1305 1/4-1307 N WATERLOO ST 90026

Certificate Information: 1305 1/4-1307 N WATERLOO ST 90026

Application / Permit
22010-10000-04536
Plan Check / Job No.
B22LA18079
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Eplan. Converting existing basement floor 430 sq.ft. in (e) duplex to new ADU.
Permit Issued
Issued on 11/29/2022
Issuing Office
Current Status
CofO Issued on 6/5/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/8/2022 APPLICANT
Assigned to Plan Check Engineer 9/9/2022 JOSEPH RAFOLS
Corrections Issued 9/9/2022 JOSEPH RAFOLS
Applicant returned to address corrections 9/29/2022 JOSEPH RAFOLS
Plan Check Approved 10/5/2022 JOSEPH RAFOLS
Issued 11/29/2022 APPLICANT
CofO in Progress 6/4/2025 HAMIK HARTOUNIAN
Permit Finaled 6/5/2025 DEROLD HAUFF
CofO Issued 6/5/2025 DEROLD HAUFF
Permit Finaled 6/5/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 9/19/2022 STEVE MELGAR
Sewer availability Cleared 9/19/2022 STEVE MELGAR
Eng Process Fee Ord 176,300 Cleared 9/22/2022 STEVE MELGAR
Tenant Habitability Plan Cleared 9/27/2022 MICHAEL SOTO

Contact Information

Contractor Iba Builders Inc; Lic. No.: 1074505-B       ,

Inspector Information

HAMIK HARTOUNIAN, (213) 202-3275 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 1/30/2023 Not Ready for Inspection KATHRYN BUTTERWORTH
PLUMBING-Rough 1/30/2023 Not Ready for Inspection KATHRYN BUTTERWORTH
Wood Frame 1/30/2023 Not Ready for Inspection KATHRYN BUTTERWORTH
Footing/Foundation/Slab 4/19/2023 Conditional Approval SCOTT FINNILA
BUILDING-Rough-Frame 5/9/2023 Not Ready for Inspection THOMAS LOGRASSO
ELECTRICAL-Rough 5/9/2023 Not Ready for Inspection THOMAS LOGRASSO
PLUMBING-Rough 5/9/2023 Not Ready for Inspection THOMAS LOGRASSO
Pre-Inspection 5/15/2023 Corrections Issued THOMAS LOGRASSO
BUILDING-Rough-Frame 7/18/2023 Not Ready for Inspection THOMAS LOGRASSO
ELECTRICAL-Rough 7/18/2023 Not Ready for Inspection THOMAS LOGRASSO
PLUMBING-Rough 7/18/2023 Corrections Issued THOMAS LOGRASSO
Special/Order Compliance 7/26/2023 Corrections Issued THOMAS LOGRASSO
BUILDING-Rough-Frame 8/4/2023 Conditional Approval THOMAS LOGRASSO
ELECTRICAL-Rough 8/4/2023 Approved THOMAS LOGRASSO
Footing/Foundation/Slab 8/4/2023 Approved THOMAS LOGRASSO
HVAC-Rough 8/4/2023 Corrections Issued THOMAS LOGRASSO
PLUMBING-Rough 8/4/2023 Conditional Approval THOMAS LOGRASSO
Sewer 8/4/2023 Approved THOMAS LOGRASSO
HVAC-Rough 8/7/2023 Not Ready for Inspection THOMAS LOGRASSO
PLUMBING-Rough 8/7/2023 Not Ready for Inspection THOMAS LOGRASSO
BUILDING-Rough-Frame 8/14/2023 Not Ready for Inspection THOMAS LOGRASSO
Insulation 8/25/2023 Not Ready for Inspection THOMAS LOGRASSO
BUILDING-Rough-Frame 4/3/2025 Approved HAMIK HARTOUNIAN
Final 4/3/2025 Partial Inspection HAMIK HARTOUNIAN
SGSOV-Seismic Gas S/O Valve 4/3/2025 SGSOV Approved HAMIK HARTOUNIAN
Smoke Detectors 4/3/2025 Approved HAMIK HARTOUNIAN
Final 5/13/2025 Partial Inspection HAMIK HARTOUNIAN
Final 5/19/2025 Corrections Issued HAMIK HARTOUNIAN
Final 6/4/2025 OK to Issue CofO HAMIK HARTOUNIAN