3930 S FIGUEROA ST 90037
Certificate Information: 3930 S FIGUEROA ST 90037
- Application / Permit
- 22010-10000-04568
- Plan Check / Job No.
- B22VN13150
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Commercial
- Primary Use
- (26) Temporary Structure
- Work Description
- ePlanLA. New commercial coach/modular - Temporary state-approved office module building (11'9"x64') with accessibility ramp.
- Permit Issued
- Issued on 11/2/2022
- Issuing Office
- Current Status
- Permit Closed on 11/1/2023
- Certificate of Occupancy
- Permit Closed More Information
Permit Application Status History
| Submitted | 8/29/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 9/1/2022 | TU HUA |
| Corrections Issued | 9/14/2022 | TU HUA |
| Quality Review Completed | 9/17/2022 | QUAN NGHIEM |
| Applicant returned to address corrections | 10/5/2022 | TU HUA |
| Applicant returned to address corrections | 10/28/2022 | TU HUA |
| Plan Check Approved | 11/2/2022 | TU HUA |
| Issued | 11/2/2022 | APPLICANT |
| Permit Closed | 10/31/2023 | LARRY ARNICK |
Permit Application Clearance Information
| Low Impact Development | Cleared | 9/16/2022 | MARTIN FRAGOSO |
| Eng Process Fee Ord 176,300 | Cleared | 9/20/2022 | AMAAN MALIK |
| Roof/Waste drainage to street | Cleared | 9/20/2022 | AMAAN MALIK |
| Sewer availability | Cleared | 9/20/2022 | AMAAN MALIK |
| DAS Clearance | Cleared | 10/5/2022 | TU HUA |
| "D" conditions | Cleared | 10/14/2022 | ANACANY HURTADO |
| "Q" conditions | Cleared | 10/14/2022 | ANACANY HURTADO |
| "T" removal | Cleared | 10/14/2022 | ANACANY HURTADO |
| CPC | Cleared | 10/14/2022 | ANACANY HURTADO |
| Green Code | Cleared | 10/14/2022 | TU HUA |
| Miscellaneous | Cleared | 10/14/2022 | ANACANY HURTADO |
| Miscellaneous | Cleared | 10/14/2022 | ANACANY HURTADO |
| ZA Case | Cleared | 10/14/2022 | ANACANY HURTADO |
| Redevelopment Project Area | Cleared | 10/24/2022 | DAVID URITA |
Contact Information
| Architect | Yelos-San, Martin, Miguel Santiago; Lic. No.: C22548 | 1320 ELLSWORTH INDUSTRIAL BLVD STE A100 ATLANTA, GA 30318 |
| Contractor | Kunzik & Sara Construction Inc; Lic. No.: 847939-B | , |
| Engineer | Mahaffey,, Riley J; Lic. No.: C51006 | 201 N MAPLE GROVE RD STE 100 BOISE, ID 83704 |
| Engineer | Nieman,, Adam M; Lic. No.: C91181 | 12008 N 144TH AVE SURPRISE, AZ 85379 |
Inspector Information
| ALFREDO LOPEZ, (213) 482-0361 | Office Hours: 7:00-8:00 AM MON-FRI |
| JAMES POWERS, (213) 482-0361 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Final | 11/7/2022 | Partial Inspection | RUSSELL BONVOULOIR |
| Footing/Foundation/Slab | 11/7/2022 | Approved | RUSSELL BONVOULOIR |
| Green Building Final | 11/7/2022 | Approved | RUSSELL BONVOULOIR |
| Green Building Rough | 11/7/2022 | Approved | RUSSELL BONVOULOIR |
| SGSOV-Seismic Gas S/O Valve | 11/7/2022 | SGSOV Approved | RUSSELL BONVOULOIR |
| Smoke Detectors | 11/7/2022 | Approved | RUSSELL BONVOULOIR |
| Verify Sprinkler Sign Off | 11/7/2022 | Approved | RUSSELL BONVOULOIR |
| Final | 10/31/2023 | Permit Closed | LARRY ARNICK |
| Wood Frame | 10/31/2023 | Approved | LARRY ARNICK |