5016 N RUBIO AVE 91436

Certificate Information: 5016 N RUBIO AVE 91436

Application / Permit
22010-10000-04535
Plan Check / Job No.
B22LA18064
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSED ( 26'-6" x 15'-6" ) IRREGULAR SHAPED ADDITION TO THE (E) SINGLE FAMILY DWELLING FOR A NEW BEDROOM, BATHROOM, CLOSET, LAUNDRY/ POWDER ROOM AND ENTRY. REMODEL (E) KITCHEN AND DINING ROOM.
Permit Issued
Issued on 10/31/2022
Issuing Office
Current Status
Issued on 10/31/2022
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 9/8/2022 APPLICANT
Assigned to Plan Check Engineer 9/13/2022 ROSENDO MEDINA
Corrections Issued 9/14/2022 ROSENDO MEDINA
Plan Check Approved 10/30/2022 SARKIS HARABEDIAN
Issued 10/31/2022 APPLICANT

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 9/15/2022 LUCIA MERCADO
Tract Map conditions Cleared 9/21/2022 STEVEN WECHSLER
Sewer availability Cleared 9/22/2022 LUCIA MERCADO
Eng Process Fee Ord 176,300 Cleared 10/27/2022 LUCIA MERCADO

Contact Information

Contractor Arteaga Humbertino; Lic. No.: 415598-B       ,
Contractor Humbert Construction Inc; Lic. No.: 415598-B       ,
Engineer Basma,, Ali J; Lic. No.: C53080 21757 DEVONSHIRE ST.   SUITE 3    CANOGA PARK, CA 91311

Inspector Information

THOMAS FINNILA, (818) 774-4324 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 8/21/2023 Conditional Approval MORRIS JACKSON
Excavation/Setback/Form/Re-Bar 9/1/2023 Corrections Issued VINCENT HANLEY
Footing/Foundation/Slab 9/1/2023 Partial Approval VINCENT HANLEY
Pre-Inspection 9/1/2023 Approved VINCENT HANLEY
BUILDING-Rough-Frame 9/14/2023 Partial Approval VINCENT HANLEY
Footing/Foundation/Slab 9/14/2023 Approved VINCENT HANLEY
PLUMBING-Rough 9/14/2023 Partial Approval VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 9/18/2023 Partial Approval VINCENT HANLEY
Insulation 9/18/2023 Partial Approval VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 1/18/2024 Approved VINCENT HANLEY
HVAC-Rough 1/18/2024 Corrections Issued VINCENT HANLEY
PLUMBING-Rough 1/18/2024 Corrections Issued VINCENT HANLEY
Rough-Elec/Plmb/HVAC 1/30/2024 Not Ready for Inspection MORRIS JACKSON
BUILDING-Rough-Frame 2/2/2024 Corrections Issued VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 2/2/2024 Approved VINCENT HANLEY
Insulation 2/2/2024 Approved VINCENT HANLEY
Interior/Exterior Lathing 2/2/2024 Partial Inspection VINCENT HANLEY
BUILDING-Rough-Frame 2/6/2024 Approved VINCENT HANLEY
ELECTRICAL-Rough 2/6/2024 Approved VINCENT HANLEY
Green Building Rough 2/6/2024 Approved VINCENT HANLEY
HVAC-Rough 2/6/2024 Approved VINCENT HANLEY
PLUMBING-Rough 2/6/2024 Approved VINCENT HANLEY
Drywall Nailing 2/9/2024 Approved VINCENT HANLEY
Interior/Exterior Lathing 2/13/2024 Approved VINCENT HANLEY
Shower Pan 2/13/2024 Approved VINCENT HANLEY
Final 12/24/2024 Not Ready for Inspection GEVORK IPCHYAN
Green Building Final 12/24/2024 Not Ready for Inspection GEVORK IPCHYAN
SGSOV-Seismic Gas S/O Valve 12/24/2024 SGSOV Approved GEVORK IPCHYAN
Smoke Detectors 12/24/2024 Approved GEVORK IPCHYAN
Gas Test 12/27/2024 Not Ready for Inspection THOMAS FINNILA
Final 12/31/2024 Corrections Issued THOMAS FINNILA
Green Building Final 12/31/2024 Not Ready for Inspection THOMAS FINNILA
Final 1/30/2025 Corrections Issued JOHN COLEMAN
Green Building Final 1/30/2025 Approved JOHN COLEMAN
Final 3/28/2025 Not Ready for Inspection THOMAS FINNILA
Final 4/10/2025 Conditional Approval THOMAS FINNILA