431 1/2 W 103RD ST 90003

Certificate Information: 431 1/2 W 103RD ST 90003

Application / Permit
22010-10000-04552
Plan Check / Job No.
B22LA18181
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
*EPLAN* NEW 1-STORY DETACHED ADU (404 SF) PER LAMC 12.22.A.33(c)-(d) ALL CONSTRUCTION PER WFPP.
Permit Issued
Issued on 10/14/2022
Issuing Office
Current Status
Issued on 10/14/2022
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 9/9/2022 APPLICANT
Assigned to Plan Check Engineer 9/14/2022 VIVIAN LAO
Corrections Issued 9/15/2022 VIVIAN LAO
Applicant returned to address corrections 9/20/2022 VIVIAN LAO
Applicant returned to address corrections 9/29/2022 VIVIAN LAO
Plan Check Approved 10/13/2022 VIVIAN LAO
Issued 10/14/2022 APPLICANT

Permit Application Clearance Information

Address approval Cleared 9/16/2022 ABEL CASILLAS
Eng Process Fee Ord 176,300 Cleared 10/7/2022 ABEL CASILLAS
Sewer availability Cleared 10/7/2022 ABEL CASILLAS
Roof/Waste drainage to street Cleared 10/11/2022 ABEL CASILLAS

Contact Information

Contractor Owner-Builder       ,

Inspector Information

BEN MOLSTAD, (310) 732-4557 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 10/24/2022 Not Ready for Inspection ALIZAH MAYAGOITIA
Footing/Foundation/Slab 10/24/2022 Not Ready for Inspection ALIZAH MAYAGOITIA
PLUMBING-Rough 10/24/2022 Corrections Issued ALIZAH MAYAGOITIA
Footing/Foundation/Slab 10/27/2022 Corrections Issued JOHN KLARIN
PLUMBING-Rough 10/27/2022 Partial Inspection JOHN KLARIN
Excavation/Setback/Form/Re-Bar 11/7/2022 Approved JOHN KLARIN
PLUMBING-Rough 11/7/2022 Partial Approval JOHN KLARIN
Floor/Roof Diaphrgm/Shear Wall 12/7/2022 Approved JAMES CHAVEZ
Interior/Exterior Lathing 12/20/2022 Approved JAMES CHAVEZ
BUILDING-Rough-Frame 12/27/2022 Not Ready for Inspection JAMES CHAVEZ
ELECTRICAL-Rough 12/27/2022 Approved JAMES CHAVEZ
Green Building Rough 12/27/2022 Not Ready for Inspection JAMES CHAVEZ
MERV13>=Rough 12/27/2022 Approved JAMES CHAVEZ
PLUMBING-Rough 12/27/2022 Corrections Issued JAMES CHAVEZ
Verify Sprinkler Sign Off 12/27/2022 Approved JAMES CHAVEZ
Insulation 1/3/2023 Approved JAMES CHAVEZ
Drywall Nailing 1/18/2023 Approved JAMES CHAVEZ
Green Building Rough 1/18/2023 Approved JAMES CHAVEZ
BUILDING-Rough-Frame 8/11/2023 Approved JOHN KLARIN
ELECTRICAL-Final 8/11/2023 Approved JOHN KLARIN
Final 8/11/2023 Corrections Issued JOHN KLARIN
Footing/Foundation/Slab 8/11/2023 Approved JOHN KLARIN
Green Building Final 8/11/2023 Corrections Issued JOHN KLARIN
MERV13>=Final 8/11/2023 Approved JOHN KLARIN
SGSOV-Seismic Gas S/O Valve 8/11/2023 SGSOV Approved JOHN KLARIN
Service/Power Release 8/11/2023 Not Ready for Inspection JOHN KLARIN
Smoke Detectors 8/11/2023 Approved JOHN KLARIN
ELECTRICAL-Final 7/8/2024 Corrections Issued BEN MOLSTAD
Final 7/8/2024 Corrections Issued BEN MOLSTAD
Green Building Final 7/8/2024 Corrections Issued BEN MOLSTAD
Service/Power Release 7/8/2024 Not Ready for Inspection BEN MOLSTAD
ELECTRICAL-Final 8/6/2024 Corrections Issued JOSEPH MCGARRY
Final 8/6/2024 Corrections Issued JOSEPH MCGARRY
Green Building Final 8/6/2024 Corrections Issued JOSEPH MCGARRY
HVAC-Final 8/6/2024 Corrections Issued JOSEPH MCGARRY
PLUMBING-Final 8/6/2024 Approved JOSEPH MCGARRY
Final 6/9/2025 No Access for Inspection BEN MOLSTAD
Green Building Final 6/9/2025 No Access for Inspection BEN MOLSTAD
Service/Power Release 6/9/2025 No Access for Inspection BEN MOLSTAD
ELECTRICAL-Final 6/25/2025 No Access for Inspection BEN MOLSTAD
ELECTRICAL-Final 6/26/2025 Not Ready for Inspection JOHN KLARIN
ELECTRICAL-Final 7/2/2025 Corrections Issued BEN MOLSTAD
ELECTRICAL-Final 7/22/2025 Corrections Issued BEN MOLSTAD
Final 8/5/2025 Not Ready for Inspection BEN MOLSTAD
Green Building Final 8/5/2025 Not Ready for Inspection BEN MOLSTAD
Service/Power Release 8/5/2025 Not Ready for Inspection BEN MOLSTAD
ELECTRICAL-Final 8/21/2025 Approved BEN MOLSTAD
Final 1/27/2026 Corrections Issued BEN MOLSTAD
Green Building Final 1/27/2026 Not Ready for Inspection BEN MOLSTAD
Service/Power Release 1/27/2026 Not Ready for Inspection BEN MOLSTAD