2036 1/2 W 68TH ST 90047
Certificate Information: 2036 1/2 W 68TH ST 90047
- Application / Permit
- 22010-10000-04654
- Plan Check / Job No.
- B22LA18739
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- New Factory-Built Accessory Dwelling Unit per CA Govt. Code 65852.2(e)(1)(B) and applicable part of LAMC 12.22 A.33 (c)-(d), (g), per LADBS Standard Plan ADU30 and per RAD-31-1029.
- Permit Issued
- Issued on 12/23/2022
- Issuing Office
- Current Status
- CofO Issued on 12/27/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/19/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 9/23/2022 | SAMUEL GONZALEZ |
| Corrections Issued | 9/23/2022 | SHANGQIN XIE |
| Applicant returned to address corrections | 10/11/2022 | GEORGE ALVAREZ |
| Plan Check Approved | 12/19/2022 | SAMUEL GONZALEZ |
| Issued | 12/23/2022 | APPLICANT |
| CofO in Progress | 12/25/2023 | CRAIG DAVIS |
| Permit Finaled | 12/27/2023 | DEROLD HAUFF |
| CofO Issued | 12/27/2023 | DEROLD HAUFF |
| Permit Finaled | 12/27/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 9/26/2022 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 9/26/2022 | JEANIE LAM |
| Sewer availability | Cleared | 9/26/2022 | JEANIE LAM |
| Low Impact Development | Cleared | 11/4/2022 | LONDY ALVARADO |
| Roof/Waste drainage to street | Cleared | 11/7/2022 | JEANIE LAM |
| Construction near power lines | Cleared | 12/16/2022 | RIDWAN HARDY |
Contact Information
| Contractor | United Dwelling Construction Inc; Lic. No.: 1066382-B | 150 E 57TH ST LOS ANGELES, CA 90011 |
| Engineer | Sveiven,, Shane; Lic. No.: C89133 | 1909 S ALMA STREET SAN PEDRO, CA 90731 |
Inspector Information
| BARRY HACHE, (213) 202-9851 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 6/22/2023 | Approved | ENRIQUE MIRELES |
| Footing/Foundation/Slab | 6/22/2023 | Approved | ENRIQUE MIRELES |
| Underground Mechanical | 7/5/2023 | Approved | ENRIQUE MIRELES |
| Wood Frame | 7/5/2023 | Approved | ENRIQUE MIRELES |
| Underground Mechanical | 7/13/2023 | Approved | ENRIQUE MIRELES |
| ELECTRICAL-Final | 10/17/2023 | Partial Approval | RONNIE MINDANAO |
| Excavation/Setback/Form/Re-Bar | 10/17/2023 | Partial Inspection | RONNIE MINDANAO |
| HVAC-Final | 10/17/2023 | Approved | RONNIE MINDANAO |
| PLUMBING-Final | 10/17/2023 | Corrections Issued | RONNIE MINDANAO |
| SGSOV-Seismic Gas S/O Valve | 10/20/2023 | SGSOV Not Ready | JUSTIN HAWLEY |
| Verify Sprinkler Sign Off | 10/20/2023 | Approved | JUSTIN HAWLEY |
| ELECTRICAL-Final | 10/24/2023 | Approved | RONNIE MINDANAO |
| HVAC-Final | 10/24/2023 | Approved | RONNIE MINDANAO |
| PLUMBING-Final | 10/24/2023 | Approved | RONNIE MINDANAO |
| BUILDING-Rough-Frame | 11/3/2023 | No Access for Inspection | CRAIG DAVIS |
| Drywall Nailing | 11/3/2023 | No Access for Inspection | CRAIG DAVIS |
| Final | 11/3/2023 | No Access for Inspection | CRAIG DAVIS |
| SGSOV-Seismic Gas S/O Valve | 11/3/2023 | SGSOV Not Ready | CRAIG DAVIS |
| Service/Power Release | 11/3/2023 | No Access for Inspection | CRAIG DAVIS |
| Smoke Detectors | 11/3/2023 | No Access for Inspection | CRAIG DAVIS |
| BUILDING-Rough-Frame | 11/7/2023 | Approved | CRAIG DAVIS |
| Drywall Nailing | 11/7/2023 | Approved | CRAIG DAVIS |
| Final | 11/7/2023 | Partial Approval | CRAIG DAVIS |
| SGSOV-Seismic Gas S/O Valve | 11/7/2023 | SGSOV Not Required | CRAIG DAVIS |
| Service/Power Release | 11/7/2023 | Approved | CRAIG DAVIS |
| Smoke Detectors | 11/7/2023 | Approved | CRAIG DAVIS |
| Final | 11/15/2023 | Partial Approval | CRAIG DAVIS |
| Final | 12/22/2023 | OK to Issue CofO | CRAIG DAVIS |