Pre-Inspection
|
2/15/2024
|
Partial Inspection
|
GREGORY POMISH
|
|
Grading Pre-Inspection
|
3/14/2024
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
|
Pre-Inspection
|
6/14/2024
|
Approved
|
EDWIN GREGORYONA
|
|
Deputy Methane Barrier
|
7/1/2024
|
Partial Approval
|
EDWIN GREGORYONA
|
|
METHANE-Rough
|
7/1/2024
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
|
Deputy Reinf. Concrete
|
7/9/2024
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Excavation/Setback/Form/Re-Bar
|
7/9/2024
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
|
METHANE-Barrier
|
7/9/2024
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
|
Deputy Reinf. Concrete
|
7/12/2024
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Excavation/Setback/Form/Re-Bar
|
7/12/2024
|
Partial Approval
|
EDWIN GREGORYONA
|
|
METHANE-Barrier
|
7/12/2024
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Deputy Reinf. Concrete
|
7/23/2024
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Excavation/Setback/Form/Re-Bar
|
7/23/2024
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
|
Excavation/Setback/Form/Re-Bar
|
7/24/2024
|
Partial Approval
|
NICK DANERI
|
|
Excavation/Setback/Form/Re-Bar
|
8/1/2024
|
Partial Approval
|
EDWIN GREGORYONA
|
|
METHANE-Subgrade
|
8/1/2024
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
|
Deputy Methane Barrier
|
8/12/2024
|
Partial Approval
|
EDWIN GREGORYONA
|
|
METHANE-Barrier
|
8/12/2024
|
Partial Inspection
|
EDWIN GREGORYONA
|
|
Deputy Reinf. Concrete
|
8/23/2024
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Excavation/Setback/Form/Re-Bar
|
8/23/2024
|
Partial Approval
|
EDWIN GREGORYONA
|
|
METHANE-Barrier
|
8/23/2024
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Deputy Reinf. Concrete
|
8/26/2024
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Excavation/Setback/Form/Re-Bar
|
9/3/2024
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Structural Steel Frame
|
9/17/2024
|
Partial Approval
|
LARRY ARNICK
|
|
Deputy Fireproofing
|
9/23/2024
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Structural Steel Frame
|
9/23/2024
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
10/11/2024
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
10/28/2024
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Wall Anchors
|
10/28/2024
|
Approved
|
EDWIN GREGORYONA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
10/31/2024
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Drywall Nailing
|
11/6/2024
|
Partial Approval
|
MARTIN TAVITIAN
|
|
Floor/Roof Diaphrgm/Shear Wall
|
11/6/2024
|
Partial Approval
|
MARTIN TAVITIAN
|
|
Floor/Roof Diaphrgm/Shear Wall
|
11/8/2024
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
11/13/2024
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Wall Anchors
|
11/13/2024
|
Approved
|
EDWIN GREGORYONA
|
|
Drywall Nailing
|
11/15/2024
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
11/16/2024
|
Partial Approval
|
NICK DANERI
|
|
Floor/Roof Diaphrgm/Shear Wall
|
11/22/2024
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Insulation
|
11/25/2024
|
Partial Approval
|
RAFAEL CORTES
|
|
Floor/Roof Diaphrgm/Shear Wall
|
11/27/2024
|
Partial Approval
|
MARTIN TAVITIAN
|
|
Floor/Roof Diaphrgm/Shear Wall
|
12/4/2024
|
Approved
|
MARTIN TAVITIAN
|
|
Deputy Wood Construction
|
12/6/2024
|
Partial Approval
|
EDWIN GREGORYONA
|
|
METHANE-Rough
|
12/6/2024
|
Approved
|
EDWIN GREGORYONA
|
|
Green Building Rough
|
12/11/2024
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
|
Verify Sprinkler Sign Off
|
12/11/2024
|
Partial Inspection
|
EDWIN GREGORYONA
|
|
Wood Frame
|
12/11/2024
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
12/16/2024
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
12/17/2024
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Insulation
|
12/17/2024
|
Partial Inspection
|
EDWIN GREGORYONA
|
|
Drywall Nailing
|
12/19/2024
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Insulation
|
12/19/2024
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Insulation
|
12/20/2024
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
12/23/2024
|
Partial Approval
|
MARTIN TAVITIAN
|
|
Drywall Nailing
|
1/10/2025
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
1/10/2025
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Insulation
|
1/10/2025
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Drywall Nailing
|
1/15/2025
|
Partial Inspection
|
EDWIN GREGORYONA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
1/22/2025
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Insulation
|
1/29/2025
|
Partial Inspection
|
EDWIN GREGORYONA
|
|
Insulation
|
1/30/2025
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
2/3/2025
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Green Building Rough
|
2/3/2025
|
Partial Inspection
|
EDWIN GREGORYONA
|
|
Light Gage Steel Frame
|
2/3/2025
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Verify Sprinkler Sign Off
|
2/3/2025
|
Approved
|
EDWIN GREGORYONA
|
|
Wood Frame
|
2/3/2025
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Insulation
|
2/10/2025
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
2/14/2025
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Insulation
|
2/24/2025
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
3/4/2025
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Drywall Nailing
|
3/7/2025
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Light Gage Steel Frame
|
3/21/2025
|
Partial Approval
|
LARRY ARNICK
|
|
Drywall Nailing
|
4/7/2025
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Interior/Exterior Lathing
|
4/7/2025
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Interior/Exterior Lathing
|
4/14/2025
|
Partial Approval
|
MARTIN TAVITIAN
|
|
Green Building Rough
|
4/18/2025
|
Approved
|
EDWIN GREGORYONA
|
|
Insulation
|
4/18/2025
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Interior/Exterior Lathing
|
4/18/2025
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Light Gage Steel Frame
|
4/18/2025
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
|
Wood Frame
|
4/18/2025
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Wood Frame
|
4/25/2025
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
|
Light Gage Steel Frame
|
4/28/2025
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
|
Light Gage Steel Frame
|
5/1/2025
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Drywall Nailing
|
5/6/2025
|
Partial Approval
|
MARTIN TAVITIAN
|
|
Light Gage Steel Frame
|
5/6/2025
|
Conditional Approval
|
MARTIN TAVITIAN
|
|
Drywall Nailing
|
5/7/2025
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Light Gage Steel Frame
|
5/7/2025
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Drywall Nailing
|
5/8/2025
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
|
Wood Frame
|
5/8/2025
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Light Gage Steel Frame
|
5/9/2025
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Drywall Nailing
|
5/12/2025
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Interior/Exterior Lathing
|
5/13/2025
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Light Gage Steel Frame
|
5/13/2025
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Drywall Nailing
|
5/22/2025
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Drywall Nailing
|
6/2/2025
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Drywall Nailing
|
6/11/2025
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Light Gage Steel Frame
|
6/27/2025
|
Partial Inspection
|
EDWIN GREGORYONA
|
|
Light Gage Steel Frame
|
7/1/2025
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
|
Light Gage Steel Frame
|
7/2/2025
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Structural Steel Frame
|
7/2/2025
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
|
Wood Frame
|
7/2/2025
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
|
Drywall Nailing
|
7/11/2025
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Deputy Steel/Welding
|
7/29/2025
|
Partial Approval
|
EDWIN GREGORYONA
|
|
T-Bar Ceiling
|
7/29/2025
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
|
T-Bar Ceiling
|
7/31/2025
|
Partial Approval
|
EDWIN GREGORYONA
|
|
T-Bar Ceiling
|
8/6/2025
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Footing/Foundation/Slab
|
8/29/2025
|
Not Ready for Inspection
|
SORIN CIRSTOIU
|
|
METHANE-Barrier
|
8/29/2025
|
Not Ready for Inspection
|
SORIN CIRSTOIU
|
|
METHANE-Subgrade
|
8/29/2025
|
Not Ready for Inspection
|
SORIN CIRSTOIU
|
|
Excavation/Setback/Form/Re-Bar
|
9/2/2025
|
Partial Approval
|
MARTIN TAVITIAN
|
|
Pre-Inspection
|
9/5/2025
|
Not Ready for Inspection
|
ALFREDO LOPEZ
|
|
Pre-Inspection
|
10/7/2025
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Pre-Inspection
|
12/1/2025
|
Partial Approval
|
LARRY ARNICK
|
|
Special/Order Compliance
|
12/1/2025
|
Conditional Approval
|
LARRY ARNICK
|
|
T-Bar Ceiling
|
12/1/2025
|
Approved
|
LARRY ARNICK
|
|
Pre-Inspection
|
1/21/2026
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Pre-Inspection
|
2/10/2026
|
Approved
|
MARTIN TAVITIAN
|
|
Posting Pre-Inspection
|
2/12/2026
|
Approved
|
MARTIN TAVITIAN
|
|
Pre-Inspection
|
2/26/2026
|
Approved
|
MARTIN TAVITIAN
|
|
Final
|
3/9/2026
|
Not Ready for Inspection
|
MARTIN TAVITIAN
|
|
Footing/Foundation/Slab
|
3/9/2026
|
Not Ready for Inspection
|
MARTIN TAVITIAN
|
|
Green Building Final
|
3/9/2026
|
Approved
|
MARTIN TAVITIAN
|
|
METHANE-Barrier
|
3/9/2026
|
Not Ready for Inspection
|
MARTIN TAVITIAN
|
|
METHANE-Subgrade
|
3/9/2026
|
Not Ready for Inspection
|
MARTIN TAVITIAN
|
|
SGSOV-Seismic Gas S/O Valve
|
3/9/2026
|
SGSOV Not Ready
|
MARTIN TAVITIAN
|
|
Smoke Detectors
|
3/9/2026
|
Not Ready for Inspection
|
MARTIN TAVITIAN
|
|
Wood Frame
|
3/9/2026
|
Not Ready for Inspection
|
MARTIN TAVITIAN
|
|
Final
|
3/25/2026
|
Not Ready for Inspection
|
MARTIN TAVITIAN
|
|
Footing/Foundation/Slab
|
3/25/2026
|
Partial Approval
|
MARTIN TAVITIAN
|
|
METHANE-Barrier
|
3/25/2026
|
Not Ready for Inspection
|
MARTIN TAVITIAN
|
|
METHANE-Subgrade
|
3/25/2026
|
Approved
|
MARTIN TAVITIAN
|
|
SGSOV-Seismic Gas S/O Valve
|
3/25/2026
|
SGSOV Not Ready
|
MARTIN TAVITIAN
|
|
Smoke Detectors
|
3/25/2026
|
Not Ready for Inspection
|
MARTIN TAVITIAN
|
|
Wood Frame
|
3/25/2026
|
Approved
|
MARTIN TAVITIAN
|