3300 W WASHINGTON BLVD 1-84 90018

Certificate Information: 3300 W WASHINGTON BLVD 1-84 90018

Application / Permit
22010-10000-04618
Plan Check / Job No.
B22LA18546
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
NEW MIXED USE BUILDING WITH RETAIL AND 84 UNIT APARTMENT (INCLUDING 31 LOW INCOME UNITS). PROJECT UTILIZES INCENTIVES PER LAMC 12.22A.25 AND SB35
Permit Issued
Issued on 11/2/2023
Issuing Office
Metro
Current Status
Issued on 11/2/2023
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 9/15/2022 APPLICANT
Assigned to Plan Check Engineer 9/15/2022 VU NGUYEN
Corrections Issued 9/20/2022 VU NGUYEN
Quality Review Completed 9/21/2022 EUGENE BARBEAU
Applicant returned to address corrections 12/20/2022 VU NGUYEN
Applicant returned to address corrections 8/15/2023 VU NGUYEN
Applicant returned to address corrections 10/10/2023 VU NGUYEN
Applicant returned to address corrections 10/25/2023 VU NGUYEN
Plan Check Approved 11/2/2023 VU NGUYEN
Issued 11/2/2023 APPLICANT
TCO Issued (Expire Date: 09-27-2026) 3/31/2026 ERNESTO CORRAL

Permit Application Clearance Information

Green Code Cleared 2/22/2023 AARON COSTA
Address approval Cleared 3/23/2023 WALLIE JONG
Community Plan Implem. Overlay Cleared 3/23/2023 WALLIE JONG
Historic Resource Verification Cleared 3/24/2023 MAX LODER
Eng Process Fee Ord 176,300 Cleared 3/28/2023 WALLIE JONG
Community Plan Implem. Overlay Cleared 4/30/2023 ADALBERTO VERA
Abandoned oil well Cleared 5/15/2023 KURT CORRAL
Hydrant and Access approval Cleared 5/15/2023 KURT CORRAL
Sewer availability Cleared 5/24/2023 JEANIE LAM
Community Plan Implem. Overlay Cleared 6/7/2023 RIDWAN HARDY
Fire Marshal Fire Life Safety Cleared 6/15/2023 WILLIAM JOHNS
Community Plan Implem. Overlay Cleared 7/27/2023 MOHAMMAD HASAN
Trees in Parkway Cleared 8/16/2023 ADALBERTO VERA
Miscellaneous Cleared 8/21/2023 ELIZABETH GALLARDO
Redevelopment Project Area Cleared 8/21/2023 ELIZABETH GALLARDO
Highway dedication Cleared 8/31/2023 STEVE MELGAR
Building over 36-ft Cleared 9/6/2023 CALOSHA APPROVED
Low Impact Development Cleared 9/10/2023 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 9/11/2023 ALBERT TAM
Density Bonus Cleared 9/14/2023 LOUIE MILLER
Miscellaneous Cleared 10/4/2023 KYLE WINSTON
ZA Case Cleared 10/4/2023 EDBER MACEDO
Public Housing Cleared 10/12/2023 LUIS ALVAREZ
Community Plan Implem. Overlay Cleared 10/16/2023 DAVID URITA
Frnt yard landscape/Water mgmt Cleared 10/16/2023 DAVID URITA
Opn space landscape/Water mgmt Cleared 10/16/2023 DAVID URITA
DAS Clearance Cleared 10/25/2023 Joe Vo
Senate Bill 35 Cleared 10/25/2023 KYLE WINSTON

Contact Information

Architect Thelen,, Dirk D; Lic. No.: C37585 1150 W CAPITOL DRIVE UNIT 110      SAN PEDRO, CA 90732
Contractor Benchmark Contractors Inc; Lic. No.: 462263-B 3330 OCEAN PARK BLVD      SANTA MONICA, CA 90405
Engineer Hassan,, Mohamed Ali; Lic. No.: S5285 3621 HARBOR BLVD #125      SANTA ANA, CA 92704
Geologist Feffer,, Joshua R; Lic. No.: EG2138 12253 GORHAM AVE      LOS ANGELES, CA 90049

Inspector Information

MARTIN TAVITIAN, (213) 482-7357 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 2/15/2024 Partial Inspection GREGORY POMISH
Grading Pre-Inspection 3/14/2024 Not Ready for Inspection EDWIN GREGORYONA
Pre-Inspection 6/14/2024 Approved EDWIN GREGORYONA
Deputy Methane Barrier 7/1/2024 Partial Approval EDWIN GREGORYONA
METHANE-Rough 7/1/2024 Not Ready for Inspection EDWIN GREGORYONA
Deputy Reinf. Concrete 7/9/2024 Partial Approval EDWIN GREGORYONA
Excavation/Setback/Form/Re-Bar 7/9/2024 Not Ready for Inspection EDWIN GREGORYONA
METHANE-Barrier 7/9/2024 Not Ready for Inspection EDWIN GREGORYONA
Deputy Reinf. Concrete 7/12/2024 Partial Approval EDWIN GREGORYONA
Excavation/Setback/Form/Re-Bar 7/12/2024 Partial Approval EDWIN GREGORYONA
METHANE-Barrier 7/12/2024 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 7/23/2024 Partial Approval EDWIN GREGORYONA
Excavation/Setback/Form/Re-Bar 7/23/2024 Not Ready for Inspection EDWIN GREGORYONA
Excavation/Setback/Form/Re-Bar 7/24/2024 Partial Approval NICK DANERI
Excavation/Setback/Form/Re-Bar 8/1/2024 Partial Approval EDWIN GREGORYONA
METHANE-Subgrade 8/1/2024 Not Ready for Inspection EDWIN GREGORYONA
Deputy Methane Barrier 8/12/2024 Partial Approval EDWIN GREGORYONA
METHANE-Barrier 8/12/2024 Partial Inspection EDWIN GREGORYONA
Deputy Reinf. Concrete 8/23/2024 Partial Approval EDWIN GREGORYONA
Excavation/Setback/Form/Re-Bar 8/23/2024 Partial Approval EDWIN GREGORYONA
METHANE-Barrier 8/23/2024 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 8/26/2024 Partial Approval EDWIN GREGORYONA
Excavation/Setback/Form/Re-Bar 9/3/2024 Partial Approval EDWIN GREGORYONA
Structural Steel Frame 9/17/2024 Partial Approval LARRY ARNICK
Deputy Fireproofing 9/23/2024 Partial Approval EDWIN GREGORYONA
Structural Steel Frame 9/23/2024 Partial Approval EDWIN GREGORYONA
Floor/Roof Diaphrgm/Shear Wall 10/11/2024 Partial Approval EDWIN GREGORYONA
Floor/Roof Diaphrgm/Shear Wall 10/28/2024 Partial Approval EDWIN GREGORYONA
Wall Anchors 10/28/2024 Approved EDWIN GREGORYONA
Floor/Roof Diaphrgm/Shear Wall 10/31/2024 Partial Approval EDWIN GREGORYONA
Drywall Nailing 11/6/2024 Partial Approval MARTIN TAVITIAN
Floor/Roof Diaphrgm/Shear Wall 11/6/2024 Partial Approval MARTIN TAVITIAN
Floor/Roof Diaphrgm/Shear Wall 11/8/2024 Partial Approval EDWIN GREGORYONA
Floor/Roof Diaphrgm/Shear Wall 11/13/2024 Partial Approval EDWIN GREGORYONA
Wall Anchors 11/13/2024 Approved EDWIN GREGORYONA
Drywall Nailing 11/15/2024 Partial Approval EDWIN GREGORYONA
Floor/Roof Diaphrgm/Shear Wall 11/16/2024 Partial Approval NICK DANERI
Floor/Roof Diaphrgm/Shear Wall 11/22/2024 Partial Approval EDWIN GREGORYONA
Insulation 11/25/2024 Partial Approval RAFAEL CORTES
Floor/Roof Diaphrgm/Shear Wall 11/27/2024 Partial Approval MARTIN TAVITIAN
Floor/Roof Diaphrgm/Shear Wall 12/4/2024 Approved MARTIN TAVITIAN
Deputy Wood Construction 12/6/2024 Partial Approval EDWIN GREGORYONA
METHANE-Rough 12/6/2024 Approved EDWIN GREGORYONA
Green Building Rough 12/11/2024 Not Ready for Inspection EDWIN GREGORYONA
Verify Sprinkler Sign Off 12/11/2024 Partial Inspection EDWIN GREGORYONA
Wood Frame 12/11/2024 Partial Approval EDWIN GREGORYONA
Floor/Roof Diaphrgm/Shear Wall 12/16/2024 Partial Approval EDWIN GREGORYONA
Floor/Roof Diaphrgm/Shear Wall 12/17/2024 Partial Approval EDWIN GREGORYONA
Insulation 12/17/2024 Partial Inspection EDWIN GREGORYONA
Drywall Nailing 12/19/2024 Partial Approval EDWIN GREGORYONA
Insulation 12/19/2024 Partial Approval EDWIN GREGORYONA
Insulation 12/20/2024 Partial Approval EDWIN GREGORYONA
Floor/Roof Diaphrgm/Shear Wall 12/23/2024 Partial Approval MARTIN TAVITIAN
Drywall Nailing 1/10/2025 Partial Approval EDWIN GREGORYONA
Floor/Roof Diaphrgm/Shear Wall 1/10/2025 Partial Approval EDWIN GREGORYONA
Insulation 1/10/2025 Partial Approval EDWIN GREGORYONA
Drywall Nailing 1/15/2025 Partial Inspection EDWIN GREGORYONA
Floor/Roof Diaphrgm/Shear Wall 1/22/2025 Partial Approval EDWIN GREGORYONA
Insulation 1/29/2025 Partial Inspection EDWIN GREGORYONA
Insulation 1/30/2025 Not Ready for Inspection EDWIN GREGORYONA
Floor/Roof Diaphrgm/Shear Wall 2/3/2025 Partial Approval EDWIN GREGORYONA
Green Building Rough 2/3/2025 Partial Inspection EDWIN GREGORYONA
Light Gage Steel Frame 2/3/2025 Partial Approval EDWIN GREGORYONA
Verify Sprinkler Sign Off 2/3/2025 Approved EDWIN GREGORYONA
Wood Frame 2/3/2025 Partial Approval EDWIN GREGORYONA
Insulation 2/10/2025 Partial Approval EDWIN GREGORYONA
Floor/Roof Diaphrgm/Shear Wall 2/14/2025 Partial Approval EDWIN GREGORYONA
Insulation 2/24/2025 Partial Approval EDWIN GREGORYONA
Floor/Roof Diaphrgm/Shear Wall 3/4/2025 Partial Approval EDWIN GREGORYONA
Drywall Nailing 3/7/2025 Partial Approval EDWIN GREGORYONA
Light Gage Steel Frame 3/21/2025 Partial Approval LARRY ARNICK
Drywall Nailing 4/7/2025 Partial Approval EDWIN GREGORYONA
Interior/Exterior Lathing 4/7/2025 Partial Approval EDWIN GREGORYONA
Interior/Exterior Lathing 4/14/2025 Partial Approval MARTIN TAVITIAN
Green Building Rough 4/18/2025 Approved EDWIN GREGORYONA
Insulation 4/18/2025 Partial Approval EDWIN GREGORYONA
Interior/Exterior Lathing 4/18/2025 Partial Approval EDWIN GREGORYONA
Light Gage Steel Frame 4/18/2025 Not Ready for Inspection EDWIN GREGORYONA
Wood Frame 4/18/2025 Partial Approval EDWIN GREGORYONA
Wood Frame 4/25/2025 Not Ready for Inspection EDWIN GREGORYONA
Light Gage Steel Frame 4/28/2025 Not Ready for Inspection EDWIN GREGORYONA
Light Gage Steel Frame 5/1/2025 Partial Approval EDWIN GREGORYONA
Drywall Nailing 5/6/2025 Partial Approval MARTIN TAVITIAN
Light Gage Steel Frame 5/6/2025 Conditional Approval MARTIN TAVITIAN
Drywall Nailing 5/7/2025 Partial Approval EDWIN GREGORYONA
Light Gage Steel Frame 5/7/2025 Partial Approval EDWIN GREGORYONA
Drywall Nailing 5/8/2025 Not Ready for Inspection EDWIN GREGORYONA
Wood Frame 5/8/2025 Partial Approval EDWIN GREGORYONA
Light Gage Steel Frame 5/9/2025 Partial Approval EDWIN GREGORYONA
Drywall Nailing 5/12/2025 Partial Approval EDWIN GREGORYONA
Interior/Exterior Lathing 5/13/2025 Partial Approval EDWIN GREGORYONA
Light Gage Steel Frame 5/13/2025 Partial Approval EDWIN GREGORYONA
Drywall Nailing 5/22/2025 Partial Approval EDWIN GREGORYONA
Drywall Nailing 6/2/2025 Partial Approval EDWIN GREGORYONA
Drywall Nailing 6/11/2025 Partial Approval EDWIN GREGORYONA
Light Gage Steel Frame 6/27/2025 Partial Inspection EDWIN GREGORYONA
Light Gage Steel Frame 7/1/2025 Not Ready for Inspection EDWIN GREGORYONA
Light Gage Steel Frame 7/2/2025 Partial Approval EDWIN GREGORYONA
Structural Steel Frame 7/2/2025 Not Ready for Inspection EDWIN GREGORYONA
Wood Frame 7/2/2025 Not Ready for Inspection EDWIN GREGORYONA
Drywall Nailing 7/11/2025 Partial Approval EDWIN GREGORYONA
Deputy Steel/Welding 7/29/2025 Partial Approval EDWIN GREGORYONA
T-Bar Ceiling 7/29/2025 Not Ready for Inspection EDWIN GREGORYONA
T-Bar Ceiling 7/31/2025 Partial Approval EDWIN GREGORYONA
T-Bar Ceiling 8/6/2025 Partial Approval EDWIN GREGORYONA
Footing/Foundation/Slab 8/29/2025 Not Ready for Inspection SORIN CIRSTOIU
METHANE-Barrier 8/29/2025 Not Ready for Inspection SORIN CIRSTOIU
METHANE-Subgrade 8/29/2025 Not Ready for Inspection SORIN CIRSTOIU
Excavation/Setback/Form/Re-Bar 9/2/2025 Partial Approval MARTIN TAVITIAN
Pre-Inspection 9/5/2025 Not Ready for Inspection ALFREDO LOPEZ
Pre-Inspection 10/7/2025 Partial Approval EDWIN GREGORYONA
Pre-Inspection 12/1/2025 Partial Approval LARRY ARNICK
Special/Order Compliance 12/1/2025 Conditional Approval LARRY ARNICK
T-Bar Ceiling 12/1/2025 Approved LARRY ARNICK
Pre-Inspection 1/21/2026 Partial Approval EDWIN GREGORYONA
Pre-Inspection 2/10/2026 Approved MARTIN TAVITIAN
Posting Pre-Inspection 2/12/2026 Approved MARTIN TAVITIAN
Pre-Inspection 2/26/2026 Approved MARTIN TAVITIAN
Final 3/9/2026 Not Ready for Inspection MARTIN TAVITIAN
Footing/Foundation/Slab 3/9/2026 Not Ready for Inspection MARTIN TAVITIAN
Green Building Final 3/9/2026 Approved MARTIN TAVITIAN
METHANE-Barrier 3/9/2026 Not Ready for Inspection MARTIN TAVITIAN
METHANE-Subgrade 3/9/2026 Not Ready for Inspection MARTIN TAVITIAN
SGSOV-Seismic Gas S/O Valve 3/9/2026 SGSOV Not Ready MARTIN TAVITIAN
Smoke Detectors 3/9/2026 Not Ready for Inspection MARTIN TAVITIAN
Wood Frame 3/9/2026 Not Ready for Inspection MARTIN TAVITIAN
Final 3/25/2026 Not Ready for Inspection MARTIN TAVITIAN
Footing/Foundation/Slab 3/25/2026 Partial Approval MARTIN TAVITIAN
METHANE-Barrier 3/25/2026 Not Ready for Inspection MARTIN TAVITIAN
METHANE-Subgrade 3/25/2026 Approved MARTIN TAVITIAN
SGSOV-Seismic Gas S/O Valve 3/25/2026 SGSOV Not Ready MARTIN TAVITIAN
Smoke Detectors 3/25/2026 Not Ready for Inspection MARTIN TAVITIAN
Wood Frame 3/25/2026 Approved MARTIN TAVITIAN