23036 W VENTURA BLVD 1-100 91364

Certificate Information: 23036 W VENTURA BLVD 1-100 91364

Application / Permit
22010-10000-04695
Plan Check / Job No.
B22LA18957
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
ePLAN. NEW 8 STORY 100 UNITS (100% AFFORDABLE HOUSING) APARTMENT TO INCLUDE 5 STORY TYPE IIIA APARTMENT OVER 3 STORY TYPE IA APARTMENT/PARKING/LOBBY/ USING DENSITY BONUS WITH ADDITIONAL INCENTIVE, 12.22.A.25
Permit Issued
Issued on 12/26/2023
Issuing Office
Metro
Current Status
Issued on 12/26/2023
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 10/11/2022 APPLICANT
Assigned to Plan Check Engineer 10/13/2022 KEVIN MORALES
Corrections Issued 10/18/2022 KEVIN MORALES
Quality Review Completed 10/19/2022 EUGENE BARBEAU
Applicant returned to address corrections 11/29/2022 KEVIN MORALES
Applicant returned to address corrections 12/21/2022 KEVIN MORALES
Plan Check Approved 12/21/2023 KEVIN MORALES
Issued 12/26/2023 APPLICANT

Permit Application Clearance Information

"D" conditions Cleared 2/6/2023 MARITZA PRZEKOP
Miscellaneous Cleared 2/6/2023 MARITZA PRZEKOP
Miscellaneous Cleared 2/6/2023 MARITZA PRZEKOP
Miscellaneous Cleared 2/6/2023 MARITZA PRZEKOP
Specific Plan Cleared 2/6/2023 MARITZA PRZEKOP
Disturb/Remove Protected Trees Cleared 2/14/2023 ADALBERTO VERA
Trees in Parkway Cleared 2/16/2023 ADALBERTO VERA
Address approval Cleared 4/19/2023 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 4/19/2023 CARLOS AGUILERA
Highway dedication Cleared 4/27/2023 CARLOS AGUILERA
Miscellaneous Cleared 4/27/2023 RYAN LY
Permanent Supportive Housing Cleared 4/27/2023 RYAN LY
Permit Cleared 4/27/2023 CARLOS AGUILERA
Building over 36-ft Cleared 9/21/2023 CALOSHA APPROVED
GPI Written Notices Cleared 9/21/2023 KEVIN MORALES
Grading Pre-Inspection Cleared 9/21/2023 KEVIN MORALES
Low Impact Development Cleared 10/19/2023 ORVAL HERNANDEZ-MARCI
Driveway location Cleared 10/27/2023 BRANDON WILSON
Specific Plan Cleared 10/27/2023 BRANDON WILSON
Construction near power lines Cleared 11/8/2023 RIDWAN HARDY
Fire Marshal Fire Life Safety Cleared 11/9/2023 MENOA AGHAJANI
Bicycle Parking Cleared 11/14/2023 CARLOS AGUILERA
Hydrant and Access approval Cleared 11/14/2023 LAVEON RIDER
Roof/Waste drainage to street Cleared 11/16/2023 MARKOS PEREZ-BRAN
CPC Cleared 11/17/2023 RYAN LY
Frnt yard landscape/Water mgmt Cleared 11/17/2023 RYAN LY
Miscellaneous Cleared 11/17/2023 MARITZA PRZEKOP
Miscellaneous Cleared 11/17/2023 RYAN LY
Miscellaneous Cleared 11/17/2023 RYAN LY
Opn space landscape/Water mgmt Cleared 11/17/2023 RYAN LY
Public Housing Cleared 11/20/2023 JOEL LAUNCHBAUGH
Density Bonus Cleared 11/21/2023 KENNETH LE
Sewer availability Cleared 11/21/2023 MARKOS PEREZ-BRAN
DAS Clearance Cleared 11/27/2023 KEVIN MORALES
Green Code Cleared 11/30/2023 KEVIN MORALES

Contact Information

Contractor Dreyfuss Builders Llc; Lic. No.: 1090458-B 2850 SATURN ST      BREA, CA 92821

Inspector Information

ROBERT DAVIS, (818) 374-1125 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

Special/Order Compliance 7/24/2026   
Special/Order Compliance 7/27/2026   

Inspection Request History

Deputy Steel/Welding 2/15/2024 Conditional Approval KENNETH ROBERTS
Deputy Steel/Welding 2/22/2024 Conditional Approval ROBERT DAVIS
Pre-Inspection 2/29/2024 Approved ROBERT DAVIS
Deputy Steel/Welding 3/11/2024 Conditional Approval CAMERON CHABAN
Deputy Steel/Welding 3/11/2024 Conditional Approval ROBERT DAVIS
Deputy Steel/Welding 3/26/2024 Conditional Approval ROBERT DAVIS
Deputy Steel/Welding 3/29/2024 Conditional Approval ROBERT DAVIS
Special/Order Compliance 3/29/2024 Partial Inspection BRIAN KELLY
Excavation/Setback/Form/Re-Bar 4/18/2024 Partial Inspection ROBERT DAVIS
Special/Order Compliance 4/22/2024 Partial Inspection ROBERT DAVIS
Excavation/Setback/Form/Re-Bar 5/9/2024 Not Ready for Inspection ROBERT DAVIS
Footing/Foundation/Slab 5/22/2024 Partial Inspection ROBERT DAVIS
Piling/Pier/Caisson 5/23/2024 Partial Inspection ROBERT DAVIS
Piling/Pier/Caisson 5/24/2024 Partial Approval ROBERT DAVIS
Deputy Reinf. Concrete 5/28/2024 Conditional Approval ROBERT DAVIS
Piling/Pier/Caisson 5/28/2024 Partial Approval ROBERT DAVIS
Deputy Reinf. Concrete 5/29/2024 Conditional Approval ROBERT DAVIS
Piling/Pier/Caisson 5/29/2024 Not Ready for Inspection ROBERT DAVIS
Deputy Reinf. Concrete 5/30/2024 Approved ROBERT DAVIS
Deputy Shotcrete 6/5/2024 Conditional Approval ROBERT DAVIS
Special/Order Compliance 6/5/2024 Approved ROBERT DAVIS
Footing/Foundation/Slab 6/6/2024 Not Ready for Inspection ROBERT DAVIS
Deputy Reinf. Concrete 6/7/2024 Conditional Approval ROBERT DAVIS
Footing/Foundation/Slab 6/7/2024 Partial Approval ROBERT DAVIS
Deputy Reinf. Concrete 6/11/2024 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 6/12/2024 Conditional Approval ROBERT DAVIS
Deputy Reinf. Concrete 6/13/2024 Approved ROBERT DAVIS
Special/Order Compliance 6/13/2024 Partial Approval ROBERT DAVIS
Footing/Foundation/Slab 6/14/2024 Partial Inspection ROBERT DAVIS
Deputy Reinf. Concrete 6/17/2024 Conditional Approval ROBERT DAVIS
Deputy Reinf. Concrete 6/18/2024 Conditional Approval ROBERT DAVIS
Deputy Reinf. Concrete 6/20/2024 Conditional Approval ROBERT DAVIS
Deputy Reinf. Concrete 6/21/2024 Conditional Approval ROBERT DAVIS
Deputy Reinf. Concrete 6/25/2024 Conditional Approval ROBERT DAVIS
Footing/Foundation/Slab 6/25/2024 Not Ready for Inspection ROBERT DAVIS
Deputy Reinf. Concrete 6/26/2024 Conditional Approval ROBERT DAVIS
Excavation/Setback/Form/Re-Bar 6/26/2024 Not Ready for Inspection ROBERT DAVIS
Deputy Reinf. Concrete 6/27/2024 Conditional Approval ROBERT DAVIS
Excavation/Setback/Form/Re-Bar 6/27/2024 Not Ready for Inspection ROBERT DAVIS
Deputy Reinf. Concrete 6/28/2024 Approved ROBERT DAVIS
Piling/Pier/Caisson 6/28/2024 Partial Approval ROBERT DAVIS
Deputy Reinf. Concrete 7/1/2024 Conditional Approval ROBERT DAVIS
Special/Order Compliance 7/1/2024 Not Ready for Inspection ROBERT DAVIS
Deputy Shotcrete 7/2/2024 Approved ROBERT DAVIS
Reinforced Concrete Frame 7/2/2024 Partial Approval ROBERT DAVIS
Deputy Reinf. Concrete 7/3/2024 Approved ROBERT DAVIS
Reinforced Concrete Frame 7/3/2024 Partial Approval ROBERT DAVIS
Deputy Shotcrete 7/8/2024 Conditional Approval ROBERT DAVIS
Deputy Reinf. Concrete 7/9/2024 Conditional Approval ROBERT DAVIS
Deputy Shotcrete 7/9/2024 Conditional Approval ROBERT DAVIS
Deputy Reinf. Concrete 7/10/2024 Conditional Approval ROBERT DAVIS
Deputy Shotcrete 7/10/2024 Conditional Approval ROBERT DAVIS
Deputy Reinf. Concrete 7/11/2024 Conditional Approval ROBERT DAVIS
Deputy Shotcrete 7/11/2024 Conditional Approval ROBERT DAVIS
Deputy Reinf. Concrete 7/12/2024 Approved ROBERT DAVIS
Excavation/Setback/Form/Re-Bar 7/12/2024 Partial Approval ROBERT DAVIS
Deputy Shotcrete 7/15/2024 Conditional Approval ROBERT DAVIS
Green Building Rough 7/15/2024 No Access for Inspection ROBERT DAVIS
Reinforced Concrete Frame 7/15/2024 Not Ready for Inspection ROBERT DAVIS
Verify Sprinkler Sign Off 7/15/2024 Not Ready for Inspection ROBERT DAVIS
Special/Order Compliance 7/16/2024 Partial Inspection ROBERT DAVIS
Deputy Reinf. Concrete 7/17/2024 Approved ROBERT DAVIS
Reinforced Concrete Frame 7/17/2024 Partial Approval ROBERT DAVIS
Deputy Reinf. Concrete 7/18/2024 Conditional Approval ROBERT DAVIS
Deputy Shotcrete 7/18/2024 Conditional Approval ROBERT DAVIS
Deputy Reinf. Concrete 7/19/2024 Conditional Approval ROBERT DAVIS
Deputy Shotcrete 7/19/2024 Conditional Approval ROBERT DAVIS
Deputy Shotcrete 7/23/2024 Approved ROBERT DAVIS
Footing/Foundation/Slab 7/23/2024 Partial Approval ROBERT DAVIS
Deputy Shotcrete 7/24/2024 Conditional Approval ROBERT DAVIS
Deputy Shotcrete 7/26/2024 Conditional Approval ROBERT DAVIS
Deputy Shotcrete 7/29/2024 Conditional Approval CAMERON CHABAN
Deputy Shotcrete 7/30/2024 Approved ROBERT DAVIS
Excavation/Setback/Form/Re-Bar 7/30/2024 Partial Approval ROBERT DAVIS
Deputy Reinf. Concrete 8/1/2024 Conditional Approval ROBERT DAVIS
Excavation/Setback/Form/Re-Bar 8/9/2024 Not Ready for Inspection ROBERT DAVIS
Excavation/Setback/Form/Re-Bar 8/12/2024 Partial Approval DANIEL VARNUM
Deputy Shotcrete 8/13/2024 Conditional Approval CAMERON CHABAN
Deputy Reinf. Concrete 8/28/2024 Conditional Approval GREGORY POMISH
Footing/Foundation/Slab 8/28/2024 Partial Approval GREGORY POMISH
Deputy Reinf. Concrete 8/30/2024 Conditional Approval ROBERT DAVIS
Green Building Rough 9/9/2024 Not Ready for Inspection ROBERT DAVIS
Verify Sprinkler Sign Off 9/9/2024 Not Ready for Inspection ROBERT DAVIS
Reinforced Concrete Frame 9/12/2024 Partial Approval ROBERT DAVIS
Deputy Reinf. Concrete 9/13/2024 Partial Approval ROBERT DAVIS
Green Building Rough 9/25/2024 Not Ready for Inspection ROBERT DAVIS
Reinforced Concrete Frame 9/25/2024 Partial Approval ROBERT DAVIS
Verify Sprinkler Sign Off 9/25/2024 Not Ready for Inspection ROBERT DAVIS
Excavation/Setback/Form/Re-Bar 10/15/2024 Partial Inspection ROBERT DAVIS
Excavation/Setback/Form/Re-Bar 10/17/2024 Not Ready for Inspection GREGORY POMISH
Special/Order Compliance 10/18/2024 Not Ready for Inspection GREGORY POMISH
Excavation/Setback/Form/Re-Bar 10/23/2024 Partial Approval GREGORY POMISH
Deputy Reinf. Concrete 10/24/2024 Conditional Approval JEFFREY DURAN
Green Building Rough 10/30/2024 Not Ready for Inspection ROBERT DAVIS
Reinforced Concrete Frame 10/30/2024 Partial Approval ROBERT DAVIS
Verify Sprinkler Sign Off 10/30/2024 Not Ready for Inspection ROBERT DAVIS
Excavation/Setback/Form/Re-Bar 11/4/2024 Partial Approval ROBERT DAVIS
Deputy Shotcrete 11/5/2024 Approved ROBERT DAVIS
Excavation/Setback/Form/Re-Bar 11/5/2024 Partial Approval ROBERT DAVIS
Deputy Reinf. Concrete 11/6/2024 Conditional Approval ROBERT DAVIS
Deputy Shotcrete 11/14/2024 Conditional Approval ROBERT DAVIS
Deputy Shotcrete 11/15/2024 Approved ROBERT DAVIS
Green Building Rough 11/15/2024 Not Ready for Inspection ROBERT DAVIS
Insulation 11/15/2024 Not Ready for Inspection ROBERT DAVIS
Reinforced Concrete Frame 11/15/2024 Partial Approval ROBERT DAVIS
Verify Sprinkler Sign Off 11/15/2024 Not Ready for Inspection ROBERT DAVIS
Deputy Reinf. Concrete 11/18/2024 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 11/19/2024 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 11/20/2024 Conditional Approval ROBERT DAVIS
Green Building Rough 11/22/2024 Not Ready for Inspection ROBERT DAVIS
Reinforced Concrete Frame 11/22/2024 Partial Approval ROBERT DAVIS
Verify Sprinkler Sign Off 11/22/2024 Not Ready for Inspection ROBERT DAVIS
Green Building Rough 12/4/2024 Not Ready for Inspection ROBERT DAVIS
Reinforced Concrete Frame 12/4/2024 Corrections Issued ROBERT DAVIS
Verify Sprinkler Sign Off 12/4/2024 Not Ready for Inspection ROBERT DAVIS
Special/Order Compliance 12/5/2024 Not Ready for Inspection ROBERT DAVIS
Green Building Rough 12/9/2024 Not Ready for Inspection ROBERT DAVIS
Reinforced Concrete Frame 12/9/2024 Not Ready for Inspection ROBERT DAVIS
Verify Sprinkler Sign Off 12/9/2024 Not Ready for Inspection ROBERT DAVIS
Green Building Rough 12/12/2024 Not Ready for Inspection ROBERT DAVIS
Reinforced Concrete Frame 12/12/2024 Partial Inspection ROBERT DAVIS
Verify Sprinkler Sign Off 12/12/2024 Not Ready for Inspection ROBERT DAVIS
Reinforced Concrete Frame 12/13/2024 Partial Approval ROBERT DAVIS
Deputy Reinf. Concrete 12/16/2024 Conditional Approval GREGORY POMISH
Reinforced Concrete Frame 12/26/2024 Partial Approval ROBERT DAVIS
Excavation/Setback/Form/Re-Bar 12/30/2024 Not Ready for Inspection ROBERT DAVIS
Special/Order Compliance 12/30/2024 Not Ready for Inspection ROBERT DAVIS
Green Building Rough 1/6/2025 Not Ready for Inspection ROBERT DAVIS
Reinforced Concrete Frame 1/6/2025 Partial Approval ROBERT DAVIS
Verify Sprinkler Sign Off 1/6/2025 Not Ready for Inspection ROBERT DAVIS
Deputy Shotcrete 1/7/2025 Conditional Approval ROBERT DAVIS
Order to Comply 1/7/2025 Not Required ROBERT DAVIS
Green Building Rough 1/9/2025 Not Ready for Inspection ROBERT DAVIS
Reinforced Concrete Frame 1/9/2025 Partial Approval ROBERT DAVIS
Verify Sprinkler Sign Off 1/9/2025 Not Ready for Inspection ROBERT DAVIS
Deputy Shotcrete 1/15/2025 Approved ROBERT DAVIS
Green Building Rough 1/15/2025 Not Ready for Inspection ROBERT DAVIS
Reinforced Concrete Frame 1/15/2025 Partial Approval ROBERT DAVIS
Verify Sprinkler Sign Off 1/15/2025 Not Ready for Inspection ROBERT DAVIS
Deputy Shotcrete 1/16/2025 Conditional Approval ROBERT DAVIS
Pre-Inspection 1/16/2025 Not Ready for Inspection ROBERT DAVIS
Deputy Reinf. Concrete 1/22/2025 Approved ROBERT DAVIS
Green Building Rough 1/23/2025 Not Ready for Inspection ROBERT DAVIS
Reinforced Concrete Frame 1/23/2025 Partial Approval ROBERT DAVIS
Verify Sprinkler Sign Off 1/23/2025 Not Ready for Inspection ROBERT DAVIS
Green Building Rough 3/6/2025 Not Ready for Inspection GREGORY POMISH
Reinforced Concrete Frame 3/6/2025 Not Ready for Inspection GREGORY POMISH
Verify Sprinkler Sign Off 3/6/2025 Not Ready for Inspection GREGORY POMISH
Special/Order Compliance 3/7/2025 Not Ready for Inspection GREGORY POMISH
Green Building Rough 3/13/2025 Not Ready for Inspection ROBERT DAVIS
Reinforced Concrete Frame 3/13/2025 Conditional Approval ROBERT DAVIS
Verify Sprinkler Sign Off 3/13/2025 Not Ready for Inspection ROBERT DAVIS
Special/Order Compliance 3/14/2025 Partial Approval ROBERT DAVIS
Deputy Reinf. Concrete 3/17/2025 Conditional Approval ROBERT DAVIS
Floor/Roof Diaphrgm/Shear Wall 4/7/2025 Conditional Approval ROBERT DAVIS
Floor/Roof Diaphrgm/Shear Wall 4/15/2025 Partial Approval ROBERT DAVIS
Floor/Roof Diaphrgm/Shear Wall 4/24/2025 Partial Approval GREGORY POMISH
Floor/Roof Diaphrgm/Shear Wall 4/28/2025 Not Ready for Inspection ROBERT DAVIS
Floor/Roof Diaphrgm/Shear Wall 4/30/2025 Partial Approval ROBERT DAVIS
Floor/Roof Diaphrgm/Shear Wall 5/1/2025 Corrections Issued ROBERT DAVIS
Floor/Roof Diaphrgm/Shear Wall 5/6/2025 No Access for Inspection ROBERT DAVIS
Floor/Roof Diaphrgm/Shear Wall 5/8/2025 Partial Approval ROBERT DAVIS
Wood Frame 5/8/2025 Partial Approval ROBERT DAVIS
Floor/Roof Diaphrgm/Shear Wall 5/13/2025 Partial Approval ROBERT DAVIS
Floor/Roof Diaphrgm/Shear Wall 5/16/2025 Partial Approval GREGORY POMISH
Special/Order Compliance 5/28/2025 Partial Inspection ROBERT DAVIS
Floor/Roof Diaphrgm/Shear Wall 5/30/2025 Partial Approval ROBERT DAVIS
Wood Frame 6/3/2025 Partial Approval ROBERT DAVIS
Floor/Roof Diaphrgm/Shear Wall 6/5/2025 Not Ready for Inspection ROBERT DAVIS
Floor/Roof Diaphrgm/Shear Wall 6/9/2025 Partial Approval DANIEL VARNUM
Floor/Roof Diaphrgm/Shear Wall 6/11/2025 Partial Approval ROBERT DAVIS
Wood Frame 6/18/2025 Partial Approval ROBERT DAVIS
Floor/Roof Diaphrgm/Shear Wall 6/23/2025 Corrections Issued ROBERT DAVIS
Drywall Nailing 6/24/2025 Partial Approval ROBERT DAVIS
Drywall Nailing 6/27/2025 Partial Approval ROBERT DAVIS
Wood Frame 7/2/2025 Partial Approval ROBERT DAVIS
Floor/Roof Diaphrgm/Shear Wall 7/8/2025 Partial Approval ROBERT DAVIS
Insulation 7/8/2025 Partial Approval ROBERT DAVIS
Wood Frame 7/8/2025 Partial Approval ROBERT DAVIS
Wood Frame 7/9/2025 Partial Approval ROBERT DAVIS
Drywall Nailing 7/11/2025 Partial Approval ROBERT DAVIS
Drywall Nailing 7/15/2025 Partial Approval ROBERT DAVIS
Floor/Roof Diaphrgm/Shear Wall 7/17/2025 Partial Approval ROBERT DAVIS
Insulation 7/22/2025 Not Ready for Inspection ROBERT DAVIS
Floor/Roof Diaphrgm/Shear Wall 7/24/2025 Partial Approval ROBERT DAVIS
Floor/Roof Diaphrgm/Shear Wall 7/30/2025 Partial Approval ROBERT DAVIS
Floor/Roof Diaphrgm/Shear Wall 8/5/2025 Partial Approval ROBERT DAVIS
Light Gage Steel Frame 8/5/2025 Approved ROBERT DAVIS
Floor/Roof Diaphrgm/Shear Wall 8/6/2025 Not Ready for Inspection ROBERT DAVIS
Floor/Roof Diaphrgm/Shear Wall 8/14/2025 Partial Approval ROBERT DAVIS
Insulation 8/19/2025 Partial Inspection GREGORY POMISH
Insulation 8/20/2025 Partial Inspection BRIAN KELLY
Wood Frame 8/26/2025 Partial Approval ROBERT DAVIS
Light Gage Steel Frame 9/2/2025 Partial Approval ROBERT DAVIS
Wood Frame 9/2/2025 Partial Approval ROBERT DAVIS
Light Gage Steel Frame 9/11/2025 Not Ready for Inspection ROBERT DAVIS
Wood Frame 9/17/2025 Partial Approval ROBERT DAVIS
Drywall Nailing 9/18/2025 Partial Approval ROBERT DAVIS
Wood Frame 9/19/2025 Partial Approval ROBERT DAVIS
Interior/Exterior Lathing 9/23/2025 Partial Inspection GREGORY POMISH
Drywall Nailing 9/24/2025 Partial Approval ROBERT DAVIS
Drywall Nailing 9/26/2025 Partial Approval GREGORY POMISH
Drywall Nailing 9/29/2025 Partial Approval BRIAN KELLY
Drywall Nailing 9/30/2025 Corrections Issued ROBERT DAVIS
Light Gage Steel Frame 10/3/2025 Not Ready for Inspection GREGORY POMISH
Drywall Nailing 10/7/2025 Partial Approval ROBERT DAVIS
Wood Frame 10/10/2025 Partial Approval ROBERT DAVIS
Drywall Nailing 10/16/2025 Partial Approval ROBERT DAVIS
Light Gage Steel Frame 10/22/2025 Partial Inspection BRIAN KELLY
Drywall Nailing 10/24/2025 Partial Inspection BRIAN KELLY
Light Gage Steel Frame 10/31/2025 Partial Inspection GREGORY POMISH
Insulation 11/4/2025 Partial Approval GREGORY POMISH
Interior/Exterior Lathing 11/7/2025 Partial Approval BRIAN KELLY
Drywall Nailing 11/12/2025 Partial Approval GREGORY POMISH
Special/Order Compliance 11/19/2025 Partial Inspection BRIAN KELLY
Light Gage Steel Frame 11/26/2025 Not Ready for Inspection GREGORY POMISH
Light Gage Steel Frame 12/1/2025 Partial Approval BRIAN KELLY
Drywall Nailing 12/2/2025 Partial Approval ROBERT DAVIS
Drywall Nailing 12/5/2025 Partial Approval ROBERT DAVIS
Drywall Nailing 12/17/2025 Partial Approval BRIAN KELLY
Excavation/Setback/Form/Re-Bar 12/19/2025 Partial Inspection GREGORY POMISH
Special/Order Compliance 1/5/2026 Partial Inspection ROBERT DAVIS
Light Gage Steel Frame 1/21/2026 Partial Inspection ROBERT DAVIS
Drywall Nailing 1/27/2026 Not Ready for Inspection ROBERT DAVIS
Drywall Nailing 1/29/2026 Partial Approval ROBERT DAVIS
Footing/Foundation/Slab 2/3/2026 Partial Approval ROBERT DAVIS
Interior/Exterior Lathing 2/10/2026 Partial Approval ROBERT DAVIS
Wood Frame 3/2/2026 Partial Inspection GREGORY POMISH
Masonry Wall/Backfill 3/6/2026 Partial Inspection GREGORY POMISH
Excavation/Setback/Form/Re-Bar 3/18/2026 Partial Approval ROBERT DAVIS
Drywall Nailing 4/7/2026 Partial Approval ROBERT DAVIS
Special/Order Compliance 4/16/2026 Not Ready for Inspection GREGORY POMISH
Special/Order Compliance 4/20/2026 Partial Inspection ROBERT DAVIS
Excavation/Setback/Form/Re-Bar 4/29/2026 Not Ready for Inspection ROBERT DAVIS
Excavation/Setback/Form/Re-Bar 5/1/2026 Partial Approval ROBERT DAVIS
Special/Order Compliance 6/3/2026 Partial Inspection ROBERT DAVIS
Special/Order Compliance 6/23/2026 Not Ready for Inspection ROBERT DAVIS
Special/Order Compliance 6/24/2026 Corrections Issued ROBERT DAVIS
Final 6/25/2026 Not Ready for Inspection ROBERT DAVIS
Footing/Foundation/Slab 6/25/2026 Approved ROBERT DAVIS
Green Building Final 6/25/2026 Partial Approval ROBERT DAVIS
Green Building Rough 6/25/2026 Approved ROBERT DAVIS
Reinforced Concrete Frame 6/25/2026 Approved ROBERT DAVIS
Reinforced Masonry Frame 6/25/2026 Approved ROBERT DAVIS
SGSOV-Seismic Gas S/O Valve 6/25/2026 SGSOV No Gas ROBERT DAVIS
Smoke Detectors 6/25/2026 Not Ready for Inspection ROBERT DAVIS
Verify Sprinkler Sign Off 6/25/2026 Approved ROBERT DAVIS
Special/Order Compliance 6/26/2026 Partial Inspection ROBERT DAVIS
Special/Order Compliance 7/6/2026 Partial Inspection ROBERT DAVIS
Special/Order Compliance 7/14/2026 Partial Inspection ROBERT DAVIS
Special/Order Compliance 7/15/2026 Corrections Issued ROBERT DAVIS