17016-17018 W COTTER PL 91436
Certificate Information: 17016-17018 W COTTER PL 91436
- Application / Permit
- 22010-10000-04685
- Plan Check / Job No.
- B22LA18902
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePlan - NEW 2 STORY SFD WITH ADU (1000SF) AND GARAGE OVER 1 STORY BASEMENT PER 12.22 A33 C & E
- Permit Issued
- Issued on 12/17/2024
- Issuing Office
- Current Status
- Issued on 12/17/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 9/20/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 9/22/2022 | STARR CHEN |
| Corrections Issued | 9/25/2022 | STARR CHEN |
| Quality Review Completed | 9/28/2022 | EUGENE BARBEAU |
| Applicant returned to address corrections | 5/4/2023 | STARR CHEN |
| Applicant returned to address corrections | 5/5/2023 | STARR CHEN |
| Applicant returned to address corrections | 7/24/2023 | STARR CHEN |
| Applicant returned to address corrections | 8/11/2023 | STARR CHEN |
| Applicant returned to address corrections | 8/24/2023 | STARR CHEN |
| Applicant returned to address corrections | 7/17/2024 | STARR CHEN |
| Applicant returned to address corrections | 9/25/2024 | STARR CHEN |
| Plan Check Approved | 12/12/2024 | STARR CHEN |
| Plan Check Approved | 12/16/2024 | STARR CHEN |
| Issued | 12/17/2024 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 11/15/2022 | CARLOS AGUILERA |
| BHO/Hillside ordinance | Cleared | 11/15/2022 | CARLOS AGUILERA |
| BHO/Hillside ordinance | Cleared | 11/15/2022 | CARLOS AGUILERA |
| BHO/Hillside ordinance | Cleared | 11/15/2022 | CARLOS AGUILERA |
| BHO/Hillside ordinance | Cleared | 11/15/2022 | CARLOS AGUILERA |
| BHO/Hillside ordinance | Cleared | 11/15/2022 | CARLOS AGUILERA |
| Street Frontage | Cleared | 11/15/2022 | CARLOS AGUILERA |
| Hydrant and Access approval | Cleared | 11/28/2022 | LAVEON RIDER |
| Eng Process Fee Ord 176,300 | Cleared | 12/6/2022 | CARLOS AGUILERA |
| Sewer availability | Cleared | 12/6/2022 | CARLOS AGUILERA |
| Trees in Parkway | Cleared | 1/5/2023 | ADALBERTO VERA |
| Permit | Cleared | 1/20/2023 | CARLOS AGUILERA |
| Roof/Waste drainage to street | Cleared | 1/20/2023 | CARLOS AGUILERA |
| Building over 36-ft | Cleared | 12/21/2023 | CALOSHA APPROVED |
| Low Impact Development | Cleared | 6/29/2024 | LUIS LUVANO |
| GPI Written Notices | Cleared | 12/12/2024 | STARR CHEN |
| Grading Pre-Inspection | Cleared | 12/12/2024 | STARR CHEN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Danz,, Joshua; Lic. No.: C84764 | 1164 ELDERBERRY CIRCLE FOLSOM, CA 95630 |
| Engineer | De, Leon, Cynthia Aguilar; Lic. No.: C31604 | 347 ROBERTSON BLVD BEVERLY HILLS, CA 90211 |
| Engineer | Yuzon,, Benigno Sari; Lic. No.: S3454 | 2511 PEACHWOOD PLACE WESTLAKE VILLAGE, CA 91361 |
| Geologist | Feffer,, Joshua R; Lic. No.: EG2138 | 12253 GORHAM AVE LOS ANGELES, CA 90049 |
Inspector Information
| THOMAS FINNILA, (818) 774-4324 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Other (see comments) | 3/26/2025 | Approved | THOMAS FINNILA |
| Piling/Pier/Caisson | 3/26/2025 | Partial Approval | THOMAS FINNILA |
| Deputy Reinf. Concrete | 3/27/2025 | Conditional Approval | THOMAS FINNILA |
| Underground Mechanical | 4/23/2025 | Partial Approval | THOMAS FINNILA |
| Sewer | 4/28/2025 | Approved | JOHN KIDWELL |
| Deputy Reinf. Concrete | 5/20/2025 | Approved | JOHN COLEMAN |
| Excavation/Setback/Form/Re-Bar | 5/20/2025 | Not Ready for Inspection | JOHN COLEMAN |
| Excavation/Setback/Form/Re-Bar | 5/21/2025 | Partial Approval | JOHN HAYES |
| Deputy Reinf. Concrete | 5/22/2025 | Conditional Approval | THOMAS FINNILA |
| Excavation/Setback/Form/Re-Bar | 5/22/2025 | Approved | JOHN COLEMAN |
| Deputy Reinf. Concrete | 6/2/2025 | Corrections Issued | THOMAS FINNILA |
| Excavation/Setback/Form/Re-Bar | 6/2/2025 | Not Ready for Inspection | THOMAS FINNILA |
| Excavation/Setback/Form/Re-Bar | 6/3/2025 | Corrections Issued | THOMAS FINNILA |
| Deputy Reinf. Concrete | 6/11/2025 | Conditional Approval | THOMAS FINNILA |
| Footing/Foundation/Slab | 6/11/2025 | Corrections Issued | THOMAS FINNILA |
| Deputy Reinf. Concrete | 6/12/2025 | Conditional Approval | THOMAS FINNILA |
| Excavation/Setback/Form/Re-Bar | 6/23/2025 | Partial Approval | THOMAS FINNILA |
| Deputy Reinf. Concrete | 6/30/2025 | Conditional Approval | THOMAS FINNILA |
| Deputy Reinf. Concrete | 7/3/2025 | Conditional Approval | MORRIS JACKSON |
| Excavation/Setback/Form/Re-Bar | 7/3/2025 | Partial Approval | JON MCHUGH |
| Floor/Roof Diaphrgm/Shear Wall | 7/31/2025 | Corrections Issued | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 8/5/2025 | Partial Approval | JON MCHUGH |
| Footing/Foundation/Slab | 8/7/2025 | Not Ready for Inspection | THOMAS FINNILA |
| Deputy Other (see comments) | 8/13/2025 | Conditional Approval | HENRY KIM |
| Excavation/Setback/Form/Re-Bar | 8/15/2025 | Corrections Issued | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 8/25/2025 | Corrections Issued | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 8/27/2025 | Partial Approval | DAVID SCANTLIN |
| Floor/Roof Diaphrgm/Shear Wall | 10/28/2025 | Corrections Issued | THOMAS FINNILA |
| PLUMBING-Rough | 11/25/2025 | Approved | THOMAS FINNILA |
| HVAC-Rough | 12/1/2025 | Approved | THOMAS FINNILA |
| Deputy Wood Construction | 1/7/2026 | Conditional Approval | THOMAS FINNILA |
| ELECTRICAL-Rough | 1/8/2026 | Corrections Issued | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 1/9/2026 | Corrections Issued | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 1/13/2026 | Partial Approval | THOMAS FINNILA |
| ELECTRICAL-Rough | 1/27/2026 | Corrections Issued | THOMAS FINNILA |
| ELECTRICAL-Rough | 2/11/2026 | Approved | THOMAS FINNILA |
| Interior/Exterior Lathing | 2/13/2026 | Partial Approval | MORRIS JACKSON |
| Deputy Wood Construction | 2/17/2026 | Partial Approval | SEAN WIRCH |
| BUILDING-Rough-Frame | 2/18/2026 | Corrections Issued | THOMAS FINNILA |
| BUILDING-Rough-Frame | 2/24/2026 | Approved | THOMAS FINNILA |
| Verify Sprinkler Sign Off | 2/24/2026 | Approved | THOMAS FINNILA |
| Insulation | 3/10/2026 | Approved | JOHN KIDWELL |
| Shower Pan | 3/16/2026 | Approved | JEFFREY PARD |
| Interior/Exterior Lathing | 4/6/2026 | Partial Approval | JOHN KIDWELL |
| Drywall Nailing | 4/16/2026 | Approved | JOHN KIDWELL |
| Green Building Rough | 4/16/2026 | Approved | JOHN KIDWELL |
| Underground Mechanical | 5/1/2026 | Partial Approval | THOMAS FINNILA |