1915 W PARK AVE 90026

Certificate Information: 1915 W PARK AVE 90026

Application / Permit
22010-10000-04732
Plan Check / Job No.
B22LA19098
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
NEW 7 STORY 36 UNITS (4 ELI = 10%) AFFORDABLE HOUSING APARTMENT TO INCLUDE 5 STORY TYPE IIIA APARTMENT OVER 2 STORY TYPE IA PARKING GARAGE, TIER 3 TOC WITH ADDITIONAL INCENTIVES
Permit Issued
Issued on 11/7/2023
Issuing Office
Metro
Current Status
CofO Issued on 11/26/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/30/2022 APPLICANT
Assigned to Plan Check Engineer 10/13/2022 VU NGUYEN
Corrections Issued 10/20/2022 VU NGUYEN
Quality Review Completed 10/20/2022 EUGENE BARBEAU
Building Plans Picked Up 10/25/2022 APPLICANT
Plan Check Approved 10/19/2023 KEVIN MORALES
Issued 11/7/2023 APPLICANT
Permit Finaled 11/26/2025 ERNESTO CORRAL
CofO Issued 11/26/2025 ERNESTO CORRAL
Permit Finaled 11/26/2025 ERNESTO CORRAL

Permit Application Clearance Information

SB8 RUD Cleared 1/10/2023 LOUIE MILLER
Address approval Cleared 1/26/2023 STEVE MELGAR
Eng Process Fee Ord 176,300 Cleared 1/26/2023 ADRIAN SANCHEZ
Building over 36-ft Cleared 2/8/2023 CALOSHA APPROVED
Sewer availability Cleared 2/16/2023 JEANETTE VONG
Bicycle Parking Cleared 2/17/2023 KATHERINE MENDOZA
GPI Written Notices Cleared 4/14/2023 VU NGUYEN
Grading Pre-Inspection Cleared 4/14/2023 VU NGUYEN
Supp. Use District POD/CDO/TDO Cleared 5/3/2023 ERICK MORALES
Green Code Cleared 6/6/2023 VU NGUYEN
DAS Clearance Cleared 6/16/2023 VU NGUYEN
Highway dedication Cleared 6/26/2023 TREVOR QUAN
Permit Cleared 6/26/2023 TREVOR QUAN
Low Impact Development Cleared 9/5/2023 MARTIN FRAGOSO
Work Adjacent to Public Way Cleared 9/6/2023 LARRY LEE
Roof/Waste drainage to street Cleared 9/13/2023 ABEL CASILLAS
Density Bonus 12.22.A.31 Cleared 9/14/2023 JAMES MCCARTHY
Fire Marshal Fire Life Safety Cleared 9/14/2023 ANDREW KO
Miscellaneous Cleared 9/19/2023 YINGSHI HUANG
ZA Case Cleared 9/19/2023 YINGSHI HUANG
ZA Case Cleared 9/19/2023 YINGSHI HUANG
Hydrant and Access approval Cleared 10/10/2023 LAVEON RIDER
Frnt yard landscape/Water mgmt Cleared 10/18/2023 RYAN LY
Miscellaneous Cleared 10/18/2023 RYAN LY
Opn space landscape/Water mgmt Cleared 10/18/2023 RYAN LY
ZA Case Cleared 10/18/2023 RYAN LY
ZI Cleared 10/18/2023 RYAN LY

Contact Information

Contractor Owner-Builder       ,

Inspector Information

DAVID BURKHEAD, (213) 482-7294 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Final 2/14/2024 Not Ready for Inspection DAVID BURKHEAD
Excavation/Setback/Form/Re-Bar 3/11/2024 Partial Inspection JEFFREY FULTON
Deputy Reinf. Concrete 3/12/2024 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Concrete 3/18/2024 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Concrete 3/21/2024 Conditional Approval JEFFREY FULTON
Excavation/Setback/Form/Re-Bar 3/21/2024 Partial Inspection JEFFREY FULTON
Deputy Drilled-In Anchors 3/27/2024 Conditional Approval JEFFREY FULTON
Deputy Reinf. Masonry 3/27/2024 Conditional Approval JEFFREY FULTON
Excavation/Setback/Form/Re-Bar 3/27/2024 Partial Inspection JEFFREY FULTON
Deputy Other (see comments) 4/3/2024 Conditional Approval JEFFREY FULTON
Excavation/Setback/Form/Re-Bar 4/3/2024 Not Ready for Inspection JEFFREY FULTON
Deputy Other (see comments) 4/5/2024 Conditional Approval LARRY ARNICK
Excavation/Setback/Form/Re-Bar 4/5/2024 Partial Approval LARRY ARNICK
Deputy Reinf. Concrete 4/25/2024 Approved DAVID BURKHEAD
Green Building Rough 4/25/2024 Not Ready for Inspection DAVID BURKHEAD
Reinforced Concrete Frame 4/25/2024 Partial Approval DAVID BURKHEAD
Verify Sprinkler Sign Off 4/25/2024 Not Ready for Inspection DAVID BURKHEAD
Deputy Reinf. Concrete 4/29/2024 Conditional Approval DAVID BURKHEAD
Green Building Rough 5/1/2024 Not Ready for Inspection JEFFREY FULTON
Reinforced Concrete Frame 5/1/2024 Corrections Issued JEFFREY FULTON
Verify Sprinkler Sign Off 5/1/2024 Not Ready for Inspection JEFFREY FULTON
Green Building Rough 5/8/2024 Not Ready for Inspection TIMOTHY POWELL
Reinforced Concrete Frame 5/8/2024 Partial Approval TIMOTHY POWELL
Verify Sprinkler Sign Off 5/8/2024 Not Ready for Inspection TIMOTHY POWELL
Deputy Reinf. Masonry 5/22/2024 Conditional Approval JEFFREY FULTON
Masonry Wall/Backfill 5/22/2024 Corrections Issued JEFFREY FULTON
Green Building Rough 6/18/2024 Partial Inspection EDWIN GREGORYONA
Reinforced Concrete Frame 6/18/2024 Partial Approval EDWIN GREGORYONA
Verify Sprinkler Sign Off 6/18/2024 Not Ready for Inspection EDWIN GREGORYONA
Green Building Rough 7/19/2024 Not Ready for Inspection DAVID BURKHEAD
Verify Sprinkler Sign Off 7/19/2024 Not Ready for Inspection DAVID BURKHEAD
Wood Frame 7/19/2024 Not Ready for Inspection DAVID BURKHEAD
Floor/Roof Diaphrgm/Shear Wall 7/22/2024 Partial Inspection JEFFREY FULTON
Deputy Wood Construction 7/25/2024 Conditional Approval MICHAEL ROSENBERG
Floor/Roof Diaphrgm/Shear Wall 8/8/2024 Partial Inspection JEFFREY FULTON
Green Building Rough 8/8/2024 Not Ready for Inspection JEFFREY FULTON
Verify Sprinkler Sign Off 8/8/2024 Not Ready for Inspection JEFFREY FULTON
Wood Frame 8/8/2024 Not Ready for Inspection JEFFREY FULTON
Floor/Roof Diaphrgm/Shear Wall 8/26/2024 Partial Inspection JEFFREY FULTON
Floor/Roof Diaphrgm/Shear Wall 9/23/2024 Partial Inspection JEFFREY FULTON
Green Building Rough 10/10/2024 Not Ready for Inspection RAFAEL CORTES
Verify Sprinkler Sign Off 10/10/2024 Not Ready for Inspection RAFAEL CORTES
Wood Frame 10/10/2024 Partial Approval RAFAEL CORTES
Floor/Roof Diaphrgm/Shear Wall 10/15/2024 Partial Inspection JEFFREY FULTON
Deputy Wood Construction 10/18/2024 Conditional Approval JEFFREY FULTON
Floor/Roof Diaphrgm/Shear Wall 10/18/2024 Conditional Approval JEFFREY FULTON
Green Building Rough 10/18/2024 Not Ready for Inspection JEFFREY FULTON
Floor/Roof Diaphrgm/Shear Wall 10/22/2024 Partial Inspection JEFFREY FULTON
Drywall Nailing 11/4/2024 Partial Inspection JEFFREY FULTON
Green Building Rough 11/4/2024 Not Ready for Inspection JEFFREY FULTON
Drywall Nailing 11/5/2024 Partial Inspection JEFFREY FULTON
Floor/Roof Diaphrgm/Shear Wall 11/5/2024 Partial Inspection JEFFREY FULTON
Floor/Roof Diaphrgm/Shear Wall 11/15/2024 Partial Inspection JEFFREY FULTON
Drywall Nailing 11/19/2024 Partial Inspection JEFFREY FULTON
Green Building Rough 11/19/2024 Not Ready for Inspection JEFFREY FULTON
Green Building Rough 12/3/2024 Not Ready for Inspection JEFFREY FULTON
Verify Sprinkler Sign Off 12/3/2024 Not Ready for Inspection JEFFREY FULTON
Wood Frame 12/3/2024 Not Ready for Inspection JEFFREY FULTON
Floor/Roof Diaphrgm/Shear Wall 12/4/2024 Partial Inspection JEFFREY FULTON
Wood Frame 12/4/2024 Partial Inspection JEFFREY FULTON
Drywall Nailing 12/10/2024 Not Ready for Inspection RAMAZANALI ALMASI
Green Building Rough 12/10/2024 Not Ready for Inspection RAMAZANALI ALMASI
Insulation 12/10/2024 Not Ready for Inspection RAMAZANALI ALMASI
Deputy Wood Construction 12/11/2024 Conditional Approval JEFFREY FULTON
Insulation 12/11/2024 Partial Inspection JEFFREY FULTON
Verify Sprinkler Sign Off 12/11/2024 Not Ready for Inspection JEFFREY FULTON
Wood Frame 12/11/2024 Partial Inspection JEFFREY FULTON
Wood Frame 12/12/2024 Partial Inspection JEFFREY FULTON
Insulation 12/13/2024 Partial Inspection JEFFREY FULTON
Wood Frame 12/13/2024 Partial Inspection JEFFREY FULTON
Insulation 12/16/2024 Partial Inspection JEFFREY FULTON
Drywall Nailing 12/17/2024 Partial Inspection JEFFREY FULTON
Insulation 12/17/2024 Partial Inspection JEFFREY FULTON
Wood Frame 12/17/2024 Partial Inspection JEFFREY FULTON
Drywall Nailing 12/18/2024 Partial Inspection JEFFREY FULTON
Green Building Rough 12/18/2024 Approved JEFFREY FULTON
Insulation 12/23/2024 Partial Approval TIMOTHY POWELL
Interior/Exterior Lathing 12/23/2024 Not Ready for Inspection TIMOTHY POWELL
Verify Sprinkler Sign Off 12/23/2024 Not Ready for Inspection TIMOTHY POWELL
Wood Frame 12/23/2024 Not Ready for Inspection TIMOTHY POWELL
Floor/Roof Diaphrgm/Shear Wall 12/31/2024 Partial Inspection JEFFREY FULTON
Verify Sprinkler Sign Off 12/31/2024 Not Ready for Inspection JEFFREY FULTON
Wood Frame 12/31/2024 Not Ready for Inspection JEFFREY FULTON
Insulation 1/7/2025 Partial Approval TIMOTHY POWELL
Insulation 1/13/2025 Not Ready for Inspection LARRY ARNICK
Interior/Exterior Lathing 1/13/2025 Not Ready for Inspection LARRY ARNICK
Insulation 1/29/2025 Partial Inspection JEFFREY FULTON
Wood Frame 1/29/2025 Partial Inspection JEFFREY FULTON
Insulation 1/31/2025 Partial Inspection JEFFREY FULTON
Drywall Nailing 2/3/2025 Partial Inspection JEFFREY FULTON
Insulation 2/3/2025 Partial Inspection JEFFREY FULTON
Drywall Nailing 2/6/2025 Partial Inspection JEFFREY FULTON
Wood Frame 2/6/2025 Partial Inspection JEFFREY FULTON
Insulation 2/7/2025 Partial Inspection JEFFREY FULTON
Insulation 2/10/2025 Partial Inspection JEFFREY FULTON
Verify Sprinkler Sign Off 2/10/2025 Not Ready for Inspection JEFFREY FULTON
Wood Frame 2/10/2025 Not Ready for Inspection JEFFREY FULTON
Interior/Exterior Lathing 2/11/2025 Partial Inspection JEFFREY FULTON
Wood Frame 2/11/2025 Partial Inspection JEFFREY FULTON
Insulation 2/12/2025 Not Ready for Inspection DAVID BURKHEAD
Interior/Exterior Lathing 2/12/2025 Partial Approval DAVID BURKHEAD
Special/Order Compliance 2/13/2025 Partial Inspection RAFAEL ESPINOZA
Drywall Nailing 2/14/2025 Not Ready for Inspection LUIS CCAMACHO
Insulation 2/14/2025 Partial Approval LUIS CCAMACHO
Interior/Exterior Lathing 2/14/2025 Partial Approval LUIS CCAMACHO
Insulation 2/18/2025 Not Ready for Inspection JAMES POWERS
Verify Sprinkler Sign Off 2/18/2025 Not Ready for Inspection JAMES POWERS
Wood Frame 2/18/2025 Partial Approval JAMES POWERS
Drywall Nailing 2/24/2025 Partial Approval EDWIN GREGORYONA
Insulation 2/24/2025 Partial Approval EDWIN GREGORYONA
Drywall Nailing 3/6/2025 Partial Inspection JEFFREY FULTON
Light Gage Steel Frame 3/6/2025 Partial Inspection JEFFREY FULTON
Drywall Nailing 3/19/2025 Not Ready for Inspection JEFFREY FULTON
Floor/Roof Diaphrgm/Shear Wall 3/19/2025 Partial Inspection JEFFREY FULTON
Verify Sprinkler Sign Off 3/19/2025 Not Ready for Inspection JEFFREY FULTON
Insulation 3/20/2025 Not Ready for Inspection JEFFREY FULTON
Drywall Nailing 3/24/2025 Not Ready for Inspection JEFFREY FULTON
Insulation 3/24/2025 Partial Inspection JEFFREY FULTON
Interior/Exterior Lathing 3/24/2025 Not Ready for Inspection JEFFREY FULTON
Special/Order Compliance 4/25/2025 Approved DAVID BURKHEAD
Pre-Inspection 5/12/2025 Partial Inspection JEFFREY FULTON
Light Gage Steel Frame 5/14/2025 Partial Inspection JEFFREY FULTON
Drywall Nailing 5/21/2025 Partial Inspection JEFFREY FULTON
Pre-Inspection 7/28/2025 Approved DAVID BURKHEAD
Drywall Nailing 9/2/2025 Approved JEFFREY FULTON
Final 9/2/2025 Not Ready for Inspection JEFFREY FULTON
Footing/Foundation/Slab 9/2/2025 Approved JEFFREY FULTON
Green Building Final 9/2/2025 Not Ready for Inspection JEFFREY FULTON
Reinforced Concrete Frame 9/2/2025 Not Ready for Inspection JEFFREY FULTON
Reinforced Masonry Frame 9/2/2025 Not Ready for Inspection JEFFREY FULTON
SGSOV-Seismic Gas S/O Valve 9/2/2025 SGSOV Not Ready JEFFREY FULTON
Smoke Detectors 9/2/2025 Not Ready for Inspection JEFFREY FULTON
Verify Sprinkler Sign Off 9/2/2025 Not Ready for Inspection JEFFREY FULTON
Wood Frame 9/2/2025 Not Ready for Inspection JEFFREY FULTON
Final 10/14/2025 Not Ready for Inspection JEFFREY FULTON
Green Building Final 10/14/2025 Not Ready for Inspection JEFFREY FULTON
Reinforced Concrete Frame 10/14/2025 Not Ready for Inspection JEFFREY FULTON
Reinforced Masonry Frame 10/14/2025 Not Ready for Inspection JEFFREY FULTON
SGSOV-Seismic Gas S/O Valve 10/14/2025 SGSOV Not Ready JEFFREY FULTON
Smoke Detectors 10/14/2025 Not Ready for Inspection JEFFREY FULTON
Verify Sprinkler Sign Off 10/14/2025 Not Ready for Inspection JEFFREY FULTON
Wood Frame 10/14/2025 Not Ready for Inspection JEFFREY FULTON
Final 10/16/2025 Partial Inspection JEFFREY FULTON
Green Building Final 10/16/2025 Approved JEFFREY FULTON
Reinforced Concrete Frame 10/16/2025 Approved JEFFREY FULTON
Reinforced Masonry Frame 10/16/2025 Approved JEFFREY FULTON
SGSOV-Seismic Gas S/O Valve 10/16/2025 SGSOV Approved JEFFREY FULTON
Smoke Detectors 10/16/2025 Approved JEFFREY FULTON
Verify Sprinkler Sign Off 10/16/2025 Approved JEFFREY FULTON
Wood Frame 10/16/2025 Approved JEFFREY FULTON
Final 10/20/2025 Partial Approval JEFFREY FULTON
Final 11/24/2025 Partial Inspection JEFFREY FULTON
Special/Order Compliance 11/25/2025 Approved DAVID BURKHEAD