RODRIGUEZ
Applicant returned to address corrections 11/9/2022 JAD BASMA
Plan Check Approved 12/23/2022 JAD BASMA
Issued 12/23/2022 APPLICANT
CofO in Progress 5/8/2024 CRAIG VAUGHAN
Permit Finaled 5/15/2024 DEROLD HAUFF
CofO Issued 5/15/2024 DEROLD HAUFF
Permit Finaled 5/15/2024 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 10/6/2022 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 10/6/2022 JEANIE LAM
Sewer availability Cleared 10/6/2022 JEANIE LAM
Street Frontage Cleared 10/6/2022 JEANIE LAM
Grading Pre-Inspection Cleared 10/25/2022 ROBERT HUGHES
Low Impact Development Cleared 11/8/2022 ROGELIO CORTES
Roof/Waste drainage to street Cleared 11/12/2022 AMAAN MALIK
GPI Written Notices Cleared 12/15/2022 JAD BASMA

Contact Information

Contractor Opus Builders Inc; Lic. No.: 1059646-B 5244 VINELAND AVENUE      NORTH HOLLYWOOD, CA 91601

Inspector Information

RONNIE MEDINA, (213) 469-5852 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 6/7/2023 Not Ready for Inspection CRAIG VAUGHAN
Excavation/Setback/Form/Re-Bar 8/10/2023 Not Ready for Inspection CRAIG VAUGHAN
Underground Mechanical 8/10/2023 Partial Approval CRAIG VAUGHAN
Footing/Foundation/Slab 8/11/2023 No Access for Inspection CRAIG VAUGHAN
Excavation/Setback/Form/Re-Bar 8/14/2023 Approved CRAIG VAUGHAN
Sewer 11/6/2023 Approved CRAIG VAUGHAN
Underground Mechanical 11/6/2023 Partial Approval CRAIG VAUGHAN
ELECTRICAL-Rough 11/21/2023 Approved CRAIG VAUGHAN
HVAC-Rough 11/21/2023 Corrections Issued CRAIG VAUGHAN
PLUMBING-Rough 11/21/2023 Approved CRAIG VAUGHAN
Wood Frame 11/21/2023 Approved CRAIG VAUGHAN
Insulation 11/27/2023 Approved ROY SPAULDING
Interior/Exterior Lathing 11/27/2023 Approved ROY SPAULDING
Pre-Inspection 11/27/2023 Approved ROY SPAULDING
Drywall Nailing 12/5/2023 Approved CRAIG VAUGHAN
Interior/Exterior Lathing 12/5/2023 Partial Approval CRAIG VAUGHAN
Sewer 12/6/2023 Approved CRAIG VAUGHAN
Interior/Exterior Lathing 12/20/2023 Approved BRENDAN MORELLI
Shower Pan 12/20/2023 Approved BRENDAN MORELLI
Service/Power Release 3/18/2024 Not Ready for Inspection CRAIG VAUGHAN
BUILDING-Rough-Frame 4/24/2024 Approved CRAIG VAUGHAN
ELECTRICAL-Final 4/24/2024 Corrections Issued CRAIG VAUGHAN
Final 4/24/2024 Corrections Issued CRAIG VAUGHAN
Footing/Foundation/Slab 4/24/2024 Approved CRAIG VAUGHAN
SGSOV-Seismic Gas S/O Valve 4/24/2024 SGSOV Not Required CRAIG VAUGHAN
Service/Power Release 4/24/2024 Approved CRAIG VAUGHAN
Smoke Detectors 4/24/2024 Approved CRAIG VAUGHAN
Verify Sprinkler Sign Off 4/24/2024 Approved CRAIG VAUGHAN
Final 5/7/2024 OK to Issue CofO CRAIG VAUGHAN