8107 S HOLY CROSS PL 90045

Certificate Information: 8107 S HOLY CROSS PL 90045

Application / Permit
22010-10000-04577
Plan Check / Job No.
B22LA18325
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
eplan: NEW 2-STORY ATTACHED ADU TO (E) GARAGE. ADU PER ORDINANCE
Permit Issued
Issued on 8/4/2023
Issuing Office
Current Status
CofO Issued on 6/10/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/26/2022 APPLICANT
Assigned to Plan Check Engineer 9/29/2022 JAD BASMA
Corrections Issued 10/1/2022 JAD BASMA
Quality Review Completed 10/12/2022 TEODORO DIAZ RODRIGUEZ
Applicant returned to address corrections 4/21/2023 JAD BASMA
Plan Check Approved 7/6/2023 JAD BASMA
Issued 8/4/2023 APPLICANT
CofO in Progress 6/5/2025 JESUS PINEDA
Permit Finaled 6/10/2025 RICHARD STEINBACH
CofO Issued 6/10/2025 RICHARD STEINBACH
Permit Finaled 6/10/2025 RICHARD STEINBACH

Permit Application Clearance Information

Address approval Cleared 10/25/2022 DINAH GARIN
Eng Process Fee Ord 176,300 Cleared 10/26/2022 DINAH GARIN
Sewer availability Cleared 10/26/2022 DINAH GARIN
Miscellaneous Cleared 4/13/2023 JAD BASMA
Specific Plan Cleared 5/9/2023 JIMMY VIVAR
Low Impact Development Cleared 6/5/2023 ROGELIO CORTES
Roof/Waste drainage to street Cleared 6/13/2023 AHMED AMARRAGY

Contact Information

Contractor Adu Building Company; Lic. No.: 1098802-B       ,

Inspector Information

MICHAEL LEWIS, (310) 914-3979 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 8/28/2023 Approved BOBBY KEY
Excavation/Setback/Form/Re-Bar 9/5/2023 Approved JESUS RODRIGUEZ
Footing/Foundation/Slab 9/5/2023 Conditional Approval JESUS RODRIGUEZ
Sewer 9/5/2023 Not Ready for Inspection JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 9/19/2023 Partial Approval BOBBY KEY
Footing/Foundation/Slab 9/19/2023 Approved BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 10/17/2023 Partial Approval BOBBY KEY
ELECTRICAL-Rough 10/25/2023 Approved JESUS RODRIGUEZ
HVAC-Rough 10/25/2023 Approved JESUS RODRIGUEZ
PLUMBING-Rough 10/25/2023 Approved JESUS RODRIGUEZ
BUILDING-Rough-Frame 10/30/2023 Approved BOBBY KEY
Green Building Rough 10/30/2023 Approved BOBBY KEY
Insulation 10/30/2023 Corrections Issued BOBBY KEY
Interior/Exterior Lathing 10/30/2023 Partial Approval BOBBY KEY
Drywall Nailing 11/3/2023 Approved KENNETH NAGLE
Gas Test 1/4/2024 Approved BOBBY KEY
PLUMBING-Rough 1/4/2024 Corrections Issued BOBBY KEY
Sewer 1/4/2024 Approved BOBBY KEY
Underground Mechanical 1/4/2024 Partial Approval BOBBY KEY
Gas Test 1/10/2024 Approved BOBBY KEY
Special/Order Compliance 1/10/2024 Partial Inspection BEN MOLSTAD
ELECTRICAL-Final 1/31/2024 Corrections Issued BOBBY KEY
Final 1/31/2024 Corrections Issued BOBBY KEY
Green Building Final 1/31/2024 Approved BOBBY KEY
HVAC-Final 1/31/2024 Corrections Issued BOBBY KEY
PLUMBING-Final 1/31/2024 Approved BOBBY KEY
SGSOV-Seismic Gas S/O Valve 1/31/2024 SGSOV Not Ready BOBBY KEY
Smoke Detectors 1/31/2024 Approved BOBBY KEY
ELECTRICAL-Final 2/14/2024 Not Ready for Inspection BOBBY KEY
HVAC-Final 2/14/2024 Approved BOBBY KEY
ELECTRICAL-Final 8/8/2024 Approved TEMISTOCLES CAAL
Final 5/28/2025 Not Ready for Inspection JESUS PINEDA
SGSOV-Seismic Gas S/O Valve 5/28/2025 SGSOV Not Ready JESUS PINEDA
Final 6/4/2025 OK to Issue CofO JESUS PINEDA
SGSOV-Seismic Gas S/O Valve 6/4/2025 SGSOV Approved JESUS PINEDA
Service/Power Release 6/6/2025 Approved JESUS PINEDA