17834 W DUNCAN ST 91316
Certificate Information: 17834 W DUNCAN ST 91316
- Application / Permit
- 22010-10000-04603
- Plan Check / Job No.
- B22LA18470
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN: CONVERT (E) DETACHED 20’ 2” X 18’ 5” GARAGE TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d). ALL WORK DONE PER WFPP.
- Permit Issued
- Issued on 1/16/2023
- Issuing Office
- Current Status
- CofO Issued on 11/14/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/15/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 9/21/2022 | GURUNATH NESARAJAH |
| Corrections Issued | 9/22/2022 | ALFRED RAMIREZ |
| Plan Check Approved | 12/16/2022 | GURUNATH NESARAJAH |
| Issued | 1/16/2023 | APPLICANT |
| CofO in Progress | 10/31/2023 | JEFFREY BULL |
| Permit Finaled | 11/14/2023 | JOHN JANSON |
| CofO Issued | 11/14/2023 | JOHN JANSON |
| Permit Finaled | 11/14/2023 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 9/27/2022 | CHRIS CHAHBAZ |
| Sewer availability | Cleared | 9/27/2022 | CHRIS CHAHBAZ |
| ZI | Cleared | 9/28/2022 | MIGUEL GAMBOA |
| Eng Process Fee Ord 176,300 | Cleared | 9/29/2022 | CHRIS CHAHBAZ |
| Construction within easement | Cleared | 12/1/2022 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| ARUTYUN MADATYAN, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
| JUAN ALVARADO, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 7/10/2023 | Corrections Issued | PETER FOLLING |
| PLUMBING-Rough | 7/13/2023 | Partial Approval | JEFFREY BULL |
| Footing/Foundation/Slab | 7/18/2023 | Approved | JEFFREY BULL |
| BUILDING-Rough-Frame | 9/7/2023 | Not Ready for Inspection | JEFFREY BULL |
| ELECTRICAL-Rough | 9/7/2023 | Approved | JEFFREY BULL |
| FLOOD-Proofing Certificate | 9/7/2023 | Approved | JEFFREY BULL |
| Green Building Rough | 9/7/2023 | Not Ready for Inspection | JEFFREY BULL |
| PLUMBING-Rough | 9/7/2023 | Approved | JEFFREY BULL |
| Insulation | 9/15/2023 | Approved | JEFFREY BULL |
| Interior/Exterior Lathing | 9/15/2023 | Partial Approval | JEFFREY BULL |
| Shower Pan | 9/15/2023 | Approved | JEFFREY BULL |
| Drywall Nailing | 9/21/2023 | Approved | JEFFREY BULL |
| Interior/Exterior Lathing | 9/21/2023 | Approved | JEFFREY BULL |
| BUILDING-Rough-Frame | 10/30/2023 | Approved | JEFFREY BULL |
| ELECTRICAL-Final | 10/30/2023 | Approved | JEFFREY BULL |
| Final | 10/30/2023 | OK to Issue CofO | JEFFREY BULL |
| Green Building Final | 10/30/2023 | Approved | JEFFREY BULL |
| Green Building Rough | 10/30/2023 | Approved | JEFFREY BULL |
| HVAC-Final | 10/30/2023 | Approved | JEFFREY BULL |
| PLUMBING-Final | 10/30/2023 | Approved | JEFFREY BULL |
| SGSOV-Seismic Gas S/O Valve | 10/30/2023 | SGSOV Not Required | JEFFREY BULL |
| Service/Power Release | 10/30/2023 | Approved | JEFFREY BULL |
| Smoke Detectors | 10/30/2023 | Approved | JEFFREY BULL |