4026 S DALTON AVE 90062
Certificate Information: 4026 S DALTON AVE 90062
- Application / Permit
- 22010-10000-04588
- Plan Check / Job No.
- B22LA18403
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- New 2 story ADU at Rear Lot. 2 of 2
- Permit Issued
- Issued on 6/21/2024
- Issuing Office
- Current Status
- CofO Issued on 5/19/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/13/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 9/29/2022 | TSE MING HUANG |
| Corrections Issued | 10/6/2022 | TSE MING HUANG |
| Quality Review Completed | 10/11/2022 | EUGENE BARBEAU |
| Building Plans Picked Up | 10/13/2022 | APPLICANT |
| Plan Check Approved | 4/23/2024 | TSE MING HUANG |
| Issued | 6/21/2024 | APPLICANT |
| CofO in Progress | 5/15/2026 | SABAS ALONSO |
| Permit Finaled | 5/19/2026 | DEROLD HAUFF |
| CofO Issued | 5/19/2026 | DEROLD HAUFF |
| Permit Finaled | 5/19/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 1/6/2023 | JEANETTE VONG |
| Eng Process Fee Ord 176,300 | Cleared | 2/21/2023 | JEANETTE VONG |
| Sewer availability | Cleared | 2/21/2023 | JEANETTE VONG |
| Construction near power lines | Cleared | 8/7/2023 | RIDWAN HARDY |
| Construction within easement | Cleared | 8/7/2023 | RIDWAN HARDY |
| Roof/Waste drainage to street | Cleared | 8/27/2023 | AHMED AMARRAGY |
| Low Impact Development | Cleared | 10/6/2023 | MELINEH AGHAKHABIAN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Melchor,, Oscar Elias; Lic. No.: C76828 | 21243 VENTURA BLVD SUITE 119 WOODLAND HILLS, CA 91364 |
Inspector Information
| SABAS ALONSO, (213) 202-3468 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 2/11/2025 | Approved | JOHN QUINTANILLA |
| Footing/Foundation/Slab | 2/24/2025 | Approved | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 3/7/2025 | Partial Approval | SABAS ALONSO |
| HVAC-Rough | 4/28/2025 | Corrections Issued | SABAS ALONSO |
| PLUMBING-Rough | 4/28/2025 | Approved | SABAS ALONSO |
| ELECTRICAL-Rough | 5/5/2025 | Approved | SABAS ALONSO |
| Green Building Rough | 5/5/2025 | Not Ready for Inspection | SABAS ALONSO |
| Insulation | 5/29/2025 | Corrections Issued | JOSE MACIAS |
| Interior/Exterior Lathing | 5/29/2025 | Approved | JOSE MACIAS |
| Special/Order Compliance | 5/29/2025 | Corrections Issued | JOSE MACIAS |
| BUILDING-Rough-Frame | 6/3/2025 | Approved | MICHAEL LEWIS |
| Green Building Rough | 6/3/2025 | Approved | MICHAEL LEWIS |
| HVAC-Rough | 6/3/2025 | Approved | MICHAEL LEWIS |
| Insulation | 6/3/2025 | Conditional Approval | MICHAEL LEWIS |
| Drywall Nailing | 6/11/2025 | Approved | ALEX COLIN |
| Interior/Exterior Lathing | 8/22/2025 | Approved | ANTHONY RAMOS |
| Shower Pan | 8/22/2025 | Approved | ANTHONY RAMOS |
| Final | 10/24/2025 | Corrections Issued | SABAS ALONSO |
| Green Building Final | 10/24/2025 | Not Ready for Inspection | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 10/24/2025 | SGSOV Not Ready | SABAS ALONSO |
| Service/Power Release | 10/24/2025 | Not Ready for Inspection | SABAS ALONSO |
| Smoke Detectors | 10/24/2025 | Approved | SABAS ALONSO |
| Final | 1/16/2026 | Not Ready for Inspection | SABAS ALONSO |
| Green Building Final | 1/16/2026 | Approved | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 1/16/2026 | SGSOV Not Ready | SABAS ALONSO |
| Service/Power Release | 1/16/2026 | Not Ready for Inspection | SABAS ALONSO |
| Final | 2/2/2026 | Not Ready for Inspection | BARRY HACHE |
| SGSOV-Seismic Gas S/O Valve | 2/2/2026 | SGSOV Approved | BARRY HACHE |
| Final | 2/10/2026 | Corrections Issued | SABAS ALONSO |
| Service/Power Release | 2/10/2026 | Not Ready for Inspection | SABAS ALONSO |
| Final | 4/20/2026 | Corrections Issued | SABAS ALONSO |
| Service/Power Release | 4/20/2026 | Not Ready for Inspection | SABAS ALONSO |
| Final | 4/29/2026 | Not Ready for Inspection | SABAS ALONSO |
| Final | 5/14/2026 | OK to Issue CofO | SABAS ALONSO |
| Service/Power Release | 5/14/2026 | Approved | SABAS ALONSO |