3128 E BLANCHARD ST 90063
Certificate Information: 3128 E BLANCHARD ST 90063
- Application / Permit
- 22010-10000-04598
- Plan Check / Job No.
- B22LA16624
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- E plan: New 2 story ADU over garage 2 of 2
- Permit Issued
- Issued on 6/25/2024
- Issuing Office
- Current Status
- CofO Issued on 12/18/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/1/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 9/8/2022 | TSE MING HUANG |
| Corrections Issued | 9/14/2022 | TSE MING HUANG |
| Re-Submittal Required | 9/27/2022 | EUGENE BARBEAU |
| Re-Submitted | 12/12/2022 | EUGENE BARBEAU |
| Corrections Issued 2 | 12/12/2022 | EUGENE BARBEAU |
| Submitted for Second Quality Review | 12/12/2022 | EUGENE BARBEAU |
| Quality Review Completed | 12/12/2022 | EUGENE BARBEAU |
| Plan Check Approved | 5/23/2024 | TSE MING HUANG |
| Plan Check Approved | 5/24/2024 | TSE MING HUANG |
| Issued | 6/25/2024 | APPLICANT |
| CofO in Progress | 12/13/2025 | ALIZAH MAYAGOITIA |
| No Progress | 12/13/2025 | DEROLD HAUFF |
| CofO in Progress | 12/13/2025 | DEROLD HAUFF |
| Permit Finaled | 12/18/2025 | DEROLD HAUFF |
| CofO Issued | 12/18/2025 | DEROLD HAUFF |
| Permit Finaled | 12/18/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| ZI | Cleared | 10/5/2022 | SPENCER WEJROWSKI |
| Address approval | Cleared | 10/6/2022 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 10/11/2022 | WALLIE JONG |
| Sewer availability | Cleared | 10/26/2022 | WALLIE JONG |
| Hydrant and Access approval | Cleared | 11/12/2022 | GILBERT URREA |
| Low Impact Development | Cleared | 1/13/2023 | LONDY ALVARADO |
| Roof/Waste drainage to street | Cleared | 1/19/2023 | WALLIE JONG |
| Grading Pre-Inspection | Cleared | 2/6/2023 | TSE MING HUANG |
| SB8 RUD | Cleared | 5/7/2024 | ALYSSA FLORES |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Salto,, Alvaro; Lic. No.: C83859 | 2543 E NORMAN AVE WEST COVINA, CA 91791 |
Inspector Information
| OSVALDO PARAMO, (213) 202-9854 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 10/30/2024 | Partial Approval | LUIS CASTRO |
| Excavation/Setback/Form/Re-Bar | 11/20/2024 | Corrections Issued | WILLIAM SIERRA |
| Footing/Foundation/Slab | 11/20/2024 | Not Ready for Inspection | WILLIAM SIERRA |
| Excavation/Setback/Form/Re-Bar | 11/22/2024 | Corrections Issued | JOHN QUINTANILLA |
| Excavation/Setback/Form/Re-Bar | 11/26/2024 | Partial Approval | OSVALDO PARAMO |
| Floor/Roof Diaphrgm/Shear Wall | 2/26/2025 | Partial Approval | ALIZAH MAYAGOITIA |
| Floor/Roof Diaphrgm/Shear Wall | 4/2/2025 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Floor/Roof Diaphrgm/Shear Wall | 5/2/2025 | Partial Approval | ALIZAH MAYAGOITIA |
| Deputy Wood Construction | 5/9/2025 | Conditional Approval | ALIZAH MAYAGOITIA |
| Floor/Roof Diaphrgm/Shear Wall | 5/14/2025 | Partial Approval | ALIZAH MAYAGOITIA |
| HVAC-Rough | 5/14/2025 | Corrections Issued | ALIZAH MAYAGOITIA |
| ELECTRICAL-Rough | 5/20/2025 | Approved | ALIZAH MAYAGOITIA |
| HVAC-Rough | 5/20/2025 | Approved | ALIZAH MAYAGOITIA |
| PLUMBING-Rough | 5/20/2025 | Approved | ALIZAH MAYAGOITIA |
| BUILDING-Rough-Frame | 5/21/2025 | Approved | ALIZAH MAYAGOITIA |
| Green Building Rough | 5/21/2025 | Approved | ALIZAH MAYAGOITIA |
| Verify Sprinkler Sign Off | 5/21/2025 | Approved | ALIZAH MAYAGOITIA |
| Insulation | 5/28/2025 | Corrections Issued | REGINA MENDEZ |
| Interior/Exterior Lathing | 5/28/2025 | Approved | REGINA MENDEZ |
| Shower Pan | 5/28/2025 | Approved | REGINA MENDEZ |
| Drywall Nailing | 6/5/2025 | Approved | REGINA MENDEZ |
| Insulation | 6/5/2025 | Approved | REGINA MENDEZ |
| Interior/Exterior Lathing | 6/6/2025 | Partial Approval | REGINA MENDEZ |
| Interior/Exterior Lathing | 6/13/2025 | Approved | REGINA MENDEZ |
| Underground Mechanical | 8/18/2025 | Partial Approval | ALIZAH MAYAGOITIA |
| Underground Mechanical | 8/27/2025 | Approved | ALIZAH MAYAGOITIA |
| Service/Power Release | 11/10/2025 | Approved | DAVID WILLIAMS |
| ELECTRICAL-Final | 11/13/2025 | Corrections Issued | ALIZAH MAYAGOITIA |
| HVAC-Final | 11/13/2025 | Approved | ALIZAH MAYAGOITIA |
| ELECTRICAL-Final | 11/19/2025 | Approved | ALIZAH MAYAGOITIA |
| PLUMBING-Final | 11/19/2025 | Approved | ALIZAH MAYAGOITIA |
| PLUMBING-Final | 12/4/2025 | Approved | ALIZAH MAYAGOITIA |
| Final | 12/12/2025 | OK to Issue CofO | ALIZAH MAYAGOITIA |
| Footing/Foundation/Slab | 12/12/2025 | Approved | ALIZAH MAYAGOITIA |
| Green Building Final | 12/12/2025 | Approved | ALIZAH MAYAGOITIA |
| SGSOV-Seismic Gas S/O Valve | 12/12/2025 | SGSOV Approved | ALIZAH MAYAGOITIA |
| Smoke Detectors | 12/12/2025 | Approved | ALIZAH MAYAGOITIA |