22109 W KITTRIDGE ST 91303

Certificate Information: 22109 W KITTRIDGE ST 91303

Application / Permit
22010-10000-04607
Plan Check / Job No.
B22LA18518
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
New one story ADU PER LAMC 12.22 A.33 (c)(d)
Permit Issued
Issued on 11/14/2022
Issuing Office
Valley
Current Status
CofO Issued on 4/17/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/15/2022 APPLICANT
Assigned to Plan Check Engineer 9/19/2022 KHUONG TRUONG
Corrections Issued 9/21/2022 KHUONG TRUONG
Building Plans Picked Up 9/27/2022 APPLICANT
Plan Check Approved 11/10/2022 RICARDO RAMIREZ
Issued 11/14/2022 APPLICANT
CofO in Progress 4/3/2024 TROY SANDERS
Permit Finaled 4/17/2024 JOHN JANSON
CofO Issued 4/17/2024 JOHN JANSON
Permit Finaled 4/17/2024 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 10/12/2022 RYAN KIM
Eng Process Fee Ord 176,300 Cleared 10/13/2022 RYAN KIM
Sewer availability Cleared 10/13/2022 RYAN KIM
ZI Cleared 10/13/2022 MAXFIELD VERMY
Low Impact Development Cleared 11/7/2022 ROGELIO CORTES
Roof/Waste drainage to street Cleared 11/8/2022 RYAN KIM

Contact Information

Contractor Owner-Builder       ,
Engineer Dorta,, Michael Rohrs; Lic. No.: C72538 2445 VIA SONOMA      PALOS VERDES ESTATES, CA 90274

Inspector Information

GEVORK IPCHYAN, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI
TROY SANDERS, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 12/23/2022 Approved TROY SANDERS
BUILDING-Rough-Frame 1/13/2023 Partial Approval TROY SANDERS
Sewer 1/13/2023 Approved TROY SANDERS
Underground Mechanical 1/13/2023 Partial Approval TROY SANDERS
Floor/Roof Diaphrgm/Shear Wall 1/20/2023 Partial Approval JON MCHUGH
Floor/Roof Diaphrgm/Shear Wall 2/9/2023 Partial Approval TROY SANDERS
BUILDING-Rough-Frame 3/16/2023 Partial Approval TROY SANDERS
Floor/Roof Diaphrgm/Shear Wall 3/16/2023 Partial Approval TROY SANDERS
Rough-Elec/Plmb/HVAC 3/16/2023 Approved TROY SANDERS
BUILDING-Rough-Frame 4/20/2023 Approved TROY SANDERS
Green Building Rough 4/20/2023 Approved TROY SANDERS
Insulation 4/20/2023 Approved TROY SANDERS
Interior/Exterior Lathing 4/20/2023 Partial Approval TROY SANDERS
Verify Sprinkler Sign Off 4/20/2023 Approved TROY SANDERS
Drywall Nailing 4/28/2023 Approved TROY SANDERS
Interior/Exterior Lathing 4/28/2023 Partial Approval TROY SANDERS
Shower Pan 4/28/2023 Approved TROY SANDERS
Final 4/2/2024 OK to Issue CofO TROY SANDERS
Footing/Foundation/Slab 4/2/2024 Approved TROY SANDERS
Green Building Final 4/2/2024 Approved TROY SANDERS
SGSOV-Seismic Gas S/O Valve 4/2/2024 SGSOV Approved TROY SANDERS
Service/Power Release 4/2/2024 Approved TROY SANDERS
Smoke Detectors 4/2/2024 Approved TROY SANDERS