771 N ILIFF ST 90272
Certificate Information: 771 N ILIFF ST 90272
- Application / Permit
- 22010-10000-04490
- Plan Check / Job No.
- B22LA17889
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePlan - NEW 2 STORY SFD W ATTACHED 2 CAR GARAGE
- Permit Issued
- Issued on 4/13/2023
- Issuing Office
- Current Status
- CofO Issued on 11/7/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/8/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 9/15/2022 | STARR CHEN |
| Corrections Issued | 9/17/2022 | STARR CHEN |
| Quality Review Completed | 9/19/2022 | EUGENE BARBEAU |
| Applicant returned to address corrections | 1/27/2023 | SERGIO GUTIERREZ |
| Applicant returned to address corrections | 3/7/2023 | STARR CHEN |
| Plan Check Approved | 3/15/2023 | STARR CHEN |
| Issued | 4/13/2023 | APPLICANT |
| CofO in Progress | 10/25/2023 | OGANES TARAKHCHYAN |
| Permit Finaled | 11/7/2023 | DANIEL ORRANTE |
| CofO Issued | 11/7/2023 | DANIEL ORRANTE |
| Permit Finaled | 11/7/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 10/20/2022 | CATHERINE ADROVER |
| Permit | Cleared | 10/20/2022 | CATHERINE ADROVER |
| Hydrant and Access approval | Cleared | 10/28/2022 | KURT CORRAL |
| Trees in Parkway | Cleared | 11/4/2022 | ADALBERTO VERA |
| Eng Process Fee Ord 176,300 | Cleared | 11/7/2022 | CATHERINE ADROVER |
| Sewer availability | Cleared | 11/7/2022 | CATHERINE ADROVER |
| Low Impact Development | Cleared | 11/23/2022 | DEBORA LEITE |
| Roof/Waste drainage to street | Cleared | 11/29/2022 | CATHERINE ADROVER |
| GPI Written Notices | Cleared | 3/15/2023 | STARR CHEN |
| Grading Pre-Inspection | Cleared | 3/15/2023 | STARR CHEN |
| Green Code | Cleared | 3/15/2023 | Cristina Salazar |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Wang,, Hongyu; Lic. No.: C72679 | 8887 W FALMINGO RD STE 101 LAS VEGAS, NV 89147 |
Inspector Information
| TEMISTOCLES CAAL, (213) 653-1908 | Office Hours: 7:00-8:00 AM MON-FRI |
| JESUS PINEDA, (213) 653-1908 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 4/18/2023 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Excavation/Setback/Form/Re-Bar | 4/21/2023 | Not Ready for Inspection | KEVIN SARGSYAN |
| Footing/Foundation/Slab | 4/21/2023 | Not Ready for Inspection | KEVIN SARGSYAN |
| PLUMBING-Rough | 4/21/2023 | Corrections Issued | KEVIN SARGSYAN |
| Excavation/Setback/Form/Re-Bar | 4/25/2023 | Partial Approval | OGANES TARAKHCHYAN |
| Underground Mechanical | 4/25/2023 | Partial Approval | OGANES TARAKHCHYAN |
| Deputy Drilled-In Anchors | 5/1/2023 | Partial Approval | OGANES TARAKHCHYAN |
| Footing/Foundation/Slab | 5/1/2023 | Approved | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/15/2023 | Partial Approval | OGANES TARAKHCHYAN |
| Sewer | 5/15/2023 | Corrections Issued | OGANES TARAKHCHYAN |
| Sewer | 5/18/2023 | Approved | OGANES TARAKHCHYAN |
| Underground Mechanical | 5/18/2023 | Partial Approval | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/30/2023 | Corrections Issued | OGANES TARAKHCHYAN |
| Deputy Wood Construction | 5/31/2023 | Partial Approval | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/1/2023 | Partial Approval | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/6/2023 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| HVAC-Rough | 6/6/2023 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| HVAC-Rough | 6/7/2023 | Approved | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/9/2023 | Corrections Issued | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/14/2023 | Approved | OGANES TARAKHCHYAN |
| ELECTRICAL-Rough | 6/21/2023 | Approved | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 6/21/2023 | Partial Approval | OGANES TARAKHCHYAN |
| ELECTRICAL-Rough | 6/22/2023 | Approved | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 6/22/2023 | Partial Approval | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 6/27/2023 | Partial Approval | OGANES TARAKHCHYAN |
| Green Building Rough | 6/27/2023 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Verify Sprinkler Sign Off | 6/27/2023 | Approved | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 6/28/2023 | Partial Approval | OGANES TARAKHCHYAN |
| Insulation | 7/3/2023 | Approved | OGANES TARAKHCHYAN |
| Shower Pan | 7/3/2023 | Approved | OGANES TARAKHCHYAN |
| Drywall Nailing | 7/10/2023 | Approved | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 7/10/2023 | Corrections Issued | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 7/12/2023 | Approved | OGANES TARAKHCHYAN |
| SGSOV-Seismic Gas S/O Valve | 9/21/2023 | SGSOV Not Ready | OGANES TARAKHCHYAN |
| Underground Mechanical | 9/25/2023 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| ELECTRICAL-Final | 10/10/2023 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| HVAC-Final | 10/10/2023 | Approved | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 10/11/2023 | Approved | OGANES TARAKHCHYAN |
| ELECTRICAL-Final | 10/11/2023 | Approved | OGANES TARAKHCHYAN |
| Green Building Final | 10/11/2023 | Approved | OGANES TARAKHCHYAN |
| Green Building Rough | 10/11/2023 | Approved | OGANES TARAKHCHYAN |
| HVAC-Final | 10/11/2023 | Approved | OGANES TARAKHCHYAN |
| PLUMBING-Final | 10/11/2023 | Approved | OGANES TARAKHCHYAN |
| SGSOV-Seismic Gas S/O Valve | 10/11/2023 | SGSOV Not Ready | OGANES TARAKHCHYAN |
| Smoke Detectors | 10/11/2023 | Approved | OGANES TARAKHCHYAN |
| Gas Test | 10/12/2023 | Approved | OGANES TARAKHCHYAN |
| PLUMBING-Final | 10/12/2023 | Approved | OGANES TARAKHCHYAN |
| Gas Test | 10/13/2023 | Approved | OGANES TARAKHCHYAN |
| PLUMBING-Final | 10/18/2023 | Approved | OGANES TARAKHCHYAN |
| SGSOV-Seismic Gas S/O Valve | 10/18/2023 | SGSOV Approved | OGANES TARAKHCHYAN |
| Service/Power Release | 10/18/2023 | Approved | OGANES TARAKHCHYAN |
| Final | 10/23/2023 | OK to Issue CofO | OGANES TARAKHCHYAN |