15446 W LA MAIDA ST 91403
Certificate Information: 15446 W LA MAIDA ST 91403
- Application / Permit
- 22010-10000-04759
- Plan Check / Job No.
- B22LA19251
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- eplan New 2-Story Single Family Home with Attached Garage.*** see comments ***
- Permit Issued
- Issued on 11/28/2022
- Issuing Office
- Current Status
- CofO Issued on 12/9/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/23/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 9/29/2022 | JAD BASMA |
| Corrections Issued | 10/4/2022 | JAD BASMA |
| Quality Review Completed | 10/19/2022 | TEODORO DIAZ RODRIGUEZ |
| Applicant returned to address corrections | 11/3/2022 | JAD BASMA |
| Plan Check Approved | 11/23/2022 | JAD BASMA |
| Issued | 11/28/2022 | APPLICANT |
| CofO in Progress | 12/9/2024 | THOMAS FINNILA |
| Permit Finaled | 12/9/2024 | JOHN JANSON |
| CofO Issued | 12/9/2024 | JOHN JANSON |
| Permit Finaled | 12/9/2024 | JOHN JANSON |
Permit Application Clearance Information
| Low Impact Development | Cleared | 10/19/2022 | LUIS LUVANO |
| Eng Process Fee Ord 176,300 | Cleared | 10/21/2022 | DAGOVERTO GUERRERO |
| Permit | Cleared | 10/21/2022 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 10/21/2022 | DAGOVERTO GUERRERO |
| Roof/Waste drainage to street | Cleared | 10/25/2022 | DAGOVERTO GUERRERO |
| Hydrant and Access approval | Cleared | 10/30/2022 | JOHN CONNEALLY |
| Trees in Parkway | Cleared | 11/16/2022 | ADALBERTO VERA |
Contact Information
| Architect | Niemerski,, Kenneth Chester; Lic. No.: NA23971 | , |
| Contractor | T J C Home Builders Llc; Lic. No.: 1025507-B | , |
| Engineer | Nguyen,, Huan; Lic. No.: NA64238 | , |
Inspector Information
| THOMAS FINNILA, (818) 774-4324 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 1/5/2024 | Approved | VINCENT HANLEY |
| Deputy Reinf. Concrete | 1/17/2024 | Partial Approval | VINCENT HANLEY |
| Excavation/Setback/Form/Re-Bar | 1/17/2024 | Approved | VINCENT HANLEY |
| Footing/Foundation/Slab | 1/17/2024 | Approved | VINCENT HANLEY |
| Deputy Reinf. Concrete | 1/18/2024 | Partial Approval | VINCENT HANLEY |
| Deputy Reinf. Concrete | 1/19/2024 | Partial Approval | VINCENT HANLEY |
| Sewer | 2/9/2024 | Approved | VINCENT HANLEY |
| Underground Mechanical | 2/9/2024 | Partial Approval | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 4/12/2024 | Partial Approval | VINCENT HANLEY |
| Deputy Wood Construction | 5/2/2024 | Conditional Approval | HENRY KIM |
| Floor/Roof Diaphrgm/Shear Wall | 5/7/2024 | Approved | GEVORK IPCHYAN |
| HVAC-Rough | 5/14/2024 | Corrections Issued | THOMAS FINNILA |
| Deputy Wood Construction | 5/15/2024 | Conditional Approval | THOMAS FINNILA |
| HVAC-Rough | 5/17/2024 | Conditional Approval | THOMAS FINNILA |
| PLUMBING-Rough | 5/17/2024 | Approved | THOMAS FINNILA |
| ELECTRICAL-Rough | 6/3/2024 | Approved | THOMAS FINNILA |
| Shower Pan | 6/3/2024 | Approved | THOMAS FINNILA |
| BUILDING-Rough-Frame | 6/11/2024 | Approved | THOMAS FINNILA |
| Green Building Rough | 6/11/2024 | Approved | THOMAS FINNILA |
| MERV13>=Rough | 6/11/2024 | Approved | THOMAS FINNILA |
| Verify Sprinkler Sign Off | 6/11/2024 | Approved | THOMAS FINNILA |
| Insulation | 6/18/2024 | Approved | JEFFREY HARTLINE |
| Interior/Exterior Lathing | 6/24/2024 | Partial Approval | THOMAS FINNILA |
| Drywall Nailing | 7/1/2024 | Approved | MORRIS JACKSON |
| Interior/Exterior Lathing | 7/17/2024 | Partial Approval | MORRIS JACKSON |
| ELECTRICAL-Final | 9/19/2024 | Approved | THOMAS FINNILA |
| PLUMBING-Final | 9/19/2024 | Partial Approval | THOMAS FINNILA |
| Gas Test | 9/30/2024 | Approved | THOMAS FINNILA |
| PLUMBING-Final | 9/30/2024 | Approved | THOMAS FINNILA |
| HVAC-Final | 10/10/2024 | Approved | THOMAS FINNILA |
| Final | 11/22/2024 | Partial Inspection | THOMAS FINNILA |
| Service/Power Release | 11/22/2024 | Approved | THOMAS FINNILA |
| Final | 12/9/2024 | OK to Issue CofO | THOMAS FINNILA |
| Green Building Final | 12/9/2024 | Approved | THOMAS FINNILA |
| MERV13>=Final | 12/9/2024 | Approved | THOMAS FINNILA |
| SGSOV-Seismic Gas S/O Valve | 12/9/2024 | SGSOV Approved | THOMAS FINNILA |
| Smoke Detectors | 12/9/2024 | Approved | THOMAS FINNILA |
| Deputy Wood Construction | 12/10/2024 | Approved | SEAN WIRCH |