2517 W 36TH ST 90018
Certificate Information: 2517 W 36TH ST 90018
- Application / Permit
- 22010-10000-04779
- Plan Check / Job No.
- B22LA19316
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW DETACHED ADU PER ORDINANCE (1-STORY)
- Permit Issued
- Issued on 12/15/2022
- Issuing Office
- Current Status
- CofO Issued on 9/21/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/27/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 9/29/2022 | CARLOS MONTES |
| Corrections Issued | 10/1/2022 | CARLOS MONTES |
| Quality Review Completed | 10/5/2022 | GARO TELMI |
| Plan Check Approved | 12/13/2022 | CARLOS MONTES |
| Issued | 12/15/2022 | APPLICANT |
| CofO in Progress | 9/19/2023 | CALEB MEISTER |
| Permit Finaled | 9/21/2023 | DEROLD HAUFF |
| CofO Issued | 9/21/2023 | DEROLD HAUFF |
| Permit Finaled | 9/21/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 10/28/2022 | CINDY QI |
| HPOZ | Cleared | 12/1/2022 | DANIEL MATA |
| Historic monument | Cleared | 12/1/2022 | DANIEL MATA |
| Miscellaneous | Cleared | 12/1/2022 | DANIEL MATA |
| Miscellaneous | Cleared | 12/1/2022 | DANIEL MATA |
| Eng Process Fee Ord 176,300 | Cleared | 12/6/2022 | AMAAN MALIK |
| Sewer availability | Cleared | 12/6/2022 | AMAAN MALIK |
| Low Impact Development | Cleared | 12/12/2022 | CHRIS VONG |
| Roof/Waste drainage to street | Cleared | 12/12/2022 | CINDY QI |
| Public Works-Highway Ded. | Cleared | 6/4/2023 | ADRIAN SANCHEZ |
| Public Works-Open Permits | Cleared | 6/4/2023 | ADRIAN SANCHEZ |
| Public Works-Sewers | Cleared | 6/4/2023 | ADRIAN SANCHEZ |
Contact Information
| Contractor | Home Creations Inc; Lic. No.: 1057627-B | , |
| Engineer | Le,, Thang Huu; Lic. No.: S4978 | 507 MAGELLAN RD ARCADIA, CA 91007 |
Inspector Information
| JUSTIN HAWLEY, (213) 202-3432 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 12/29/2022 | Approved | CALEB MEISTER |
| Underground Mechanical | 12/29/2022 | Approved | CALEB MEISTER |
| Underground Mechanical | 1/13/2023 | Corrections Issued | MICHAEL LEWIS |
| ELECTRICAL-Rough | 1/17/2023 | Corrections Issued | CALEB MEISTER |
| Floor/Roof Diaphrgm/Shear Wall | 1/17/2023 | Not Ready for Inspection | CALEB MEISTER |
| PLUMBING-Rough | 1/17/2023 | Corrections Issued | CALEB MEISTER |
| Deputy Wood Construction | 1/20/2023 | Conditional Approval | CALEB MEISTER |
| BUILDING-Rough-Frame | 1/25/2023 | Not Ready for Inspection | CALEB MEISTER |
| ELECTRICAL-Rough | 1/25/2023 | Corrections Issued | CALEB MEISTER |
| Floor/Roof Diaphrgm/Shear Wall | 1/25/2023 | Corrections Issued | CALEB MEISTER |
| Green Building Rough | 1/25/2023 | Not Ready for Inspection | CALEB MEISTER |
| HVAC-Rough | 1/25/2023 | Not Ready for Inspection | CALEB MEISTER |
| PLUMBING-Rough | 1/25/2023 | Approved | CALEB MEISTER |
| Underground Mechanical | 1/25/2023 | Approved | CALEB MEISTER |
| Verify Sprinkler Sign Off | 1/25/2023 | Not Ready for Inspection | CALEB MEISTER |
| Interior/Exterior Lathing | 1/31/2023 | Partial Approval | CALEB MEISTER |
| BUILDING-Rough-Frame | 2/2/2023 | Approved | CALEB MEISTER |
| Green Building Rough | 2/2/2023 | Approved | CALEB MEISTER |
| Insulation | 2/2/2023 | Corrections Issued | CALEB MEISTER |
| Interior/Exterior Lathing | 2/2/2023 | Partial Approval | CALEB MEISTER |
| Shower Pan | 2/2/2023 | Approved | CALEB MEISTER |
| Verify Sprinkler Sign Off | 2/2/2023 | Approved | CALEB MEISTER |
| Drywall Nailing | 2/9/2023 | Approved | CALEB MEISTER |
| ELECTRICAL-Rough | 2/9/2023 | Approved | CALEB MEISTER |
| HVAC-Rough | 2/9/2023 | Approved | CALEB MEISTER |
| Insulation | 2/9/2023 | Approved | CALEB MEISTER |
| Interior/Exterior Lathing | 2/9/2023 | Approved | CALEB MEISTER |
| Final | 5/16/2023 | Not Ready for Inspection | CALEB MEISTER |
| Footing/Foundation/Slab | 5/16/2023 | Approved | CALEB MEISTER |
| Green Building Final | 5/16/2023 | Not Ready for Inspection | CALEB MEISTER |
| SGSOV-Seismic Gas S/O Valve | 5/16/2023 | SGSOV Not Ready | CALEB MEISTER |
| Service/Power Release | 5/16/2023 | Not Ready for Inspection | CALEB MEISTER |
| Smoke Detectors | 5/16/2023 | Not Ready for Inspection | CALEB MEISTER |
| Final | 6/5/2023 | Corrections Issued | CALEB MEISTER |
| Green Building Final | 6/5/2023 | Approved | CALEB MEISTER |
| SGSOV-Seismic Gas S/O Valve | 6/5/2023 | SGSOV Approved | CALEB MEISTER |
| Service/Power Release | 6/5/2023 | Not Ready for Inspection | CALEB MEISTER |
| Smoke Detectors | 6/5/2023 | Approved | CALEB MEISTER |
| Final | 7/19/2023 | Corrections Issued | |
| Service/Power Release | 7/20/2023 | Approved | CALEB MEISTER |
| Final | 9/19/2023 | OK to Issue CofO | CALEB MEISTER |