2159 S BALSAM AVE 90025
Certificate Information: 2159 S BALSAM AVE 90025
- Application / Permit
- 22010-10000-04751
- Plan Check / Job No.
- B22LA19210
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- *EPLAN* GROUND FLOOR ADDITION (227 SF) TO (E) DETACHED 2-CAR GARAGE (386 SF) CONVERT TO ADU PER LAMC 12.22A.33(c)-(e).
- Permit Issued
- Issued on 2/6/2023
- Issuing Office
- Current Status
- CofO Issued on 4/21/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/30/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 10/6/2022 | VIVIAN LAO |
| Corrections Issued | 10/7/2022 | VIVIAN LAO |
| Applicant returned to address corrections | 10/27/2022 | VIVIAN LAO |
| Applicant returned to address corrections | 11/29/2022 | VIVIAN LAO |
| Plan Check Approved | 12/8/2022 | VIVIAN LAO |
| Issued | 2/6/2023 | APPLICANT |
| CofO in Progress | 4/8/2025 | DANIEL VERA |
| Permit Finaled | 4/21/2025 | RICHARD STEINBACH |
| CofO Issued | 4/21/2025 | RICHARD STEINBACH |
| Permit Finaled | 4/21/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Address approval | Cleared | 10/8/2022 | STEVEN JIN |
| Eng Process Fee Ord 176,300 | Cleared | 10/13/2022 | JENSON LEE |
| Sewer availability | Cleared | 10/13/2022 | JENSON LEE |
| Grading Pre-Inspection | Cleared | 12/1/2022 | KIRK LINKLATER |
| Roof/Waste drainage to street | Cleared | 12/2/2022 | JENSON LEE |
| Miscellaneous | Cleared | 12/3/2022 | SAUL GARCIA |
| Specific Plan | Cleared | 12/6/2022 | ROBERT SANCHEZ |
Contact Information
| Contractor | Sidekick Homes Llc; Lic. No.: 1098013-B | , |
| Engineer | Barakat,, Fouad Chafic; Lic. No.: C67449 | 11 CEDARWOOD DR POMONA, CA 91766 |
Inspector Information
| DAVID SCANTLIN, (310) 914-3863 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/24/2023 | Partial Inspection | STEPHANIE SWANSON |
| Footing/Foundation/Slab | 9/25/2023 | Corrections Issued | STEPHANIE SWANSON |
| Pre-Inspection | 9/25/2023 | Partial Inspection | STEPHANIE SWANSON |
| Underground Mechanical | 9/25/2023 | Partial Inspection | STEPHANIE SWANSON |
| Footing/Foundation/Slab | 10/12/2023 | Not Ready for Inspection | STEPHANIE SWANSON |
| Footing/Foundation/Slab | 11/2/2023 | Corrections Issued | STEPHANIE SWANSON |
| Footing/Foundation/Slab | 4/19/2024 | Partial Inspection | STEPHANIE SWANSON |
| Footing/Foundation/Slab | 5/14/2024 | Corrections Issued | STEPHANIE SWANSON |
| PLUMBING-Rough | 5/14/2024 | Partial Approval | STEPHANIE SWANSON |
| Excavation/Setback/Form/Re-Bar | 5/15/2024 | Corrections Issued | STEPHANIE SWANSON |
| Excavation/Setback/Form/Re-Bar | 5/20/2024 | Approved | STEPHANIE SWANSON |
| ELECTRICAL-Rough | 6/21/2024 | Corrections Issued | STEPHANIE SWANSON |
| PLUMBING-Rough | 6/21/2024 | Corrections Issued | STEPHANIE SWANSON |
| Underground Mechanical | 6/21/2024 | Partial Approval | STEPHANIE SWANSON |
| Rough-Elec/Plmb/HVAC | 7/11/2024 | Not Ready for Inspection | CHRISTOPHER WILSON |
| ELECTRICAL-Rough | 7/25/2024 | Corrections Issued | STEPHANIE SWANSON |
| Floor/Roof Diaphrgm/Shear Wall | 7/25/2024 | Corrections Issued | STEPHANIE SWANSON |
| HVAC-Rough | 7/25/2024 | Corrections Issued | STEPHANIE SWANSON |
| PLUMBING-Rough | 7/25/2024 | Approved | STEPHANIE SWANSON |
| BUILDING-Rough-Frame | 8/5/2024 | Partial Approval | SEAN HAUPT |
| Rough-Elec/Plmb/HVAC | 8/5/2024 | Approved | SEAN HAUPT |
| Insulation | 8/12/2024 | Not Ready for Inspection | STEPHANIE SWANSON |
| Interior/Exterior Lathing | 8/12/2024 | Corrections Issued | STEPHANIE SWANSON |
| BUILDING-Rough-Frame | 8/21/2024 | Approved | STEPHANIE SWANSON |
| Green Building Rough | 8/21/2024 | Approved | STEPHANIE SWANSON |
| Insulation | 8/21/2024 | Approved | STEPHANIE SWANSON |
| Interior/Exterior Lathing | 8/21/2024 | Partial Approval | STEPHANIE SWANSON |
| Drywall Nailing | 9/5/2024 | Approved | STEPHANIE SWANSON |
| Interior/Exterior Lathing | 10/16/2024 | Not Ready for Inspection | STEPHANIE SWANSON |
| Shower Pan | 10/16/2024 | Not Ready for Inspection | STEPHANIE SWANSON |
| Interior/Exterior Lathing | 11/14/2024 | Conditional Approval | STEPHANIE SWANSON |
| Shower Pan | 11/14/2024 | Not Ready for Inspection | STEPHANIE SWANSON |
| Interior/Exterior Lathing | 11/20/2024 | Approved | STEPHANIE SWANSON |
| Shower Pan | 11/20/2024 | Approved | STEPHANIE SWANSON |
| SGSOV-Seismic Gas S/O Valve | 3/18/2025 | SGSOV Not Ready | DANIEL VERA |
| ELECTRICAL-Final | 4/2/2025 | Corrections Issued | STEPHANIE SWANSON |
| Final | 4/2/2025 | Conditional Approval | STEPHANIE SWANSON |
| Footing/Foundation/Slab | 4/2/2025 | Approved | STEPHANIE SWANSON |
| Green Building Final | 4/2/2025 | Approved | STEPHANIE SWANSON |
| HVAC-Final | 4/2/2025 | Corrections Issued | STEPHANIE SWANSON |
| PLUMBING-Final | 4/2/2025 | Approved | STEPHANIE SWANSON |
| SGSOV-Seismic Gas S/O Valve | 4/2/2025 | SGSOV Approved | STEPHANIE SWANSON |
| Smoke Detectors | 4/2/2025 | Corrections Issued | STEPHANIE SWANSON |
| ELECTRICAL-Final | 4/7/2025 | Approved | DANIEL VERA |
| Final | 4/7/2025 | OK to Issue CofO | DANIEL VERA |
| HVAC-Final | 4/7/2025 | Approved | DANIEL VERA |
| Service/Power Release | 4/7/2025 | Approved | DANIEL VERA |
| Smoke Detectors | 4/7/2025 | Approved | DANIEL VERA |