1243 N COMMONWEALTH AVE 90029

Certificate Information: 1243 N COMMONWEALTH AVE 90029

Application / Permit
22010-10000-04769
Plan Check / Job No.
B22LA19277
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 2 STORY SINGLE FAMILY DWELLING WITH ATTACHED 2 CAR GARAGE
Permit Issued
Issued on 12/19/2023
Issuing Office
Metro
Current Status
CofO Issued on 12/2/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/23/2022 APPLICANT
Assigned to Plan Check Engineer 10/13/2022 MARCELA FRANQUEZ
Corrections Issued 10/20/2022 MARCELA FRANQUEZ
Quality Review Completed 11/2/2022 TEODORO DIAZ RODRIGUEZ
Building Plans Picked Up 11/9/2022 APPLICANT
Plan Check Approved 8/16/2023 MARCELA FRANQUEZ
Issued 12/19/2023 APPLICANT
CofO in Progress 12/2/2025 FREDDIE RIVERA
Permit Finaled 12/2/2025 DEROLD HAUFF
CofO Issued 12/2/2025 DEROLD HAUFF
Permit Finaled 12/2/2025 DEROLD HAUFF

Permit Application Clearance Information

Permit Cleared 1/11/2023 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 1/12/2023 JEANIE LAM
Sewer availability Cleared 1/12/2023 JEANIE LAM
Hydrant and Access approval Cleared 2/3/2023 KURT CORRAL
Low Impact Development Cleared 4/3/2023 LUIS LUVANO
Roof/Waste drainage to street Cleared 4/26/2023 CINDY QI
Trees in Parkway Cleared 5/2/2023 ADALBERTO VERA
GPI Written Notices Cleared 5/3/2023 MARCELA FRANQUEZ
Grading Pre-Inspection Cleared 5/3/2023 MARCELA FRANQUEZ

Contact Information

Contractor Ramos Manuel; Lic. No.: 937994-B 29021 BOUQUET CANYON RD SP 341      SANTA CLARITA, CA 91390
Engineer Hwang,, Junho; Lic. No.: S5592 815 FAIRVIEW AVE #205      SOUTH PASADENA, CA 91030
Engineer Kim,, Jin; Lic. No.: C64433 5 MONTELENA      IRVINE, CA 92602
Engineer Pukkanasut,, Jirayus; Lic. No.: C73728 1424 ROLLING HILLS DR      FULLERTON, CA 92835

Inspector Information

FREDDIE RIVERA, (213) 202-3437 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 3/22/2024 Approved FREDDIE RIVERA
Excavation/Setback/Form/Re-Bar 4/1/2024 Partial Approval FREDDIE RIVERA
Sewer 4/1/2024 Corrections Issued FREDDIE RIVERA
Sewer 4/3/2024 Approved FREDDIE RIVERA
Footing/Foundation/Slab 4/11/2024 Corrections Issued FREDDIE RIVERA
Footing/Foundation/Slab 4/15/2024 Corrections Issued BRENDAN MORELLI
Footing/Foundation/Slab 4/18/2024 Approved FREDDIE RIVERA
Floor/Roof Diaphrgm/Shear Wall 5/21/2024 Partial Approval ALIZAH MAYAGOITIA
Floor/Roof Diaphrgm/Shear Wall 6/21/2024 Partial Approval FREDDIE RIVERA
HVAC-Rough 9/19/2024 Corrections Issued FREDDIE RIVERA
PLUMBING-Rough 9/19/2024 Corrections Issued FREDDIE RIVERA
ELECTRICAL-Rough 9/20/2024 Corrections Issued JOHN QUINTANILLA
Wood Frame 9/23/2024 Partial Inspection FREDDIE RIVERA
ELECTRICAL-Rough 9/24/2024 Approved FREDDIE RIVERA
HVAC-Rough 9/24/2024 Approved FREDDIE RIVERA
Wood Frame 9/30/2024 Partial Inspection FREDDIE RIVERA
BUILDING-Rough-Frame 10/1/2024 Approved FREDDIE RIVERA
Green Building Rough 10/1/2024 Approved FREDDIE RIVERA
Interior/Exterior Lathing 10/1/2024 Partial Approval FREDDIE RIVERA
Shower Pan 10/1/2024 Partial Approval FREDDIE RIVERA
Verify Sprinkler Sign Off 10/1/2024 Approved FREDDIE RIVERA
Grounding or Bonding 10/8/2024 Partial Inspection FREDDIE RIVERA
Gas Test 10/11/2024 Partial Approval FREDDIE RIVERA
Insulation 10/11/2024 Conditional Approval FREDDIE RIVERA
Interior/Exterior Lathing 10/21/2024 Partial Approval FREDDIE RIVERA
Shower Pan 10/21/2024 Partial Approval FREDDIE RIVERA
Drywall Nailing 10/30/2024 Approved FREDDIE RIVERA
Interior/Exterior Lathing 11/1/2024 Partial Approval NICHOLAS LOPEZ
Shower Pan 2/21/2025 Approved ALEX COLIN
ELECTRICAL-Final 7/2/2025 Corrections Issued ENRIQUE MIRELES
Gas Test 7/2/2025 Not Ready for Inspection ENRIQUE MIRELES
HVAC-Final 7/2/2025 Not Ready for Inspection ENRIQUE MIRELES
PLUMBING-Final 7/2/2025 Not Ready for Inspection ENRIQUE MIRELES
Service/Power Release 7/2/2025 Not Ready for Inspection ENRIQUE MIRELES
ELECTRICAL-Final 7/16/2025 Approved FREDDIE RIVERA
Special/Order Compliance 7/23/2025 Corrections Issued FREDDIE RIVERA
Gas Test 7/29/2025 Approved FREDDIE RIVERA
HVAC-Final 7/29/2025 Approved FREDDIE RIVERA
Service/Power Release 8/12/2025 Partial Inspection FREDDIE RIVERA
PLUMBING-Final 8/29/2025 Approved FREDDIE RIVERA
Final 10/30/2025 Corrections Issued FREDDIE RIVERA
Green Building Final 10/30/2025 Approved FREDDIE RIVERA
SGSOV-Seismic Gas S/O Valve 10/30/2025 SGSOV Approved FREDDIE RIVERA
Service/Power Release 10/30/2025 Partial Inspection FREDDIE RIVERA
Smoke Detectors 10/30/2025 Approved FREDDIE RIVERA
Structural Steel Frame 10/30/2025 Partial Inspection FREDDIE RIVERA
Final 12/1/2025 OK to Issue CofO FREDDIE RIVERA
Service/Power Release 12/1/2025 Approved FREDDIE RIVERA
Structural Steel Frame 12/1/2025 Approved FREDDIE RIVERA