2202 S BALSAM AVE 90064
Certificate Information: 2202 S BALSAM AVE 90064
- Application / Permit
- 22010-10000-04587
- Plan Check / Job No.
- B22LA18392
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- e garage conversion to adu PER STATE LAW
- Permit Issued
- Issued on 11/2/2022
- Issuing Office
- Current Status
- CofO Corrected on 6/6/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/13/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 9/19/2022 | KHUONG TRUONG |
| Corrections Issued | 9/20/2022 | KHUONG TRUONG |
| Plan Check Approved | 10/31/2022 | KHUONG TRUONG |
| Issued | 11/2/2022 | APPLICANT |
| CofO in Progress | 6/1/2023 | MICHAEL PELHAM |
| CofO in Progress | 6/1/2023 | MICHAEL PELHAM |
| CofO Issued-Status Void | 6/5/2023 | DANIEL ORRANTE |
| Permit Finaled-Status Void | 6/5/2023 | DANIEL ORRANTE |
| Re-Activate Permit | 6/6/2023 | DANIEL ORRANTE |
| Permit Finaled | 6/6/2023 | DANIEL ORRANTE |
| CofO Corrected | 6/6/2023 | DANIEL ORRANTE |
| Permit Finaled | 6/6/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Sewer availability | Cleared | 9/22/2022 | JENSON LEE |
| Grading Pre-Inspection | Cleared | 10/3/2022 | LANNY MERRICK |
| Address approval | Cleared | 10/12/2022 | JENSON LEE |
| Eng Process Fee Ord 176,300 | Cleared | 10/12/2022 | JENSON LEE |
| Specific Plan | Cleared | 10/20/2022 | EDUARDO HERMOSO |
Contact Information
| Contractor | America Green Builders; Lic. No.: 1020657-B | , |
| Contractor | Bhm Group Inc; Lic. No.: 1020657-B | , |
| Engineer | Melchor,, Oscar Elias; Lic. No.: C76828 | 21243 VENTURA BLVD SUITE 119 WOODLAND HILLS, CA 91364 |
Inspector Information
| DAVID SCANTLIN, (310) 914-3863 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 11/29/2022 | Conditional Approval | MICHAEL PELHAM |
| Footing/Foundation/Slab | 11/30/2022 | Approved | CARLOS MATAMOROS |
| Underground Mechanical | 11/30/2022 | Approved | CARLOS MATAMOROS |
| BUILDING-Rough-Frame | 1/17/2023 | Partial Approval | STEPHANIE SWANSON |
| ELECTRICAL-Rough | 1/17/2023 | Not Ready for Inspection | STEPHANIE SWANSON |
| FLOOD-Proofing Certificate | 1/17/2023 | Approved | STEPHANIE SWANSON |
| Green Building Rough | 1/17/2023 | Not Ready for Inspection | STEPHANIE SWANSON |
| HVAC-Rough | 1/17/2023 | Partial Approval | STEPHANIE SWANSON |
| METHANE-Rough | 1/17/2023 | Approved | STEPHANIE SWANSON |
| PLUMBING-Rough | 1/17/2023 | Approved | STEPHANIE SWANSON |
| SGSOV-Seismic Gas S/O Valve | 1/17/2023 | SGSOV Not Ready | STEPHANIE SWANSON |
| Underground Mechanical | 1/17/2023 | Corrections Issued | STEPHANIE SWANSON |
| ELECTRICAL-Rough | 1/23/2023 | Corrections Issued | STEPHANIE SWANSON |
| Underground Mechanical | 1/23/2023 | Approved | STEPHANIE SWANSON |
| ELECTRICAL-Rough | 1/27/2023 | Corrections Issued | STEPHANIE SWANSON |
| HVAC-Rough | 1/27/2023 | Corrections Issued | STEPHANIE SWANSON |
| Interior/Exterior Lathing | 1/27/2023 | Corrections Issued | STEPHANIE SWANSON |
| ELECTRICAL-Rough | 1/31/2023 | Partial Approval | STEPHANIE SWANSON |
| HVAC-Rough | 1/31/2023 | Approved | STEPHANIE SWANSON |
| Interior/Exterior Lathing | 1/31/2023 | Partial Approval | STEPHANIE SWANSON |
| Insulation | 2/1/2023 | Approved | STEPHANIE SWANSON |
| Floor/Roof Diaphrgm/Shear Wall | 2/6/2023 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| BUILDING-Rough-Frame | 2/8/2023 | Approved | STEPHANIE SWANSON |
| Floor/Roof Diaphrgm/Shear Wall | 2/8/2023 | Approved | STEPHANIE SWANSON |
| Green Building Rough | 2/8/2023 | Approved | STEPHANIE SWANSON |
| Deputy Wood Construction | 2/9/2023 | Conditional Approval | MICHAEL PELHAM |
| Drywall Nailing | 2/13/2023 | Approved | STEPHANIE SWANSON |
| Shower Pan | 2/15/2023 | Approved | STEPHANIE SWANSON |
| Interior/Exterior Lathing | 2/21/2023 | Approved | STEPHANIE SWANSON |
| ELECTRICAL-Rough | 3/2/2023 | Not Ready for Inspection | CHRISTOPHER WILSON |
| ELECTRICAL-Final | 3/29/2023 | Corrections Issued | STEPHANIE SWANSON |
| Green Building Final | 3/29/2023 | Approved | STEPHANIE SWANSON |
| HVAC-Final | 3/29/2023 | Approved | STEPHANIE SWANSON |
| PLUMBING-Final | 3/29/2023 | Not Ready for Inspection | STEPHANIE SWANSON |
| SGSOV-Seismic Gas S/O Valve | 3/29/2023 | SGSOV Not Ready | STEPHANIE SWANSON |
| Smoke Detectors | 3/29/2023 | Approved | STEPHANIE SWANSON |
| ELECTRICAL-Final | 4/5/2023 | Approved | STEPHANIE SWANSON |
| Final | 4/5/2023 | Corrections Issued | STEPHANIE SWANSON |
| PLUMBING-Final | 4/5/2023 | Corrections Issued | STEPHANIE SWANSON |
| SGSOV-Seismic Gas S/O Valve | 4/5/2023 | SGSOV Approved | STEPHANIE SWANSON |
| Final | 4/10/2023 | OK to Issue CofO | STEPHANIE SWANSON |
| PLUMBING-Final | 4/10/2023 | Approved | STEPHANIE SWANSON |