10342 N QUILL AVE 91040

Certificate Information: 10342 N QUILL AVE 91040

Pre - Inspection only, not a permit for construction

Application / Permit
22010-10000-04521
Plan Check / Job No.
B22LA18030
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(N) DETACHED 1-STORY IRREGULAR SHAPED 33'-6" x 42'-4" ACCESSORY DWELLING UNIT TO COMPLY WITH LAMC 12.22 A.33(c),(d) AND (g). ALL WORK PER ENGINEERING
Permit Issued
Issued on 2/15/2023
Issuing Office
Current Status
Pending
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/8/2022 APPLICANT
Assigned to Plan Check Engineer 9/12/2022 JOSEPH RAFOLS
Corrections Issued 9/14/2022 JOSEPH RAFOLS
Building Plans Picked Up 9/22/2022 APPLICANT
Applicant returned to address corrections 1/27/2023 ALFRED RAMIREZ
Issued 2/15/2023 APPLICANT
CofO in Progress 8/8/2023 DAVID ANDERSON
CofO Issued 9/11/2023 RUBEN SALAS
Permit Finaled 9/11/2023 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 9/28/2022 COLIN LOREDO
Eng Process Fee Ord 176,300 Cleared 9/28/2022 COLIN LOREDO
Sewer availability Cleared 9/29/2022 COLIN LOREDO
Construction near power lines Cleared 11/10/2022 RIDWAN HARDY
Low Impact Development Cleared 1/13/2023 DEBORA LEITE
Roof/Waste drainage to street Cleared 1/13/2023 COLIN LOREDO
Grading Pre-Inspection Cleared 1/24/2023 MICHAEL TEMPLE
GPI Written Notices Cleared 2/15/2023 JOSEPH RAFOLS

Contact Information

Contractor Owner-Builder       ,
Engineer Grigoryan,, Souren; Lic. No.: C93320 6506 TEESDALE AVE      NORTH HOLLYWOOD, CA 91606

Inspector Information

DAVID ANDERSON, (818) 374-1168 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 2/17/2023 Corrections Issued DAVID ANDERSON
Footing/Foundation/Slab 2/17/2023 Not Ready for Inspection DAVID ANDERSON
Underground Mechanical 2/17/2023 Not Ready for Inspection DAVID ANDERSON
Excavation/Setback/Form/Re-Bar 2/22/2023 Approved DAVID ANDERSON
PLUMBING-Rough 2/22/2023 Partial Approval DAVID ANDERSON
Pre-Inspection 2/22/2023 Not Ready for Inspection DAVID ANDERSON
Excavation/Setback/Form/Re-Bar 3/3/2023 Approved DAVID ANDERSON
BUILDING-Rough-Frame 4/18/2023 Not Ready for Inspection DAVID ANDERSON
Floor/Roof Diaphrgm/Shear Wall 4/18/2023 Approved DAVID ANDERSON
Green Building Rough 4/18/2023 Not Ready for Inspection DAVID ANDERSON
Verify Sprinkler Sign Off 4/18/2023 Approved DAVID ANDERSON
Wood Frame 4/18/2023 Not Ready for Inspection DAVID ANDERSON
Deputy Wood Construction 4/20/2023 Conditional Approval MICHAEL SMITH
BUILDING-Rough-Frame 4/26/2023 Partial Approval DAVID ANDERSON
ELECTRICAL-Rough 5/3/2023 Corrections Issued DAVID ANDERSON
HVAC-Rough 5/3/2023 Approved DAVID ANDERSON
PLUMBING-Rough 5/3/2023 Approved DAVID ANDERSON
ELECTRICAL-Rough 5/4/2023 Approved DAVID ANDERSON
BUILDING-Rough-Frame 5/8/2023 Approved DAVID ANDERSON
Green Building Rough 5/8/2023 Approved DAVID ANDERSON
Insulation 5/8/2023 Approved DAVID ANDERSON
Interior/Exterior Lathing 5/8/2023 Approved DAVID ANDERSON
Shower Pan 5/8/2023 Approved DAVID ANDERSON
Drywall Nailing 5/11/2023 Approved DAVID ANDERSON
Interior/Exterior Lathing 5/11/2023 Approved DAVID ANDERSON
ELECTRICAL-Final 6/29/2023 Not Ready for Inspection DAVID ANDERSON
Final 6/29/2023 Corrections Issued DAVID ANDERSON
Footing/Foundation/Slab 6/29/2023 Approved DAVID ANDERSON
Green Building Final 6/29/2023 Approved DAVID ANDERSON
HVAC-Final 6/29/2023 Approved DAVID ANDERSON
PLUMBING-Final 6/29/2023 Approved DAVID ANDERSON
SGSOV-Seismic Gas S/O Valve 6/29/2023 SGSOV Not Ready DAVID ANDERSON
Service/Power Release 6/29/2023 Not Ready for Inspection DAVID ANDERSON
Smoke Detectors 6/29/2023 Approved DAVID ANDERSON
ELECTRICAL-Final 8/7/2023 Approved DAVID ANDERSON
Final 8/7/2023 OK to Issue CofO DAVID ANDERSON
SGSOV-Seismic Gas S/O Valve 8/7/2023 SGSOV Approved DAVID ANDERSON
Service/Power Release 8/7/2023 Approved DAVID ANDERSON