22109 W KITTRIDGE ST 91303
Certificate Information: 22109 W KITTRIDGE ST 91303
- Application / Permit
- 22010-10000-04607
- Plan Check / Job No.
- B22LA18518
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- New one story ADU PER LAMC 12.22 A.33 (c)(d)
- Permit Issued
- Issued on 11/14/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 4/17/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/15/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 9/19/2022 | KHUONG TRUONG |
| Corrections Issued | 9/21/2022 | KHUONG TRUONG |
| Building Plans Picked Up | 9/27/2022 | APPLICANT |
| Plan Check Approved | 11/10/2022 | RICARDO RAMIREZ |
| Issued | 11/14/2022 | APPLICANT |
| CofO in Progress | 4/3/2024 | TROY SANDERS |
| Permit Finaled | 4/17/2024 | JOHN JANSON |
| CofO Issued | 4/17/2024 | JOHN JANSON |
| Permit Finaled | 4/17/2024 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 10/12/2022 | RYAN KIM |
| Eng Process Fee Ord 176,300 | Cleared | 10/13/2022 | RYAN KIM |
| Sewer availability | Cleared | 10/13/2022 | RYAN KIM |
| ZI | Cleared | 10/13/2022 | MAXFIELD VERMY |
| Low Impact Development | Cleared | 11/7/2022 | ROGELIO CORTES |
| Roof/Waste drainage to street | Cleared | 11/8/2022 | RYAN KIM |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Dorta,, Michael Rohrs; Lic. No.: C72538 | 2445 VIA SONOMA PALOS VERDES ESTATES, CA 90274 |
Inspector Information
| GEVORK IPCHYAN, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
| TROY SANDERS, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 12/23/2022 | Approved | TROY SANDERS |
| BUILDING-Rough-Frame | 1/13/2023 | Partial Approval | TROY SANDERS |
| Sewer | 1/13/2023 | Approved | TROY SANDERS |
| Underground Mechanical | 1/13/2023 | Partial Approval | TROY SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 1/20/2023 | Partial Approval | JON MCHUGH |
| Floor/Roof Diaphrgm/Shear Wall | 2/9/2023 | Partial Approval | TROY SANDERS |
| BUILDING-Rough-Frame | 3/16/2023 | Partial Approval | TROY SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 3/16/2023 | Partial Approval | TROY SANDERS |
| Rough-Elec/Plmb/HVAC | 3/16/2023 | Approved | TROY SANDERS |
| BUILDING-Rough-Frame | 4/20/2023 | Approved | TROY SANDERS |
| Green Building Rough | 4/20/2023 | Approved | TROY SANDERS |
| Insulation | 4/20/2023 | Approved | TROY SANDERS |
| Interior/Exterior Lathing | 4/20/2023 | Partial Approval | TROY SANDERS |
| Verify Sprinkler Sign Off | 4/20/2023 | Approved | TROY SANDERS |
| Drywall Nailing | 4/28/2023 | Approved | TROY SANDERS |
| Interior/Exterior Lathing | 4/28/2023 | Partial Approval | TROY SANDERS |
| Shower Pan | 4/28/2023 | Approved | TROY SANDERS |
| Final | 4/2/2024 | OK to Issue CofO | TROY SANDERS |
| Footing/Foundation/Slab | 4/2/2024 | Approved | TROY SANDERS |
| Green Building Final | 4/2/2024 | Approved | TROY SANDERS |
| SGSOV-Seismic Gas S/O Valve | 4/2/2024 | SGSOV Approved | TROY SANDERS |
| Service/Power Release | 4/2/2024 | Approved | TROY SANDERS |
| Smoke Detectors | 4/2/2024 | Approved | TROY SANDERS |