715 N ALVARADO ST 90026

Certificate Information: 715 N ALVARADO ST 90026

Application / Permit
22010-10000-04676
Plan Check / Job No.
B22LA18856
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
NEW 6 STORY 81 UNITS (INCLUDING 80 LOW INCOME UNIT AND 1 MANAGER UNIT), 100% AFFORDABLE HOUSING APARTMENT TO INCLUDE 5 STORY TYPE IIIA APARTMENT OVER 1 STORY TYPE IA PARKING/LOBBY, PER DIR-2019-5086-TOC-SPR.
Permit Issued
Issued on 12/21/2022
Issuing Office
Metro
Current Status
Issued on 12/21/2022
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 9/20/2022 APPLICANT
Assigned to Plan Check Engineer 9/22/2022 VU NGUYEN
Corrections Issued 9/26/2022 VU NGUYEN
Quality Review Completed 9/27/2022 ALLEN MANALANSAN
Applicant returned to address corrections 11/4/2022 VU NGUYEN
Applicant returned to address corrections 11/29/2022 VU NGUYEN
Plan Check Approved 12/21/2022 VU NGUYEN
Issued 12/21/2022 APPLICANT
TCO Issued (Expire Date: 08-26-2026) 2/27/2026 ADAM BURGESS

Permit Application Clearance Information

Address approval Cleared 10/14/2022 AMAAN MALIK
Eng Process Fee Ord 176,300 Cleared 10/17/2022 JEANIE LAM
Highway dedication Cleared 11/1/2022 WALLIE JONG
Miscellaneous Cleared 11/2/2022 RUBEN VASQUEZ
ZA Case Cleared 11/2/2022 RUBEN VASQUEZ
Hydrant and Access approval Cleared 11/8/2022 KURT CORRAL
Green Code Cleared 11/18/2022 MICHAEL MARTINEZ
GPI Written Notices Cleared 11/30/2022 VU NGUYEN
Grading Pre-Inspection Cleared 11/30/2022 VU NGUYEN
DCP conditions approval Cleared 12/6/2022 JAMES MCCARTHY
Permit Cleared 12/6/2022 TREVOR QUAN
Fire Marshal Fire Life Safety Cleared 12/8/2022 SEAN DANG
Public Housing Cleared 12/12/2022 SUNYOUNG KIM
Sewer availability Cleared 12/12/2022 CINDY QI
DAS Clearance Cleared 12/14/2022 Rodolfo Arias
Frnt yard landscape/Water mgmt Cleared 12/15/2022 RUBEN VASQUEZ
Miscellaneous Cleared 12/15/2022 RUBEN VASQUEZ
Miscellaneous Cleared 12/15/2022 RUBEN VASQUEZ
Opn space landscape/Water mgmt Cleared 12/15/2022 RUBEN VASQUEZ
Site Plan review Cleared 12/15/2022 RUBEN VASQUEZ
Building over 36-ft Cleared 12/19/2022 CALOSHA APPROVED
Low Impact Development Cleared 12/20/2022 ORVAL HERNANDEZ-MARCI
Roof/Waste drainage to street Cleared 12/20/2022 CINDY QI

Contact Information

Architect Egan,, John S; Lic. No.: C28572 EGAN SIMON ARCHITECTURE   7740 W. MANCHESTER AVE. STE. 205    PLAYA DEL REY, CA 90293
Contractor Westport Construction Inc; Lic. No.: 712732-B 125 W MAPLE AVE      MONROVIA, CA 91016
Engineer Derkalousdian,, Hrair Harry; Lic. No.: C79694 3622 VIRGINIA STREET      GLENDALE, CA 91214
Engineer Labib,, Youhanna T.; Lic. No.: S4549 319 MAIN STREET      EL SEGUNDO, CA 90245

Inspector Information

DAVID BURKHEAD, (213) 482-7294 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 4/4/2023 Not Ready for Inspection DAVID BURKHEAD
Pre-Inspection 4/19/2023 Partial Approval DAVID BURKHEAD
Deputy Reinf. Concrete 6/14/2023 Conditional Approval MICHAEL ROSENBERG
Excavation/Setback/Form/Re-Bar 6/16/2023 Not Ready for Inspection DAVID BURKHEAD
Deputy Reinf. Concrete 6/21/2023 Conditional Approval GREGORY POMISH
Excavation/Setback/Form/Re-Bar 6/21/2023 Off-Hour Fees Due
Excavation/Setback/Form/Re-Bar 6/21/2023 Partial Approval GREGORY POMISH
Footing/Foundation/Slab 6/21/2023 Partial Approval GREGORY POMISH
Excavation/Setback/Form/Re-Bar 6/26/2023 Partial Approval DAVID BURKHEAD
Excavation/Setback/Form/Re-Bar 6/27/2023 Partial Approval DAVID BURKHEAD
Footing/Foundation/Slab 6/27/2023 Partial Approval DAVID BURKHEAD
Deputy Reinf. Concrete 7/6/2023 Approved DAVID BURKHEAD
Excavation/Setback/Form/Re-Bar 7/6/2023 Partial Approval DAVID BURKHEAD
Excavation/Setback/Form/Re-Bar 7/13/2023 Partial Approval DAVID BURKHEAD
Deputy Reinf. Concrete 7/26/2023 Conditional Approval DAVID BURKHEAD
Deputy Reinf. Concrete 7/28/2023 Conditional Approval DAVID BURKHEAD
Excavation/Setback/Form/Re-Bar 7/28/2023 Partial Approval DAVID BURKHEAD
Deputy Reinf. Concrete 8/3/2023 Conditional Approval DAVID BURKHEAD
Deputy Shotcrete 8/3/2023 Conditional Approval DAVID BURKHEAD
Deputy Reinf. Concrete 8/4/2023 Approved DAVID BURKHEAD
Deputy Shotcrete 8/4/2023 Approved DAVID BURKHEAD
Excavation/Setback/Form/Re-Bar 8/4/2023 Partial Approval DAVID BURKHEAD
Deputy Reinf. Concrete 8/7/2023 Conditional Approval DAVID BURKHEAD
Deputy Shotcrete 8/7/2023 Conditional Approval DAVID BURKHEAD
Deputy Reinf. Concrete 8/8/2023 Conditional Approval DAVID BURKHEAD
Deputy Shotcrete 8/8/2023 Conditional Approval DAVID BURKHEAD
Deputy Reinf. Concrete 8/9/2023 Approved DAVID BURKHEAD
Deputy Shotcrete 8/9/2023 Conditional Approval DAVID BURKHEAD
Excavation/Setback/Form/Re-Bar 8/9/2023 Partial Approval DAVID BURKHEAD
Deputy Reinf. Concrete 8/10/2023 Conditional Approval DAVID BURKHEAD
Deputy Shotcrete 8/10/2023 Conditional Approval DAVID BURKHEAD
Deputy Reinf. Concrete 8/11/2023 Conditional Approval DAVID BURKHEAD
Deputy Shotcrete 8/11/2023 Conditional Approval DAVID BURKHEAD
Deputy Drilled-In Anchors 8/15/2023 Conditional Approval DAVID BURKHEAD
Deputy Reinf. Masonry 8/15/2023 Conditional Approval DAVID BURKHEAD
Deputy Reinf. Masonry 8/16/2023 Conditional Approval DAVID BURKHEAD
Deputy Reinf. Masonry 8/17/2023 Conditional Approval RAFAEL ESPINOZA
Masonry Wall/Backfill 8/17/2023 Partial Approval RAFAEL ESPINOZA
Deputy Drilled-In Anchors 8/23/2023 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 8/23/2023 Conditional Approval NICK DANERI
Deputy Reinf. Masonry 8/23/2023 Conditional Approval NICK DANERI
Excavation/Setback/Form/Re-Bar 8/23/2023 Partial Approval NICK DANERI
Deputy Drilled-In Anchors 8/24/2023 Conditional Approval DAVID BURKHEAD
Deputy Reinf. Concrete 8/24/2023 Conditional Approval DAVID BURKHEAD
Deputy Reinf. Masonry 8/24/2023 Conditional Approval DAVID BURKHEAD
Deputy Drilled-In Anchors 8/25/2023 Conditional Approval DAVID BURKHEAD
Deputy Reinf. Concrete 8/25/2023 Conditional Approval DAVID BURKHEAD
Deputy Reinf. Masonry 8/25/2023 Conditional Approval DAVID BURKHEAD
Deputy Reinf. Concrete 9/11/2023 Conditional Approval RAFAEL ESPINOZA
Footing/Foundation/Slab 9/11/2023 Partial Approval RAFAEL ESPINOZA
Excavation/Setback/Form/Re-Bar 9/14/2023 Partial Approval DAVID BURKHEAD
Deputy Drilled-In Anchors 9/27/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Drilled-In Anchors 9/28/2023 Conditional Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 9/29/2023 Conditional Approval DAVID BURKHEAD
Excavation/Setback/Form/Re-Bar 9/29/2023 Partial Approval DAVID BURKHEAD
Deputy Reinf. Concrete 10/18/2023 Conditional Approval DAVID BURKHEAD
Deputy Reinf. Concrete 10/19/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Concrete 10/23/2023 Conditional Approval MICHAEL ROSENBERG
Light Gage Steel Frame 10/30/2023 Partial Approval LARRY ARNICK
Excavation/Setback/Form/Re-Bar 11/9/2023 Partial Approval DAVID BURKHEAD
Structural Steel Frame 11/20/2023 Partial Approval NICK DANERI
Floor/Roof Diaphrgm/Shear Wall 12/1/2023 Partial Approval GREGORY POMISH
Wood Frame 12/1/2023 Partial Approval GREGORY POMISH
Deputy Wood Construction 12/4/2023 Conditional Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 12/4/2023 Partial Approval RAFAEL ESPINOZA
Wood Frame 12/4/2023 Partial Inspection RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 12/12/2023 Partial Approval DAVID BURKHEAD
Deputy Wood Construction 12/15/2023 Conditional Approval LARRY ARNICK
Floor/Roof Diaphrgm/Shear Wall 12/15/2023 Not Ready for Inspection LARRY ARNICK
Wood Frame 12/15/2023 Not Ready for Inspection LARRY ARNICK
Drywall Nailing 12/19/2023 Conditional Approval LARRY ARNICK
Floor/Roof Diaphrgm/Shear Wall 12/20/2023 Partial Inspection DAVID BURKHEAD
Deputy Wood Construction 1/2/2024 Conditional Approval GREGORY POMISH
Floor/Roof Diaphrgm/Shear Wall 1/2/2024 Partial Approval GREGORY POMISH
Deputy Wood Construction 1/4/2024 Conditional Approval DAVID BURKHEAD
Drywall Nailing 1/4/2024 Partial Inspection DAVID BURKHEAD
Floor/Roof Diaphrgm/Shear Wall 1/4/2024 Partial Approval DAVID BURKHEAD
Drywall Nailing 1/16/2024 Not Ready for Inspection GREGORY POMISH
Floor/Roof Diaphrgm/Shear Wall 1/16/2024 Partial Approval GREGORY POMISH
Deputy Wood Construction 1/17/2024 Conditional Approval GREGORY POMISH
Floor/Roof Diaphrgm/Shear Wall 1/17/2024 Partial Approval GREGORY POMISH
Floor/Roof Diaphrgm/Shear Wall 2/2/2024 Partial Approval DAVID BURKHEAD
Floor/Roof Diaphrgm/Shear Wall 2/8/2024 Not Ready for Inspection LARRY ARNICK
Deputy Steel/Welding 2/13/2024 Conditional Approval DAVID BURKHEAD
Floor/Roof Diaphrgm/Shear Wall 2/13/2024 Partial Approval RAFAEL ESPINOZA
Drywall Nailing 2/16/2024 Partial Approval GREGORY POMISH
Floor/Roof Diaphrgm/Shear Wall 2/16/2024 Partial Approval GREGORY POMISH
Floor/Roof Diaphrgm/Shear Wall 2/21/2024 Partial Inspection DAVID BURKHEAD
Deputy Wood Construction 2/26/2024 Conditional Approval JEFFREY FULTON
Floor/Roof Diaphrgm/Shear Wall 2/26/2024 Partial Inspection JEFFREY FULTON
Structural Steel Frame 2/26/2024 Partial Inspection JEFFREY FULTON
Insulation 2/28/2024 Partial Inspection JEFFREY FULTON
Wood Frame 2/28/2024 Partial Inspection JEFFREY FULTON
Drywall Nailing 3/1/2024 Partial Inspection JEFFREY FULTON
Drywall Nailing 3/7/2024 Partial Inspection JEFFREY FULTON
Floor/Roof Diaphrgm/Shear Wall 3/7/2024 Partial Inspection JEFFREY FULTON
Deputy Wood Construction 3/11/2024 Conditional Approval JEFFREY FULTON
Floor/Roof Diaphrgm/Shear Wall 3/11/2024 Partial Inspection JEFFREY FULTON
Insulation 3/14/2024 Partial Inspection JEFFREY FULTON
Floor/Roof Diaphrgm/Shear Wall 3/18/2024 Partial Inspection JEFFREY FULTON
Wood Frame 3/19/2024 Partial Inspection JEFFREY FULTON
Light Gage Steel Frame 3/21/2024 Partial Inspection JEFFREY FULTON
Special/Order Compliance 3/21/2024 Partial Inspection JEFFREY FULTON
Wood Frame 3/21/2024 Partial Inspection JEFFREY FULTON
Insulation 3/26/2024 Partial Inspection JEFFREY FULTON
Wood Frame 3/26/2024 Partial Inspection JEFFREY FULTON
Insulation 3/28/2024 Partial Inspection JEFFREY FULTON
Wood Frame 3/28/2024 Partial Inspection JEFFREY FULTON
Deputy Drilled-In Anchors 4/2/2024 Conditional Approval JEFFREY FULTON
Insulation 4/2/2024 Partial Inspection JEFFREY FULTON
Wood Frame 4/2/2024 Partial Inspection JEFFREY FULTON
Deputy Reinf. Masonry 4/3/2024 Conditional Approval JEFFREY FULTON
Wood Frame 4/3/2024 Partial Inspection JEFFREY FULTON
Deputy Reinf. Masonry 4/8/2024 Conditional Approval JEFFREY FULTON
Masonry Wall/Backfill 4/8/2024 Partial Inspection JEFFREY FULTON
Deputy Reinf. Masonry 4/9/2024 Conditional Approval JEFFREY FULTON
Floor/Roof Diaphrgm/Shear Wall 4/9/2024 Not Ready for Inspection JEFFREY FULTON
Insulation 4/9/2024 Not Ready for Inspection JEFFREY FULTON
Wood Frame 4/10/2024 Partial Inspection JEFFREY FULTON
Insulation 4/11/2024 Partial Inspection JEFFREY FULTON
Floor/Roof Diaphrgm/Shear Wall 4/15/2024 Partial Inspection JEFFREY FULTON
Deputy Drilled-In Anchors 4/18/2024 Conditional Approval JEFFREY FULTON
Drywall Nailing 4/18/2024 Partial Inspection JEFFREY FULTON
Excavation/Setback/Form/Re-Bar 4/18/2024 Partial Inspection JEFFREY FULTON
Insulation 4/18/2024 Partial Inspection JEFFREY FULTON
Drywall Nailing 4/23/2024 Conditional Approval LARRY ARNICK
Floor/Roof Diaphrgm/Shear Wall 4/23/2024 Partial Approval LARRY ARNICK
Deputy Wood Construction 4/25/2024 Conditional Approval DAVID BURKHEAD
Drywall Nailing 4/25/2024 Not Ready for Inspection DAVID BURKHEAD
Floor/Roof Diaphrgm/Shear Wall 4/25/2024 Not Ready for Inspection DAVID BURKHEAD
Drywall Nailing 4/29/2024 Partial Inspection JEFFREY FULTON
Floor/Roof Diaphrgm/Shear Wall 4/29/2024 Partial Inspection JEFFREY FULTON
Drywall Nailing 5/1/2024 Not Ready for Inspection JEFFREY FULTON
Insulation 5/6/2024 Partial Approval JEROME BLACKWOOD
Excavation/Setback/Form/Re-Bar 5/7/2024 Partial Approval NICK DANERI
Insulation 5/8/2024 Partial Approval TIMOTHY POWELL
Drywall Nailing 5/9/2024 Partial Inspection JEFFREY FULTON
Insulation 5/9/2024 Not Ready for Inspection JEFFREY FULTON
Light Gage Steel Frame 5/9/2024 Not Ready for Inspection JEFFREY FULTON
Wood Frame 5/9/2024 Not Ready for Inspection JEFFREY FULTON
Drywall Nailing 5/10/2024 Partial Approval RONALD JIMENEZ
Insulation 5/10/2024 Partial Approval RONALD JIMENEZ
Light Gage Steel Frame 5/10/2024 Partial Approval RONALD JIMENEZ
Drywall Nailing 5/14/2024 Partial Inspection JEFFREY FULTON
Light Gage Steel Frame 5/14/2024 Partial Inspection JEFFREY FULTON
Pre-Inspection 5/14/2024 Not Ready for Inspection JEFFREY FULTON
Drywall Nailing 5/15/2024 Partial Inspection JEFFREY FULTON
Light Gage Steel Frame 5/15/2024 Partial Inspection JEFFREY FULTON
Drywall Nailing 5/16/2024 Not Ready for Inspection JEFFREY FULTON
Insulation 5/16/2024 Partial Inspection JEFFREY FULTON
Drywall Nailing 5/17/2024 Partial Inspection JEFFREY FULTON
Light Gage Steel Frame 5/21/2024 Partial Inspection JEFFREY FULTON
Wood Frame 5/21/2024 Partial Inspection JEFFREY FULTON
Interior/Exterior Lathing 5/24/2024 Partial Inspection JEFFREY FULTON
Drywall Nailing 5/30/2024 Partial Inspection JEFFREY FULTON
Insulation 5/30/2024 Partial Inspection JEFFREY FULTON
Special/Order Compliance 6/3/2024 Partial Inspection JEFFREY FULTON
Interior/Exterior Lathing 6/7/2024 Partial Inspection JEFFREY FULTON
Light Gage Steel Frame 6/7/2024 Not Ready for Inspection JEFFREY FULTON
Wood Frame 6/7/2024 Partial Inspection JEFFREY FULTON
Insulation 6/11/2024 Partial Inspection JEFFREY FULTON
Light Gage Steel Frame 6/11/2024 Partial Inspection JEFFREY FULTON
Wood Frame 6/11/2024 Partial Inspection JEFFREY FULTON
Wood Frame 6/12/2024 Partial Inspection JEFFREY FULTON
Insulation 6/13/2024 Partial Inspection JEFFREY FULTON
Light Gage Steel Frame 6/13/2024 Partial Inspection JEFFREY FULTON
Insulation 6/14/2024 Partial Inspection JEFFREY FULTON
Drywall Nailing 6/24/2024 Partial Inspection JEFFREY FULTON
Insulation 6/24/2024 Partial Inspection JEFFREY FULTON
Drywall Nailing 6/26/2024 Partial Inspection JEFFREY FULTON
Insulation 6/26/2024 Partial Inspection JEFFREY FULTON
Light Gage Steel Frame 6/27/2024 Not Ready for Inspection RAMAZANALI ALMASI
Wood Frame 6/27/2024 Partial Approval RAMAZANALI ALMASI
Wood Frame 6/28/2024 Partial Inspection JEFFREY FULTON
Insulation 7/1/2024 Partial Inspection JEFFREY FULTON
Wood Frame 7/1/2024 Not Ready for Inspection JEFFREY FULTON
Light Gage Steel Frame 7/3/2024 Partial Inspection JEFFREY FULTON
Drywall Nailing 7/9/2024 Partial Inspection JEFFREY FULTON
Insulation 7/11/2024 Partial Inspection JEFFREY FULTON
Wood Frame 7/11/2024 Partial Inspection JEFFREY FULTON
Insulation 7/12/2024 Not Ready for Inspection JEFFREY FULTON
Wood Frame 7/12/2024 Partial Inspection JEFFREY FULTON
Drywall Nailing 7/16/2024 Partial Inspection JEFFREY FULTON
Drywall Nailing 7/17/2024 Partial Inspection JEFFREY FULTON
Insulation 7/17/2024 Partial Inspection JEFFREY FULTON
Special/Order Compliance 7/19/2024 Partial Inspection DAVID BURKHEAD
Light Gage Steel Frame 7/23/2024 Partial Approval LARRY ARNICK
Drywall Nailing 7/24/2024 Partial Inspection JEFFREY FULTON
Special/Order Compliance 7/26/2024 Partial Inspection JEFFREY FULTON
Insulation 7/30/2024 Partial Approval RAMAZANALI ALMASI
Drywall Nailing 8/2/2024 Partial Inspection JEFFREY FULTON
Light Gage Steel Frame 8/2/2024 Partial Inspection JEFFREY FULTON
Special/Order Compliance 8/2/2024 Corrections Issued JEFFREY FULTON
Light Gage Steel Frame 8/5/2024 Partial Inspection JEFFREY FULTON
Drywall Nailing 8/7/2024 Partial Inspection JEFFREY FULTON
Drywall Nailing 8/12/2024 Partial Inspection JEFFREY FULTON
Light Gage Steel Frame 8/12/2024 Partial Inspection JEFFREY FULTON
Drywall Nailing 8/13/2024 Partial Inspection JEFFREY FULTON
Excavation/Setback/Form/Re-Bar 8/13/2024 Partial Inspection JEFFREY FULTON
Light Gage Steel Frame 8/13/2024 Partial Inspection JEFFREY FULTON
Deputy Reinf. Concrete 8/16/2024 Conditional Approval JEFFREY FULTON
Excavation/Setback/Form/Re-Bar 8/16/2024 Partial Inspection JEFFREY FULTON
Drywall Nailing 8/20/2024 Partial Approval LARRY ARNICK
Special/Order Compliance 8/23/2024 Not Ready for Inspection JEFFREY FULTON
Wood Frame 9/25/2024 Partial Inspection JEFFREY FULTON
Insulation 9/27/2024 Partial Inspection JEFFREY FULTON
Deputy Drilled-In Anchors 9/30/2024 Conditional Approval LARRY ARNICK
Deputy Reinf. Concrete 9/30/2024 Conditional Approval DAVID BURKHEAD
Deputy Reinf. Concrete 9/30/2024 Conditional Approval LARRY ARNICK
Excavation/Setback/Form/Re-Bar 9/30/2024 Not Ready for Inspection LARRY ARNICK
Excavation/Setback/Form/Re-Bar 10/1/2024 Partial Inspection JEFFREY FULTON
Deputy Reinf. Concrete 10/2/2024 Conditional Approval DAVID BURKHEAD
Excavation/Setback/Form/Re-Bar 10/2/2024 Not Ready for Inspection JEFFREY FULTON
Light Gage Steel Frame 10/2/2024 Not Ready for Inspection JEFFREY FULTON
Light Gage Steel Frame 10/3/2024 Not Ready for Inspection JEROME BLACKWOOD
Light Gage Steel Frame 10/4/2024 Not Ready for Inspection LUIS CCAMACHO
Deputy Reinf. Concrete 10/8/2024 Conditional Approval LARRY ARNICK
Deputy Reinf. Masonry 10/8/2024 Conditional Approval LARRY ARNICK
Excavation/Setback/Form/Re-Bar 10/8/2024 Not Ready for Inspection LARRY ARNICK
Light Gage Steel Frame 10/9/2024 Partial Approval LARRY ARNICK
Deputy Reinf. Concrete 10/10/2024 Partial Approval LUIS CCAMACHO
Deputy Reinf. Masonry 10/10/2024 Partial Approval LUIS CCAMACHO
Excavation/Setback/Form/Re-Bar 10/10/2024 Partial Approval LUIS CCAMACHO
Deputy Pre-Stress Concrete 10/15/2024 Conditional Approval JEFFREY FULTON
Deputy Reinf. Concrete 10/15/2024 Conditional Approval JEFFREY FULTON
Excavation/Setback/Form/Re-Bar 10/15/2024 Partial Inspection JEFFREY FULTON
Masonry Wall/Backfill 10/15/2024 Partial Inspection JEFFREY FULTON
Drywall Nailing 10/21/2024 Partial Inspection JEFFREY FULTON
Floor/Roof Diaphrgm/Shear Wall 10/23/2024 Partial Inspection JEFFREY FULTON
Deputy Reinf. Concrete 10/25/2024 Conditional Approval JEFFREY FULTON
Drywall Nailing 10/25/2024 Partial Inspection JEFFREY FULTON
Excavation/Setback/Form/Re-Bar 10/25/2024 Partial Inspection JEFFREY FULTON
Light Gage Steel Frame 10/29/2024 Partial Inspection JEFFREY FULTON
Drywall Nailing 11/4/2024 Partial Inspection JEFFREY FULTON
Excavation/Setback/Form/Re-Bar 11/4/2024 Partial Inspection JEFFREY FULTON
Pre-Inspection 11/4/2024 Not Ready for Inspection JEFFREY FULTON
Wood Frame 11/4/2024 Partial Inspection JEFFREY FULTON
Insulation 11/6/2024 Partial Inspection JEFFREY FULTON
Insulation 11/7/2024 Not Ready for Inspection JEFFREY FULTON
Drywall Nailing 11/8/2024 Partial Inspection JEFFREY FULTON
Light Gage Steel Frame 11/12/2024 Partial Inspection JEFFREY FULTON
Wood Frame 11/12/2024 Partial Inspection JEFFREY FULTON
Insulation 11/14/2024 Not Ready for Inspection JEFFREY FULTON
Drywall Nailing 11/18/2024 Partial Inspection JEFFREY FULTON
Excavation/Setback/Form/Re-Bar 11/19/2024 Partial Inspection JEFFREY FULTON
Footing/Foundation/Slab 12/4/2024 Not Ready for Inspection JEFFREY FULTON
Footing/Foundation/Slab 12/5/2024 Partial Inspection JEFFREY FULTON
Footing/Foundation/Slab 12/11/2024 Partial Inspection JEFFREY FULTON
Deputy Reinf. Concrete 12/20/2024 Approved LUIS CCAMACHO
Footing/Foundation/Slab 12/20/2024 Partial Approval LUIS CCAMACHO
Excavation/Setback/Form/Re-Bar 12/30/2024 Partial Inspection JEFFREY FULTON
Excavation/Setback/Form/Re-Bar 1/23/2025 Partial Inspection JEFFREY FULTON
Footing/Foundation/Slab 2/3/2025 Not Ready for Inspection JEFFREY FULTON
Excavation/Setback/Form/Re-Bar 2/4/2025 Partial Inspection JEFFREY FULTON
Special/Order Compliance 2/19/2025 Partial Approval TIMOTHY POWELL
Excavation/Setback/Form/Re-Bar 4/28/2025 Not Ready for Inspection NICK DANERI
Green Building Rough 4/28/2025 Not Ready for Inspection NICK DANERI
Reinforced Concrete Frame 4/28/2025 Not Ready for Inspection NICK DANERI
Verify Sprinkler Sign Off 4/28/2025 Not Ready for Inspection NICK DANERI
Excavation/Setback/Form/Re-Bar 4/29/2025 Partial Approval DAVID BURKHEAD
Special/Order Compliance 4/29/2025 Not Ready for Inspection DAVID BURKHEAD
Final 5/20/2025 Partial Inspection JEFFREY FULTON
Special/Order Compliance 10/29/2025 Partial Inspection JEFFREY FULTON
Final 1/22/2026 Not Ready for Inspection JEFFREY FULTON
Verify Sprinkler Sign Off 1/22/2026 Approved JEFFREY FULTON
Final 1/23/2026 Partial Inspection JEFFREY FULTON
Verify Rec and Parks Fee Memo 1/26/2026 Not Ready for Inspection LARRY ARNICK
Special/Order Compliance 1/27/2026 Partial Inspection DAVID BURKHEAD
Special/Order Compliance 1/28/2026 Partial Approval LARRY ARNICK
Special/Order Compliance 1/29/2026 Not Ready for Inspection LARRY ARNICK
Special/Order Compliance 1/30/2026 Not Ready for Inspection LARRY ARNICK
Special/Order Compliance 2/20/2026 Corrections Issued DAVID BURKHEAD
Special/Order Compliance 2/23/2026 Partial Inspection DAVID BURKHEAD
Special/Order Compliance 2/24/2026 Partial Inspection DAVID BURKHEAD
Special/Order Compliance 2/26/2026 Partial Inspection DAVID BURKHEAD
Final 2/27/2026 OK for TCO DAVID BURKHEAD
Footing/Foundation/Slab 2/27/2026 Approved DAVID BURKHEAD
Green Building Final 2/27/2026 Approved DAVID BURKHEAD
Green Building Rough 2/27/2026 Approved DAVID BURKHEAD
Reinforced Concrete Frame 2/27/2026 Approved DAVID BURKHEAD
Reinforced Masonry Frame 2/27/2026 Approved DAVID BURKHEAD
SGSOV-Seismic Gas S/O Valve 2/27/2026 SGSOV Approved DAVID BURKHEAD
Smoke Detectors 2/27/2026 Approved DAVID BURKHEAD
Final 3/24/2026 Partial Inspection DAVID BURKHEAD
Special/Order Compliance 7/28/2026 Approved DAVID BURKHEAD